Canceled Plans | Original | / | 5/11/2024 | ADMIN | ADMIN | Electronic Plan automatically cancelled due to inactivity. | | Canceled Plans | 2002202 |
Electrical | Original | D | 2/6/2023 | RICHG | RICHG | 1. Comply with previous review comments. Quantity on one line does not match utility letter.
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Electrical | 1799669 |
Construction | Original | A | 2/6/2023 | CHRISTINEH | CHRISTINEH | | | Construction | 1799149 |
Submittal 5 | Original | / | 2/3/2023 | SIERRAC | SIERRAC | Submittal #5 | | Submittal 5 | 1798662 |
Electrical | Original | D | 1/27/2023 | RICHG | RICHG | 1. Quantity on one line does not match site plan and utility approval letter.
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Electrical | 1796205 |
Electronic Plan | Original | / | 1/27/2023 | RICHG | RICHG | In Current Review by RICHG | | Electronic Plan | 1796127 |
Construction | Original | D | 1/26/2023 | CHRISTINEH | CHRISTINEH | SEE ALL PREVIOUS REVIEW COMMENTS - WIND SPEED STILL NEEDS TO BE DESIGNED FOR 130 MPH PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1795553 |
Submittal 4 | Original | / | 1/26/2023 | KALLISTAJ | KALLISTAJ | Submittal #4 | | Submittal 4 | 1795495 |
Electrical | Original | D | 1/18/2023 | RICHG | RICHG | 1. Number of modules don't match utility approval.
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Electrical | 1792351 |
Electronic Plan | Original | / | 1/18/2023 | RICHG | RICHG | In Current Review by RICHG | | Electronic Plan | 1792346 |
Construction | Original | D | 1/18/2023 | CHRISTINEH | CHRISTINEH | STILL NEEDS TO BE 130 MPH
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1792116 |
Submittal 3 | Original | / | 1/17/2023 | KALLISTAJ | KALLISTAJ | Submittal #3 | | Submittal 3 | 1791713 |
Electrical | Original | A | 1/6/2023 | RICHG | RICHG | | | Electrical | 1788480 |
Electronic Plan | Original | / | 1/6/2023 | RICHG | RICHG | In Current Review by RICHG | | Electronic Plan | 1788476 |
Construction | Original | D | 1/5/2023 | CHRISTINEH | CHRISTINEH | Corrections not made: Still needs to be 130 mph PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1787871 |
Submittal 2 | Original | / | 1/5/2023 | KALLISTAJ | KALLISTAJ | Submittal #2 | | Submittal 2 | 1787829 |
Electrical | Original | D | 12/28/2022 | RICHG | RICHG | 1. Number of modules don't match utility approval.
2.Remove parallel neutral in service conductor.
Provide Labeling on future solar submittal include labeling flow chart.
See labeling added to this plan set.
Note: January 1, 2023 comply with 230.46 NEC
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Electrical | 1785923 |
Electronic Plan | Original | / | 12/28/2022 | RICHG | RICHG | In Current Review by RICHG | | Electronic Plan | 1785921 |
Construction | Original | D | 12/22/2022 | CHRISTINEH | CHRISTINEH | Needs to be 130 mph
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1784664 |
Electronic Plan | Original | / | 12/22/2022 | CHRISTINEH | CHRISTINEH | In Current Review by CHRISTINEH | | Electronic Plan | 1784648 |
Zoning | Original | N | 12/21/2022 | SYSTEM | SYSTEM | Zoning review is not required for roof-mounted PV solar projects in Colorado Springs. Flush roof-mounted solar panels and/or PV angled roof-mounted panels not to exceed residential zoning height requirements. The City of Colorado Springs does not review covenants or requirements of homeowners' associations. Property owners are responsible for reviewing and complying with any covenants or other private requirements that may apply to their property. | | Zoning | 1784083 |
Floodplain | Original | N | 12/21/2022 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 7427202004) | | Floodplain | 1784082 |