Enumeration | Original | A | 4/9/2024 | AMY | AMY | CABINS 21 & 22 | | Enumeration | 1986292 |
Electronic Plan | Original | / | 4/9/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 1986159 |
Energy | Original | A | 3/6/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1971787 |
Mechanical | Original | A | 3/6/2024 | DALEH | DALEH | | | Mechanical | 1971786 |
| Original | / | 3/5/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 1970946 |
| Original | / | 3/4/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 1970767 |
Submittal 3 | Original | / | 3/4/2024 | QUINTONW | QUINTONW | Submittal #3 | | Submittal 3 | 1970766 |
Construction | Original | N | 2/13/2024 | DANM | DANM | Upon further review, no construction in scope of work | | Construction | 1963194 |
Energy | Original | D | 2/13/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1963174 |
Mechanical | Original | D | 2/13/2024 | DALEH | DALEH | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 1963173 |
Construction | Original | A | 2/13/2024 | DANM | DANM | | | Construction | 1963160 |
Electronic Plan | Original | / | 2/13/2024 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1963106 |
Submittal 2 | Original | / | 2/13/2024 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 1962970 |
Energy | Original | D | 1/5/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1947928 |
Mechanical | Original | D | 1/5/2024 | DALEH | DALEH | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 1947927 |
Construction | Original | D | 1/5/2024 | DANM | DANM | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1947870 |
Electronic Plan | Original | / | 1/5/2024 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1947838 |
Floodplain | Original | A | 1/2/2024 | KEITH | KEITH | | | Floodplain | 1945997 |
Energy | Original | / | 1/2/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1945858 |
Floodplain | Original | / | 1/2/2024 | RBD GIS | RBD GIS | Autogenerated Review: Parcel intersects with 100 Year Floodplain. (Parcel: 7403324067) | | Floodplain | 1945857 |