Electrical | Original | A | 4/27/2011 | SHELBY | SHELBY | Terry Paulson | | Electrical | 504452 |
Out to Review | Original | / | 4/12/2011 | NELIDA | NELIDA | Teri 491-5711 | | Out to Review | 502177 |
Hazmat | Original | D | 4/12/2011 | CSFIRE | CSFIRE | SUBMITTED BY: YEAGER, KAY A | csfirehm | Hazmat | 502163 |
Mechanical | Original | A | 3/24/2011 | RUSSELL | RUSSELL | | | Mechanical | 499497 |
Out to Review | Original | / | 3/16/2011 | JAY | JAY | customer walking | | Out to Review | 498286 |
Construction | Original | A | 3/16/2011 | JAY | JAY | Cut sheets included. OK | | Construction | 498285 |
Fire | Original | / | 3/16/2011 | | CSZONING | Location = Fire by CSZONING | Dtortorice | Fire | 498192 |
CO Springs DRE | Original | A | 3/16/2011 | CSZONING | CSZONING | Interiror Remodel - remodel service bays into paint booth, autobody and fender repair. Per S. Tuck and R. Oconnor, the repair and paint function is accessory to the auto dealership and requires no additional action. | Dtortorice | CO Springs DRE | 498191 |
Zoning/Planning | Original | / | 3/11/2011 | | JANE | Location = Zoning/Planning by JANE | | Zoning/Planning | 497583 |
Plan Coordinator | Original | / | 3/11/2011 | | RUSSELL | Location = Plan Coordinator by RUSSELL | | Plan Coordinator | 497572 |
Mechanical | Original | D | 3/11/2011 | RUSSELL | RUSSELL | Need MAU-3 scheduled on plans, coordinate exhaust cfms for EF-17, is it 3480 per schedule or 5760 per plan ?, see other notes regarding exhaust and makeup air on plan, see note regarding 1 1/2" gas serving paint booth with length in question, also need total connected load to 3"-2# and length from most remote gas pressure regulator to meter to verify load, length and size per '03 IFGC | | Mechanical | 497570 |
Mechanical | Original | / | 3/10/2011 | RUSSELL | RUSSELL | In Current Review by RUSSELL | | Mechanical | 497519 |
Mechanical | Original | / | 3/8/2011 | | MINDY | Location = Mechanical by MINDY | | Mechanical | 497144 |
Out to Review | Original | / | 3/8/2011 | SHELBY | SHELBY | Terry Paulson | | Out to Review | 497119 |
Electrical | Original | D | 3/8/2011 | SHELBY | SHELBY | 1. Verify peak demand meter. 2. Provide detail of activity and configuration of the "work station". 3. Clearly show paint booth openings. 4. Clearly show all paint booth disconnects. 5. Show all electrical equipment in a hazardous area. | | Electrical | 497118 |
Monday Plancheck | Original | / | 3/8/2011 | | KIM | Location = Monday Plancheck by KIM | | Monday Plancheck | 497055 |
Electrical | Original | / | 3/7/2011 | | MINDY | Location = Electrical by MINDY | | Electrical | 496813 |
Plan Coordinator | Original | / | 3/7/2011 | | TCRIPPEN | Location = Plan Coordinator by TCRIPPEN | | Plan Coordinator | 496806 |
Plumbing | Original | N | 3/7/2011 | TCRIPPEN | TCRIPPEN | no plumbing work | | Plumbing | 496805 |
Plumbing | Original | / | 3/7/2011 | | JANE | Location = Plumbing by JANE | | Plumbing | 496795 |
Electrical | Original | / | 3/7/2011 | TCRIPPEN | TCRIPPEN | In Current Review by TCRIPPEN | | Electrical | 496794 |
Electrical | Original | / | 3/4/2011 | | JANE | Location = Electrical by JANE | | Electrical | 496734 |
Plan Coordinator | Original | / | 3/4/2011 | | MICHAELA | Location = Plan Coordinator by MICHAEL | | Plan Coordinator | 496725 |
Construction | Original | D | 3/4/2011 | MICHAELA | MICHAELA | Provide cut sheets for U.L. listed paint booth Walk-through OK | | Construction | 496724 |
Construction | Original | / | 3/4/2011 | MICHAELA | MICHAELA | In Current Review by MICHAEL | | Construction | 496712 |
Construction | Original | / | 3/3/2011 | | NELIDA | Location = Construction by NELIDA | | Construction | 496524 |
Out to Review | Original | / | 3/3/2011 | JEANNINE | JEANNINE | | | Out to Review | 496383 |
Floodplain | Original | N | 3/3/2011 | JEANNINE | JEANNINE | | | Floodplain | 496384 |
Enumeration | Original | A | 3/3/2011 | JEANNINE | JEANNINE | Single tenant building. | | Enumeration | 496382 |