Traffic Engr. | Original | A | 12/4/2007 | JAN | JAN | SS 12-4-07 | | Traffic Engr. | 334252 |
Health Dept. | Original | A | 12/4/2007 | JAN | JAN | LD 12-4-07 | | Health Dept. | 334243 |
City Engr. | Original | A | 12/4/2007 | JAN | JAN | sbk 12-4-07 | | City Engr. | 334225 |
Gas/Elec. Utils | Original | N | 12/4/2007 | JAN | JAN | WD 12-4-07 | | Gas/Elec. Utils | 334241 |
Out to Review | Original | A | 12/4/2007 | ANGELA | ANGELA | OUT TO RAY WITH HAMMERS CONSTRUCTION. | | Out to Review | 334249 |
Finished Bin | Original | / | 12/4/2007 | | SHARON | Location = Finished Bin by SHARON | | Finished Bin | 334237 |
Zoning/Planning | Original | A | 12/4/2007 | SHARON | SHARON | 11/28/07 bad | | Zoning/Planning | 334253 |
Hazmat/High Pile | Original | N | 12/4/2007 | SHARON | SHARON | 12/03/07vc | | Hazmat/High Pile | 334242 |
Fire | Original | A | 12/4/2007 | SHARON | SHARON | 12/03/07vc | | Fire | 334238 |
Out to Review | Original | A | 11/30/2007 | SHELBY | SHELBY | RAY | | Out to Review | 334248 |
Electrical | Original | A | 11/30/2007 | SHELBY | SHELBY | COMPLY 547 NEC | | Electrical | 334234 |
Electrical | Original | / | 11/30/2007 | | SHELBY | Location = Electrical by SHELBY | | Electrical | 334233 |
Construction | Original | A | 11/30/2007 | STEPHEN | STEPHEN | | | Construction | 334228 |
CSU Contract Admin. | Original | A | 11/30/2007 | r.plush | r.plush | HAY BARN RLP 11-29-07 | | CSU Contract Admin. | 334224 |
Out to Review | Original | A | 11/20/2007 | MINDY | MINDY | Ray w/ Hammers | | Out to Review | 334247 |
Plan Coordinator | Original | / | 11/20/2007 | | SHELBY | Location = Plan Coordinator by SHELBY | | Plan Coordinator | 334251 |
Electrical | Original | D | 11/20/2007 | SHELBY | SHELBY | SHOW DETAILS OF HOW DUST IS HANDLED(IS AREA CLASSIFIED?)---SIGN IECC CALCULATION---SHOW BUILDING 104 AND PANEL FB---PROVIDE FEEDER SCHEDULE | | Electrical | 334235 |
Electrical | Original | / | 11/19/2007 | MINDY | MINDY | Given to SHELBY by MINDY | | Electrical | 334232 |
Electrical | Original | / | 11/19/2007 | | MINDY | Location = Electrical by MINDY | | Electrical | 334231 |
Out to Review | Original | A | 11/19/2007 | MINDY | MINDY | Ray w/ Hammers | | Out to Review | 334246 |
Electrical | Original | / | 11/19/2007 | | MINDY | Location = Electrical by MINDY | | Electrical | 334230 |
Plan Coordinator | Original | / | 11/18/2007 | | STEPHEN | Location = Plan Coordinator by STEPHEN | | Plan Coordinator | 334250 |
Construction | Original | D | 11/18/2007 | STEPHEN | STEPHEN | Revise metal building design criteria per RBC302.4.56 and RBC302.4.66 Provide metal building gutter and downspout sizing per RBC306.4.47 Show mezzanine deign loads on S1.1 Provide building and/or building levels (including Mezz.) with a means of egress system per IBC 1001.1 Provide means of egress system continuity per IBC 1003.6 Provide means of egress door(s) per IBC 1008.1 and door operation per IBC 1008.1.8 Provide a buiding cross section thru the Mezz. -- provide 7'-0" clearance per IBC 505.1 | | Construction | 334229 |
Construction | Original | / | 11/16/2007 | MINDY | MINDY | Given to STEPHEN by MINDY | | Construction | 334227 |
Construction | Original | / | 11/16/2007 | | MINDY | Location = Construction by MINDY | | Construction | 334226 |
Out to Review | Original | A | 11/16/2007 | JEANNINE | JEANNINE | Ray w Hammers | | Out to Review | 334245 |
Floodplain | Original | A | 11/16/2007 | JEANNINE | JEANNINE | | | Floodplain | 334240 |
Floodplain | Original | / | 11/16/2007 | | MARLENE | Location = Floodplain by MARLENE | | Floodplain | 334239 |
Enumeration | Original | A | 11/16/2007 | MARLENE | MARLENE | | | Enumeration | 334236 |
Out to Review | Original | A | 11/16/2007 | JAN | JAN | Ray walking addressing | | Out to Review | 334244 |