Electrical | Electrical 6-27-17 | A | 6/27/2017 | BERTHA | BERTHA | Revised to indicate Mid Clamp grounding. | | Electrical | 973283 |
Health Dept. | Original | N | 3/9/2017 | HEALTHDEPT | HEALTHDEPT | Not applicable. ABrannon (719)352-1842 | abrannon | Health Dept. | 942692 |
City Engr. | Original | N | 3/8/2017 | PMORRIS | PMORRIS | | | City Engr. | 942110 |
Out to Review | Original | / | 3/7/2017 | SHELLEY | SHELLEY | zach 310-9518 | | Out to Review | 941954 |
Hazmat | Original | N | 3/7/2017 | SHELLEY | SHELLEY | per CLT 3/7/17 | | Hazmat | 941953 |
Construction | Original | A | 3/7/2017 | SHELLEY | SHELLEY | | | Construction | 941951 |
Hazmat | Original | / | 3/2/2017 | | MINDY | Location = Hazmat by MINDY | | Hazmat | 940458 |
Plan Coordinator | Original | / | 3/2/2017 | | MICHAELA | Location = Plan Coordinator by MICHAELA | | Plan Coordinator | 940449 |
Construction | Original | D | 3/2/2017 | MICHAELA | MICHAELA | Indicate hardware required to resist truss uplift Indicate connection requirements at piggyback trusses Add basement occupant load for fixture count Walk-through OK (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 940448 |
Construction | Original | / | 3/2/2017 | MICHAELA | MICHAELA | In Current Review by MICHAELA | | Construction | 940443 |
Construction | Original | / | 3/1/2017 | | NELIDA | Location = Construction by NELIDA | | Construction | 940428 |
Resubmittal 1 | Original | / | 3/1/2017 | NELIDA | NELIDA | Resubmittal #1 3/1/17 | | Resubmittal 1 | 940427 |
Gas/Elec. Utils | Original | A | 3/1/2017 | CSUREVIEW | CSUREVIEW | Gas meter relocation completed on 1/17/17 per Mary Hoaglund on 3/1/17. HSF | hfranson | Gas/Elec. Utils | 940422 |
CO Springs Fire | Original | A | 3/1/2017 | CSFIRE | CSFIRE | Submitted By: Peterson, Roland Thomas (see full review) | csfdit | CO Springs Fire | 940359 |
Out to Review | Original | / | 2/24/2017 | RDCUSER | RDCUSER | Out to applicant | | Out to Review | 939290 |
CO Springs DRE | Original | A | 2/24/2017 | RDCUSER | RDCUSER | MRB per RBT - Per CPC DP 97-146-A2MJ16 (see full review) | | CO Springs DRE | 939289 |
Plumbing | Original | A | 2/24/2017 | TCRIPPEN | TCRIPPEN | okay,per section 403.1.1 fixture calculation | | Plumbing | 939283 |
Out to Review | Original | / | 2/24/2017 | BERTHA | BERTHA | 3060W | | Out to Review | 939256 |
Electrical | Original | A | 2/24/2017 | BERTHA | BERTHA | | | Electrical | 939255 |
Mechanical | Original | A | 2/24/2017 | DALEH | DALEH | re-approved changes | | Mechanical | 939220 |
Plan Coordinator | Original | / | 2/22/2017 | | RDCUSER | Location = Plan Coordinator by RDCUSER | | Plan Coordinator | 938530 |
Out to Review | Original | / | 2/22/2017 | RDCUSER | RDCUSER | Laurie checked out plan | | Out to Review | 938521 |
Zoning/Planning | Original | / | 2/22/2017 | | MINDY | Location = Zoning/Planning by MINDY | | Zoning/Planning | 938442 |
Plan Coordinator | Original | / | 2/22/2017 | | TCRIPPEN | Location = Plan Coordinator by TCRIPPEN | | Plan Coordinator | 938397 |
Plumbing | Original | D | 2/22/2017 | TCRIPPEN | TCRIPPEN | your added load of 40 occupants will require 2 men`s and 2 women`s toilets, (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Plumbing | 938396 |
Plumbing | Original | / | 2/22/2017 | TCRIPPEN | TCRIPPEN | In Current Review by TCRIPPEN | | Plumbing | 938337 |
Plumbing | Original | / | 2/17/2017 | | MINDY | Location = Plumbing by MINDY | | Plumbing | 937653 |
Plan Coordinator | Original | / | 2/16/2017 | | JUSTINC | Location = Plan Coordinator by JUSTINC | | Plan Coordinator | 937627 |
Mechanical | Original | A | 2/16/2017 | JUSTINC | JUSTINC | | | Mechanical | 937626 |
Mechanical | Original | / | 2/16/2017 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Mechanical | 937577 |
Mechanical | Original | / | 2/16/2017 | | MINDY | Location = Mechanical by MINDY | | Mechanical | 937299 |
Plan Coordinator | Original | / | 2/15/2017 | | SHELBY | Location = Plan Coordinator by SHELBY | | Plan Coordinator | 937273 |
Electrical | Original | D | 2/15/2017 | SHELBY | SHELBY | 1. Provide all specifications for PV installation pasted on full size sheets ( please provide only the specifications required on the alternative energy checklist http://www.pprbd.org/plancheck/Alternative_Energy_2016.pdf ). 2. Feeder for new panel requires an equipment ground. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Electrical | 937272 |
Electrical | Original | / | 2/7/2017 | | JESSICAM | Location = Electrical by JESSICAM | | Electrical | 934896 |
Plan Coordinator | Original | / | 2/6/2017 | | MICHAELA | Location = Plan Coordinator by MICHAELA | | Plan Coordinator | 934864 |
Construction | Original | D | 2/6/2017 | MICHAELA | MICHAELA | Locate solar array on structural drawings Clarify uplift hardware Clarify attachment of 'P' trusses Add basement occupancy and occupant load - add to total for fixture count No walk-through (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 934863 |
Construction | Original | / | 2/6/2017 | MICHAELA | MICHAELA | In Current Review by MICHAELA | | Construction | 934584 |
Construction | Original | / | 2/2/2017 | | JANE | Location = Construction by JANE | | Construction | 933938 |
Enumeration | Original | A | 1/31/2017 | BRENT | BRENT | | | Enumeration | 933443 |
Floodplain | Original | N | 1/31/2017 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain | | Floodplain | 933425 |