Mechanical | Splice 08/06/19 | A | 8/21/2019 | DALEH | DALEH | | | Mechanical | 1226448 |
Resubmittal 4 | Splice 08/06/19 | / | 8/20/2019 | BECKYA | BECKYA | Resubmittal #4 | | Resubmittal 4 | 1226033 |
Health Dept. | Splice 08/06/19 | N | 8/20/2019 | HEALTHDEPT | HEALTHDEPT | Not applicable. | KCohen | Health Dept. | 1225895 |
Mechanical | Splice 08/06/19 | D | 8/20/2019 | DALEH | DALEH | revise mechanical drawings and calcs to reflect new bedroom (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1225772 |
Construction | Splice 08/06/19 | A | 8/19/2019 | DANM | DANM | Add bathroom and closet to unfinished basement and convert Finished Storage to a Bedroom | | Construction | 1225550 |
Electronic Plan | Splice 08/06/19 | / | 8/19/2019 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1225527 |
Resubmittal 3 | Splice 08/06/19 | / | 8/19/2019 | BECKYA | BECKYA | Resubmittal #3 | | Resubmittal 3 | 1225333 |
Mechanical | Splice 08/06/19 | D | 8/19/2019 | DALEH | DALEH | need clarification on bedroom or not if bedroom revise documents (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1225288 |
Construction | Splice 08/06/19 | D | 8/19/2019 | DANM | DANM | Upon further review, mechanical drawing is showing that the adjacent finished storage space is a future bedroom - clarify if finished storage space will be a bedroom and note as such
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1225283 |
Resubmittal 2 | Splice 08/06/19 | / | 8/19/2019 | BECKYA | BECKYA | Resubmittal #2 | | Resubmittal 2 | 1225223 |
Mechanical | Splice 08/06/19 | D | 8/16/2019 | DALEH | DALEH | It appears that part of this splice is to revise the entire set of Mechanical documents If this is the case please cloud all changes and only provide the sheets that are effected. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1225037 |
Mechanical | Splice 08/06/19 | A | 8/15/2019 | DALEH | DALEH | bath exhaust fan | | Mechanical | 1224334 |
Construction | Splice 08/06/19 | A | 8/14/2019 | DANM | DANM | IECC and full basement drawing added per Mechanical request | | Construction | 1224014 |
Electronic Plan | Splice 08/06/19 | / | 8/14/2019 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1224007 |
Resubmittal 1 | Splice 08/06/19 | / | 8/14/2019 | BECKYA | BECKYA | Resubmittal #1 | | Resubmittal 1 | 1223998 |
Mechanical | Splice 08/06/19 | D | 8/7/2019 | DALEH | DALEH | provide revised mechanical documents and revisions need to be made to the full set of drawings do not provide a partial image of just the bathroom on an 8 1/2 x11 (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1221204 |
Construction | Splice 08/06/19 | A | 8/6/2019 | DANM | DANM | Finish unfinished space into a bathroom and closet making adjacent Finished Storage now a Bedroom | | Construction | 1220895 |
Electronic Plan | Splice 08/06/19 | / | 8/6/2019 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1220882 |
County Zoning | Original | A | 1/4/2019 | DSDARCHULETA | DSDARCHULETA | | | County Zoning | 1146920 |
Resubmittal 1 | Original | / | 1/3/2019 | BECKYA | BECKYA | Resubmittal #1 | | Resubmittal 1 | 1146743 |
County Zoning | Original | D | 12/7/2018 | DSDARCHULETA | DSDARCHULETA | DENIED - COMPLETE EXCEPT FOR ACC APPROVAL LETTER | | County Zoning | 1138887 |
Mechanical | Original | A | 12/6/2018 | DALEH | DALEH | | | Mechanical | 1138544 |
County Zoning | Original | / | 12/4/2018 | DSDARCHULETA | DSDARCHULETA | Complete except for ACC letter | | County Zoning | 1137711 |
Zoning/Planning | Original | / | 12/3/2018 | DSDARCHULETA | DSDARCHULETA | In Current Review by DSDARCHULETA | | Zoning/Planning | 1137129 |
Construction | Original | A | 12/3/2018 | DANM | DANM | | | Construction | 1136990 |
Electronic Plan | Original | / | 12/3/2018 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1136914 |
Enumeration | Original | A | 11/30/2018 | BRENT | BRENT | | | Enumeration | 1136609 |
Electronic Plan | Original | / | 11/30/2018 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 1136596 |
Floodplain | Original | N | 11/27/2018 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6127003010) | | Floodplain | 1134666 |