Energy | Original | A | 3/20/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1976976 |
Construction | Original | A | 3/20/2024 | SHELLEY | SHELLEY | | | Construction | 1976975 |
| Original | / | 3/20/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 1976736 |
| Original | / | 3/20/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 1976686 |
Submittal 5 | Original | / | 3/20/2024 | QUINTONW | QUINTONW | Submittal #5 | | Submittal 5 | 1976685 |
WP Zoning | Original | A | 3/18/2024 | DBURGESS | DBURGESS | ZDP approved on 2/27/2024 & Development Fees paid on 3/18/2024 | | WP Zoning | 1975391 |
Energy | Original | D | 3/12/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1974512 |
Mechanical | Original | A | 3/12/2024 | TCRIPPEN | TCRIPPEN | Approved | | Mechanical | 1974511 |
Construction | Original | D | 3/12/2024 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1974412 |
| Original | / | 3/12/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 1974346 |
| Original | / | 3/12/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 1974036 |
Submittal 4 | Original | / | 3/12/2024 | QUINTONW | QUINTONW | Submittal #4 | | Submittal 4 | 1974035 |
WP Zoning | Original | D | 3/11/2024 | TCRIPPEN | TCRIPPEN | disapproved so revised plans can be re uploaded. | | WP Zoning | 1973661 |
Energy | Original | D | 3/6/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1971518 |
Mechanical | Original | D | 3/6/2024 | TCRIPPEN | TCRIPPEN | Disapproved Approved IECC required first. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 1971517 |
Construction | Original | D | 3/5/2024 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1971316 |
| Original | / | 3/4/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 1970435 |
| Original | / | 3/4/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 1970433 |
Submittal 3 | Original | / | 3/4/2024 | QUINTONW | QUINTONW | Submittal #3 | | Submittal 3 | 1970432 |
WP Zoning | Original | D | 2/20/2024 | DBURGESS | DBURGESS | Pending ZDP approval. Disapproved at this time to release plan set to address PPRBD comments. | | WP Zoning | 1964941 |
Energy | Original | D | 2/8/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1961357 |
Mechanical | Original | D | 2/8/2024 | TCRIPPEN | TCRIPPEN | An approved IECC is required first, 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 1961356 |
Plumbing | Original | A | 2/7/2024 | SHANEN | SHANEN | | | Plumbing | 1960884 |
Construction | Original | D | 2/7/2024 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1960871 |
Submittal 2 | Original | / | 2/7/2024 | BRIANNAM | BRIANNAM | Submittal #2 | | Submittal 2 | 1960556 |
WP Zoning | Original | D | 2/1/2024 | DBURGESS | DBURGESS | Pending ZDP Approval. Disapproved at this time to release plan set to address PPRBD comments. | | WP Zoning | 1958208 |
WP Fire (CSFD Commercial) | Original | N | 2/1/2024 | DBURGESS | DBURGESS | N/A per Fire Chief Tyler Lambert via email to D. Burgess on 1/30/2024: "No issues from FD with the driveway submitted on site plan." | | WP Fire (CSFD Commercial) | 1958207 |
Energy | Original | D | 1/30/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1957323 |
Mechanical | Original | D | 1/30/2024 | JUSTINC | JUSTINC | Missing required manual J sheets - Component construction, AED, Load short form, project summary, etc.. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 1957322 |
Electrical | Original | A | 1/30/2024 | DANIELG | DANIELG | | | Electrical | 1957265 |
Electronic Plan | Original | / | 1/30/2024 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1957262 |
Plumbing | Original | D | 1/30/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 1957042 |
Construction | Original | D | 1/30/2024 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1957005 |
Electronic Plan | Original | / | 1/30/2024 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Electronic Plan | 1956956 |
WP Floodplain | Original | N | 1/29/2024 | DBURGESS | DBURGESS | Verified not in a floodplain | | WP Floodplain | 1956717 |
WP Enumeration | Original | A | 1/29/2024 | DBURGESS | DBURGESS | Address, owner, parcel number & Tax number verified | | WP Enumeration | 1956716 |
Energy | Original | / | 1/25/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1955150 |