CO Springs DRE | Original | A | 2/2/2024 | KSCHOTT | KSCHOTT | approval for in ground pool at rear of single family home. Applicant understands that the limit of disturbance boundary must be in place at all times throughout construction and that random hillside inspections will occur. If the LOD is not in place and/or if stockpiling does not occur in accordance with this approved plan, further reviews will be required and code enforcement may incur. (see full review) | | CO Springs DRE | 1959187 |
Stormwater | Original | A | 1/31/2024 | EWANG | EWANG | | | Stormwater | 1957785 |
City Engr | Original | N | 1/31/2024 | PMORRIS | PMORRIS | The geologic hazard waiver is with the permit for the residential house (R174960) | | City Engr | 1957597 |
Zoning/Planning | Original | / | 1/30/2024 | KSCHOTT | KSCHOTT | In Current Review by KSCHOTT | | Zoning/Planning | 1957267 |
Construction | Original | A | 1/30/2024 | CGIECK | CGIECK | OK | | Construction | 1957087 |
Submittal 2 | Original | / | 1/26/2024 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 1955991 |
City Engr | Original | D | 9/21/2023 | JDAGNILLO | JDAGNILLO | Upload a copy of the approved geological hazard report into the electronic building permit set. | | City Engr | 1902622 |
Stormwater | Original | D | 9/20/2023 | EWANG | EWANG | Include the following on Hillside Site Plan: 1. Limits of disturbance (LOD) 2. Existing and proposed contour lines with labels 3. Stockpile within LOD 4. Stormwater flow arrows 5. PE signature and stamp | | Stormwater | 1902234 |
CO Springs DRE | Original | D | 9/20/2023 | KSCHOTT | KSCHOTT | This lot is located within the HS overlay, therefore must have a HS site plan stamped by PE. Show existing grade lines and proposed grade lines, limit of disturbance boundary, drainage arrows and stockpile location
kerri.schott@coloradosprings.gov (see full review) | | CO Springs DRE | 1902180 |
Zoning/Planning | Original | / | 9/19/2023 | KSCHOTT | KSCHOTT | In Current Review by KSCHOTT | | Zoning/Planning | 1901528 |
Construction | Original | D | 9/19/2023 | CGIECK | CGIECK | Please review progress set 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1901208 |
Electronic Plan | Original | / | 9/18/2023 | CGIECK | CGIECK | In Current Review by CGIECK | | Electronic Plan | 1901092 |
Energy | Original | N | 9/6/2023 | SYSTEM | SYSTEM | Energy Department review not required under 2023 PPRBC when IECC is N/A | | Energy | 1896292 |
Stormwater | Original | / | 9/6/2023 | SYSTEM | SYSTEM | Parcel 7326302025 is within the Hillside Overlay (HS). Stormwater Review is required. | | Stormwater | 1896290 |
Floodplain | Original | N | 9/6/2023 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 7326302025) | | Floodplain | 1896291 |