Fire | Original | / | 9/26/2019 | AMY | AMY | In Current Review by AMY | | Fire | 1239838 |
Construction | Splice 06/13/19 | A | 6/13/2019 | DANM | DANM | Framing revisions for non-balloon framed wall + support for roof overhang | | Construction | 1202080 |
Out to Review | Splice 06/13/19 | / | 6/13/2019 | BECKYA | BECKYA | | | Out to Review | 1202039 |
Construction | Splice 04/15/19 | A | 4/15/2019 | LBENNETT | LBENNETT | Revised framing to eliminate steel column | | Construction | 1178796 |
Out to Review | Splice 04/15/19 | / | 4/15/2019 | JANE | JANE | Susan walking | | Out to Review | 1178760 |
CO Springs Fire | Original | A | 11/21/2018 | CSFIRE | CSFIRE | | rpeterson | CO Springs Fire | 1133283 |
Fire | Original | / | 11/20/2018 | | SDALSING | Location = Fire by SDALSING | | Fire | 1132873 |
CO Springs DRE | Original | A | 11/20/2018 | SDALSING | SDALSING | APPROVED: HS CRITERIA MET. APPROVED GEOHAZARD REPORT AND GECP ON FILE.
New SFR - All DP Standards are met. Any new addition, patio cover, deck, etc., not shown on this site plan will need to go through a new review process through City Planning. (see full review) | | CO Springs DRE | 1132872 |
Zoning/Planning | Original | / | 11/15/2018 | SDALSING | SDALSING | In Current Review by SDALSING | | Zoning/Planning | 1131402 |
Zoning/Planning | Original | / | 11/14/2018 | | SCANNING | Location = Zoning/Planning by SCANNING | | Zoning/Planning | 1130661 |
Plan Coordinator | Original | / | 11/14/2018 | | JUSTINC | Location = Plan Coordinator by JUSTINC | | Plan Coordinator | 1130604 |
Mechanical | Original | A | 11/14/2018 | JUSTINC | JUSTINC | | | Mechanical | 1130603 |
Mechanical | Original | / | 11/14/2018 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Mechanical | 1130591 |
Mechanical | Original | / | 11/14/2018 | | NELIDA | Location = Mechanical by NELIDA | | Mechanical | 1130465 |
Resubmittal 2 | Original | / | 11/14/2018 | NELIDA | NELIDA | Resubmittal #2 11/14/18 | | Resubmittal 2 | 1130464 |
Out to Review | Original | / | 11/6/2018 | RITA | RITA | Susan | | Out to Review | 1127667 |
CO Springs Fire | Original | D | 11/5/2018 | CSFIRE | CSFIRE | See CSFD Plan Review Comments | wtaylor | CO Springs Fire | 1127542 |
Fire | Original | / | 11/1/2018 | | SDALSING | Location = Fire by SDALSING | | Fire | 1126396 |
CO Springs DRE | Original | D | 11/1/2018 | SDALSING | SDALSING | SITE PLAN OKAY. WAITING ON APPROVED GECP THROUGH STORMWATER ENG. (see full review) | | CO Springs DRE | 1126395 |
Zoning/Planning | Original | / | 10/30/2018 | | SCANNING | Location = Zoning/Planning by SCANNING | | Zoning/Planning | 1125499 |
Plan Coordinator | Original | / | 10/30/2018 | | JUSTINC | Location = Plan Coordinator by JUSTINC | | Plan Coordinator | 1125384 |
Mechanical | Original | D | 10/30/2018 | JUSTINC | JUSTINC | MECHANICAL REVIEW INCOMPLETE
It appears that the comments from 1st review were addressed however with the provided duct design on 8 1/2" x 11" paper the design is too small to review. I did try to enlarge to the minimum submittal size of 11" x 17" however even this size is too small for review. Please provide duct design on full size sheet for review
Will require full mechanical review with next submittal. NO WALK
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1125381 |
Mechanical | Original | / | 10/24/2018 | | SCANNING | Location = Mechanical by SCANNING | | Mechanical | 1123551 |
Plan Coordinator | Original | / | 10/24/2018 | | BPHILLIPS | Location = Plan Coordinator by BPHILLIPS | | Plan Coordinator | 1123526 |
Construction | Original | A | 10/24/2018 | BPHILLIPS | BPHILLIPS | | | Construction | 1123525 |
Construction | Original | / | 10/24/2018 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Construction | 1123348 |
Construction | Original | / | 10/24/2018 | | GITA | Location = Construction by GITA | | Construction | 1123258 |
Resubmittal 1 | Original | / | 10/24/2018 | GITA | GITA | Resubmittal #1 | | Resubmittal 1 | 1123257 |
Out to Review | Original | / | 10/23/2018 | SDALSING | SDALSING | SUSAN | | Out to Review | 1123002 |
CO Springs DRE | Original | D | 10/23/2018 | SDALSING | SDALSING | DENIED:
NO APPROVED GECP. PLANNING CANNOT SIGN OFF UNTIL GECP HAS BEEN APPROVED. (see full review) | | CO Springs DRE | 1123001 |
Zoning/Planning | Original | / | 9/25/2018 | | SDALSING | Location = Zoning/Planning by SDALSING | | Zoning/Planning | 1113718 |
CO Springs DRE | Original | D | 9/25/2018 | SDALSING | SDALSING | Site plan is missing several minor items from the hillside site plan checklist. Please see the checklist that has been attached to the site plan. Plans are being routed to Stormwater Eng for their review. (see full review) | | CO Springs DRE | 1113717 |
Zoning/Planning | Original | / | 9/19/2018 | | SCANNING | Location = Zoning/Planning by SCANNING | | Zoning/Planning | 1111647 |
Plan Coordinator | Original | / | 9/19/2018 | | JUSTINC | Location = Plan Coordinator by JUSTINC | | Plan Coordinator | 1111621 |
Mechanical | Original | D | 9/19/2018 | JUSTINC | JUSTINC | MECHANICAL REVIEW INCOMPLETE
Basement level office on duct design shows 4" optional run? There is no options or alternates allowed in site specific permits. This room is also "Habitable space" which requires heat. Revise Basement office does not meet 4% natural ventilation. No O.S.A has been indicated. How ventilating?
REVIEW STOPPED NO WALK
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1111619 |
Mechanical | Original | / | 9/19/2018 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Mechanical | 1111521 |
Mechanical | Original | / | 9/18/2018 | | SCANNING | Location = Mechanical by SCANNING | | Mechanical | 1111381 |
Plan Coordinator | Original | / | 9/18/2018 | | BPHILLIPS | Location = Plan Coordinator by BPHILLIPS | | Plan Coordinator | 1111355 |
Construction | Original | D | 9/18/2018 | BPHILLIPS | BPHILLIPS | Revise truss profile sheets to reflect code cycle under which plan was submitted, or submit Alternate Materials & Methods request form to use 2015 IRC- designed trusses. Preliminary review only performed on roof framing plan pending resolution. No walk. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1111354 |
Construction | Original | / | 9/18/2018 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Construction | 1111103 |
Construction | Original | / | 9/17/2018 | | SCANNING | Location = Construction by SCANNING | | Construction | 1110552 |
Plan Coordinator | Original | / | 9/17/2018 | | AMY | Location = Plan Coordinator by AMY | | Plan Coordinator | 1110501 |
Enumeration | Original | A | 9/17/2018 | AMY | AMY | | | Enumeration | 1110499 |
Fire | Original | / | 9/13/2018 | RBD GIS | RBD GIS | Parcel 7315109019 is within the Wildland Urban Interface (WUI). Fire Department Review is required. | | Fire | 1109670 |
Floodplain | Original | N | 9/13/2018 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 7315109019) | | Floodplain | 1109671 |