Plumbing | Splice 3/26/18 | A | 3/26/2018 | TCRIPPEN | TCRIPPEN | new splice page relocated roof drains added heat tape | | Plumbing | 1050436 |
Electrical | Splice 3/26/18 | A | 3/26/2018 | SHELBY | SHELBY | For heat tape | | Electrical | 1050415 |
Out to Review | Splice 3/26/18 | / | 3/26/2018 | BECKYA | BECKYA | | | Out to Review | 1050404 |
Plumbing | Splice 2/8/18 | A | 2/9/2018 | TCRIPPEN | TCRIPPEN | okay relocate water meter add back flow device. | | Plumbing | 1036324 |
Water Division | Splice 2/8/18 | A | 2/9/2018 | CSUREVIEW | CSUREVIEW | | mlwilliams | Water Division | 1036306 |
Electrical | Splice 2/8/18 | A | 2/8/2018 | BERTHA | BERTHA | Revised OCPD and conductor for Panel C. | | Electrical | 1036032 |
Out to Review | Splice 2/8/18 | / | 2/8/2018 | BECKYA | BECKYA | | | Out to Review | 1036014 |
Construction | Splice 01/17/18 | A | 1/23/2018 | DANM | DANM | Modified parapet detail; roofing to go up back of parapet; various structural revisions | | Construction | 1031044 |
Construction | Splice 01/17/18 | D | 1/23/2018 | SHELLEY | SHELLEY | Per design professional, sheet 1 is only installation instructions, ok to omit. Need stamped detail for parapet modification. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1030947 |
Out to Review | Splice 01/17/18 | / | 1/19/2018 | MINDY | MINDY | Bruce Judd 801 690 4661 | | Out to Review | 1030317 |
Finished Bin | Splice 01/17/18 | / | 1/18/2018 | | SCANNING | Location = Finished Bin by SCANNING | | Finished Bin | 1029492 |
Plan Coordinator | Splice 01/17/18 | / | 1/18/2018 | | SHELLEY | Location = Plan Coordinator by SHELLEY | | Plan Coordinator | 1029475 |
Construction | Splice 01/17/18 | D | 1/18/2018 | SHELLEY | SHELLEY | Missing Redbuilt plan sheet 1. Walk ok. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1029474 |
Construction | Splice 01/17/18 | / | 1/18/2018 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Construction | 1029473 |
Construction | Splice 01/17/18 | / | 1/17/2018 | | JANE | Location = Construction by JANE | | Construction | 1029126 |
Electrical | Original | A | 9/21/2017 | SHELBY | SHELBY | | | Electrical | 997459 |
Health Dept. | Original | A | 9/18/2017 | HEALTHDEPT | HEALTHDEPT | Approved in plan review. A pre-operational inspection will be required before final approval for opening is granted. Jodi Zimmerman 719-433-3685 | Jzimmerman | Health Dept. | 996487 |
Mechanical | Original | A | 9/18/2017 | DALEH | DALEH | | | Mechanical | 996199 |
Resubmittal 3 | Original | / | 9/15/2017 | BECKYA | BECKYA | Resubmittal #3 | | Resubmittal 3 | 995745 |
Mechanical | Original | D | 8/29/2017 | DALEH | DALEH | Engineer still needs to responded to all previous comments (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 990919 |
Electrical | Original | D | 8/28/2017 | SHELBY | SHELBY | Please address previous review comments 3 and 3. Please call for consultation 719 327 2974 (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Electrical | 990598 |
Plumbing | Original | A | 8/28/2017 | TCRIPPEN | TCRIPPEN | okay | | Plumbing | 990500 |
Electronic Plan | Original | / | 8/28/2017 | TCRIPPEN | TCRIPPEN | In Current Review by TCRIPPEN | | Electronic Plan | 990479 |
Health Dept. | Original | D | 8/25/2017 | HEALTHDEPT | HEALTHDEPT | Plan review required. Please contact the health department at (719) 578-3199 option 3. RNielsen 575-8965 | rnielsen | Health Dept. | 990245 |
Hazmat | Original | A | 8/25/2017 | CSFIRE | CSFIRE | Plans approved. Please read approval comments. Inspection required. (see full review) | smanning | Hazmat | 990236 |
Construction | Original | A | 8/25/2017 | SHELLEY | SHELLEY | | | Construction | 990176 |
Enumeration | Original | A | 8/24/2017 | AMY | AMY | TRASH ENCLOSURE 1622 S NEVADA AVE | | Enumeration | 989861 |
Electronic Plan | Original | / | 8/24/2017 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 989841 |
Resubmittal 2 | Original | / | 8/24/2017 | BECKYA | BECKYA | Resubmittal #2 | | Resubmittal 2 | 989618 |
CSU Contract Admin. | Original | A | 8/23/2017 | CSUAPPSPRM | CSUAPPSPRM | Applicable development charges and fees paid 8/23/2017, please see paid utility receipt. MKL | mkluke | CSU Contract Admin. | 989546 |
Enumeration | Original | D | 8/17/2017 | AMY | AMY | TRASH ENCLOSURE IS OVER 7FT 1'-ADDRESS WILL BE ASSIGNED (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Enumeration | 987530 |
CSU Contract Admin. | Original | D | 8/9/2017 | CSUAPPSPRM | CSUAPPSPRM | Commercial water meter sizing form approved; however, requires payment of development charges and fees. MKL | mkluke | CSU Contract Admin. | 984961 |
City Engr | Original | A | 8/8/2017 | PMORRIS | PMORRIS | | | City Engr | 984776 |
Plumbing | Original | D | 8/8/2017 | TCRIPPEN | TCRIPPEN | provide an water pipe size analysis data on plans rest okay (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Plumbing | 984682 |
Electronic Plan | Original | / | 8/8/2017 | TCRIPPEN | TCRIPPEN | In Current Review by TCRIPPEN | | Electronic Plan | 984597 |
Electrical | Original | D | 8/8/2017 | SHELBY | SHELBY | Please comply with previous review comments 1, 2, and 3. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Electrical | 984534 |
Hazmat | Original | D | 8/7/2017 | CSFIRE | CSFIRE | Plans disapproved. Plans require CO2 detection and ventilation system as supply is greater than 100 lbs per Admin Ruling 2017-1; neither is provided. Hazmat operation permit application requires to be filled out and attached: https://csfd.coloradosprings.gov/sites/csfd.coloradosprings.gov/files/IFC%202009%20Hazardous%20Activity%20Permit_0416.pdf (see full review) | smanning | Hazmat | 984423 |
Health Dept. | Original | D | 8/7/2017 | HEALTHDEPT | HEALTHDEPT | Plan review required. Please contact the health department at (719) 578-3199 option 3. AnkitP (719) 578-3278 | Aparikh | Health Dept. | 984334 |
CO Springs Fire | Original | A | 8/7/2017 | CSFIRE | CSFIRE | Submitted By: Taylor II, Wyman L (see full review) | csfdit | CO Springs Fire | 984248 |
Mechanical | Original | D | 8/7/2017 | DALEH | DALEH | engineer to respond to all comments on plans even if it does not warrant a change to the drawing,,,some comments are for clarification purposes. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 984215 |
Construction | Original | D | 8/4/2017 | JAY | JAY | Projection from north wall exceeds limitations of 705.2. See sheet A2.2. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 983932 |
Resubmittal 1 | Original | / | 8/4/2017 | BECKYA | BECKYA | Resubmittal #1 | | Resubmittal 1 | 983793 |
City Engr | Original | D | 6/19/2017 | PMORRIS | PMORRIS | Include a copy of the Water Resources Engineer Division approved Grading & Erosion Control Plan. | | City Engr | 970369 |
CSU Contract Admin. | Original | D | 6/19/2017 | CSUAPPSPRM | CSUAPPSPRM | Commercial water meter sizing form approved 4/18/2017 - requires payment of applicable development charges and fees - MKL 668-7467 | mkluke | CSU Contract Admin. | 970214 |
CO Springs DRE | Original | A | 6/16/2017 | RTEFERTILLER | RTEFERTILLER | Construction set is consistent with approved development plan (AR DP 16-00414). However, a minor amendment to the development plan will be required prior to CO to update the Nevada Ave. streetscape design to be consistent with the S. Nevada Streetscape Design Guidelines and to update the Chick-Fil-A building elevations to add awnings to the south facing facade and remove them from the north facing facade. (see full review) | | CO Springs DRE | 970060 |
Plumbing | Original | D | 6/16/2017 | TCRIPPEN | TCRIPPEN | Gas piping and related items to be on the M-pages per our web site provide GPM at each roof drain for sizing (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Plumbing | 969813 |
Mechanical | Original | D | 6/15/2017 | DALEH | DALEH | see plans for all red lines return red lines (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 969519 |
Health Dept. | Original | D | 6/15/2017 | HEALTHDEPT | HEALTHDEPT | Plan review required. Please contact the health department at (719) 578-3199 option 3. Rebecca Nielsen 575-8965 | rnielsen | Health Dept. | 969510 |
Electronic Plan | Original | / | 6/15/2017 | DALEH | DALEH | In Current Review by DALEH | | Electronic Plan | 969396 |
Water Division | Original | A | 6/14/2017 | CSUREVIEW | CSUREVIEW | Approved USP included in plan set for PPRBD plan no. C-90949 (Permit No. K91342). HSF | hfranson | Water Division | 969207 |
Waste Water Div | Original | A | 6/14/2017 | CSUREVIEW | CSUREVIEW | Approved USP included in plan set for PPRBD plan no. C-90949 (Permit No. K91342). HSF | hfranson | Waste Water Div | 969206 |
Hazmat | Original | D | 6/14/2017 | CSFIRE | CSFIRE | | wtaylor | Hazmat | 969154 |
CO Springs Fire | Original | D | 6/14/2017 | CSFIRE | CSFIRE | Submitted By: Taylor II, Wyman L (see full review) | csfdit | CO Springs Fire | 969153 |
Electronic Plan | Original | / | 6/14/2017 | TCRIPPEN | TCRIPPEN | In Current Review by TCRIPPEN | | Electronic Plan | 969054 |
Electrical | Original | D | 6/14/2017 | SHELBY | SHELBY | 1. Show SCA at all electrical equipment. 2. Indicate AIC rating of lowest rated breaker in each panel. 3. Clearly specify series rating or fully rated for each panel. If series rating the panels provide manufacturers information listing series rated devices. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Electrical | 969007 |
Gas/Elec. Utils | Original | A | 6/14/2017 | CSUREVIEW | CSUREVIEW | CSU Field Engineer to determine final meter/service/transformer locations. Please submit the Electric Load Data Form, and the Application for Gas Service Line Approval. The forms can be found at: https://www.csu.org/Pages/development-files-forms.aspx Contact DeeDee Brook at 719-668-4510 with any gas/electric questions. HSF | hfranson | Gas/Elec. Utils | 968953 |
Zoning/Planning | Original | / | 6/14/2017 | RTEFERTILLER | RTEFERTILLER | In Current Review by RTEFERTILLER | | Zoning/Planning | 968934 |
Construction | Original | D | 6/13/2017 | SHELLEY | SHELLEY | Revise code study form to reflect no mixed occupancies; address fire separation distance issue with north wall to include rated assembly, opening limitations, and eave projections; foundation plan must reference soils report provided; see plans for all comments;. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 968845 |
Electronic Plan | Original | / | 6/13/2017 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Electronic Plan | 968670 |
Enumeration | Original | A | 6/13/2017 | BRENT | BRENT | | | Enumeration | 968657 |
Electronic Plan | Original | / | 6/13/2017 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 968652 |
Floodplain | Original | A | 6/13/2017 | KEITH | KEITH | FP 17025 | | Floodplain | 968614 |