Plumbing | Original | A | 6/4/2010 | TCRIPPEN | TCRIPPEN | new splice pages | | Plumbing | 460494 |
Scanned/Finished Bin | Original | / | 6/1/2010 | | MINDY | Location = Scanned/Finished Bin by MINDY | | Scanned/Finished Bin | 459785 |
Plan Coordinator | Original | / | 5/26/2010 | | MICHAELA | Location = Plan Coordinator by MICHAEL | | Plan Coordinator | 459122 |
Construction | Original | A | 5/26/2010 | MICHAELA | MICHAELA | | | Construction | 459121 |
Construction | Original | / | 5/20/2010 | REBECCA | REBECCA | Plan Reviewer = MICHAEL by REBECCA | | Construction | 458272 |
Construction | Original | / | 5/19/2010 | MINDY | MINDY | Splice | | Construction | 458260 |
Scanned/Finished Bin | Original | / | 4/1/2010 | | SHARON | Location = Scanned/Finished Bin by SHARON | | Scanned/Finished Bin | 451752 |
Hazmat | Original | A | 4/1/2010 | MINDY | MINDY | 03/31/10 kay | | Hazmat | 451639 |
To Be Scanned Bin | Original | / | 4/1/2010 | | MINDY | Location = To Be Scanned Bin by MINDY | | To Be Scanned Bin | 451638 |
High Pile | Original | N | 4/1/2010 | MINDY | MINDY | 03/15/10 dew | | High Pile | 451637 |
Plan Coordinator | Original | / | 4/1/2010 | | MATTHEW | Location = Plan Coordinator by MATTHEW | | Plan Coordinator | 451630 |
Electrical | Original | A | 4/1/2010 | MATTHEW | MATTHEW | | | Electrical | 451629 |
Hazmat | Original | / | 3/26/2010 | | MINDY | Location = Hazmat by MINDY | | Hazmat | 450809 |
Plan Coordinator | Original | / | 3/26/2010 | | RUSSELL | Location = Plan Coordinator by RUSSELL | | Plan Coordinator | 450769 |
Mechanical | Original | A | 3/26/2010 | RUSSELL | RUSSELL | | | Mechanical | 450768 |
Mechanical | Original | / | 3/26/2010 | MINDY | MINDY | Plan Reviewer = RUSSELL by MINDY | | Mechanical | 450747 |
Mechanical | Original | / | 3/25/2010 | | MINDY | Location = Mechanical by MINDY | | Mechanical | 450718 |
Plan Coordinator | Original | / | 3/25/2010 | | SHELBY | Location = Plan Coordinator by SHELBY | | Plan Coordinator | 450716 |
Electrical | Original | D | 3/25/2010 | SHELBY | SHELBY | Collate IECC calculation (2003)---See previous review comments | | Electrical | 450715 |
Electrical | Original | / | 3/25/2010 | MINDY | MINDY | Plan Reviewer = SHELBY by MINDY | | Electrical | 450535 |
Electrical | Original | / | 3/24/2010 | | NELIDA | Location = Electrical by NELIDA | | Electrical | 450504 |
Resubmittal 2 | Original | / | 3/24/2010 | NELIDA | NELIDA | Resubmittal #2 3/24/10 | | Resubmittal 2 | 450471 |
Out to Review | Original | / | 3/18/2010 | NELIDA | NELIDA | Harry Lindmark 303-472-6832 | | Out to Review | 449664 |
Finished Bin | Original | / | 3/17/2010 | | MINDY | Location = Finished Bin by MINDY | | Finished Bin | 449504 |
Hazmat | Original | D | 3/17/2010 | CSFIRE | CSFIRE | Hazardous materials quantity list still not submitted. See attached comments. | csfirehp | Hazmat | 449471 |
Hazmat | Original | / | 3/15/2010 | | CSFIRE | Location = Hazmat by CSFIRE | csfdit | Hazmat | 448950 |
Fire | Original | A | 3/15/2010 | CSFIRE | CSFIRE | | csfdit | Fire | 448949 |
Fire | Original | / | 3/12/2010 | | CSZONING | Location = Fire by CSZONING | bveltman | Fire | 448697 |
Zoning/Planning | Original | A | 3/12/2010 | CSZONING | CSZONING | Approved for Phase I improvements per AR DPA 96-438-A3MJ09. For CO inspection, phase I is on page 4 of the DP. A second CO will be needed for Phase II, pages 1 & 3 on the DP. | bdiana | Zoning/Planning | 448696 |
Zoning/Planning | Original | / | 3/11/2010 | | MINDY | Location = Zoning/Planning by MINDY | | Zoning/Planning | 448500 |
Plan Coordinator | Original | / | 3/11/2010 | | MATTHEW | Location = Plan Coordinator by MATTHEW | | Plan Coordinator | 448495 |
Electrical | Original | D | 3/11/2010 | MATTHEW | MATTHEW | all corrections need to be addressed and reflected on all appropriate sheets | | Electrical | 448493 |
Electrical | Original | / | 3/10/2010 | RUSSELL | RUSSELL | Plan Reviewer = SHELBY by RUSSELL | | Electrical | 448369 |
Electrical | Original | / | 3/10/2010 | | RUSSELL | Location = Electrical by RUSSELL | | Electrical | 448368 |
Mechanical | Original | D | 3/10/2010 | RUSSELL | RUSSELL | Sheet M112 & M601, AHU-IDF-1 shown shceduled at 2100 cfm, air balance shcedule shows unit at 1400 cfm and diffusers total `1955 cfm, which one is suppose to be correct ?, sheet M112, flag note 4 indicates to see detail, what detail and what sheet is it located on, can't seem to find detail, also VAV -26 shown on this sheet and sheet M122, isn't shceduled with existing VAV's scheduled on sheet M602, still some ductwork on sheet M112 missing sizes as indicated, | | Mechanical | 448367 |
Mechanical | Original | / | 3/9/2010 | MINDY | MINDY | Plan Reviewer = RUSSELL by MINDY | | Mechanical | 448174 |
Mechanical | Original | / | 3/9/2010 | | MINDY | Location = Mechanical by MINDY | | Mechanical | 448171 |
Plan Coordinator | Original | / | 3/9/2010 | | MICHAELA | Location = Plan Coordinator by MICHAEL | | Plan Coordinator | 448169 |
Construction | Original | A | 3/9/2010 | MICHAELA | MICHAELA | Splice | | Construction | 448168 |
Construction | Original | / | 3/8/2010 | | MINDY | Location = Construction by MINDY | | Construction | 448067 |
Resubmittal 1 | Original | / | 3/8/2010 | MINDY | MINDY | Resubmittal #1 Some Construction pages changed also, so resubmittal to Construction as well as other departments | | Resubmittal 1 | 448066 |
Out to Review | Original | / | 2/12/2010 | MINDY | MINDY | Checked out from Fire - Harry Lindmark | | Out to Review | 445400 |
Hazmat | Original | / | 2/11/2010 | | CSFIRE | Location = Hazmat by CSFIRE | csfdit | Hazmat | 445186 |
Fire | Original | D | 2/11/2010 | CSFIRE | CSFIRE | REFER TO ATTACHED PLAN REVIEW REPORT FOR DISAPPROVED ITEMS. | csfdit | Fire | 445185 |
Fire | Original | / | 2/8/2010 | | CSZONING | Location = Fire by CSZONING | bdiana | Fire | 444863 |
Zoning/Planning | Original | D | 2/8/2010 | CSZONING | CSZONING | Provide a copy of the stamped, approved development plan. | bdiana | Zoning/Planning | 444862 |
Zoning/Planning | Original | / | 2/5/2010 | | MINDY | Location = Zoning/Planning by MINDY | | Zoning/Planning | 444527 |
Plan Coordinator | Original | / | 2/5/2010 | | SHELBY | Location = Plan Coordinator by SHELBY | | Plan Coordinator | 444503 |
Electrical | Original | D | 2/5/2010 | SHELBY | SHELBY | Panels HLB and LA require main breakers. Collate IECC calculations. SCCR of panels DP-2A and DP-1A insufficient for SCA. Show method of compliance with 702.6 NEC for panels HLB and LA. Show conductor size and type between battery assemblies and each UPS on one line. Clarify power characteristics(Transformers TDSB-5,and THLB are delta/wye transformers but service is 480 volt 4 wire) | | Electrical | 444502 |
Electrical | Original | / | 2/3/2010 | MINDY | MINDY | Plan Reviewer = SHELBY by MINDY | | Electrical | 444108 |
Electrical | Original | / | 2/2/2010 | | TCRIPPEN | Location = Electrical by TCRIPPEN | | Electrical | 444024 |
Plumbing | Original | A | 2/2/2010 | TCRIPPEN | TCRIPPEN | | | Plumbing | 444023 |
Plumbing | Original | / | 2/2/2010 | MINDY | MINDY | Plan Reviewer = TCRIPPEN by MINDY | | Plumbing | 444017 |
Plumbing | Original | / | 2/2/2010 | RUSSELL | RUSSELL | Plan Reviewer = TCRIPPEN by RUSSELL | | Plumbing | 443983 |
Plumbing | Original | / | 2/2/2010 | | RUSSELL | Location = Plumbing by RUSSELL | | Plumbing | 443982 |
Mechanical | Original | D | 2/2/2010 | RUSSELL | RUSSELL | Battery room ventilation not met per '03 IMC section 502.4 & IFC section 609, return air from batter y rrom, no, provide in scheduling operation of unit and those on standby, per section 603.13 balancing dampers required at all take offs throughout the facility, schedule all louvered openings, add note on plans: provide balance report to mechanical inspector at time of heat final inspection,, size all O.A. plenums and indicate on drawings location of plenums, at floor at ceiling or somewhere in between, some cfms don't match up between schedule and diffusers on plans, need to schedule AHU-IDF-1, only show on air balance schedule, some duct sizes are missing as indicated on plans, plus more, see plans for additional comments including the BA sheets | | Mechanical | 443981 |
Mechanical | Original | / | 2/2/2010 | MICHAELA | MICHAELA | Plan Reviewer = RUSSELL by MICHAEL | | Mechanical | 443864 |
Construction | Original | A | 2/2/2010 | MICHAELA | MICHAELA | Change of occupancy require compliance with ANSI 117.1 and IBC sect 1210 for all toilet rooms. Open hole inspections are required at all new foundation work | | Construction | 443861 |
Construction | Original | / | 1/29/2010 | MINDY | MINDY | Plan Reviewer = MICHAEL by MINDY | | Construction | 443707 |
Construction | Original | / | 1/29/2010 | | MINDY | Location = Construction by MINDY | | Construction | 443664 |
Plan Coordinator | Original | / | 1/29/2010 | | JEANNINE | Location = Plan Coordinator by JEANNINE | | Plan Coordinator | 443635 |
Enumeration | Original | A | 1/29/2010 | JEANNINE | JEANNINE | 1 tenant building -- no secondary addresses given. | | Enumeration | 443634 |
Floodplain | Original | N | 1/29/2010 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain | | Floodplain | 443521 |