Electrical | Original | D | 11/15/2024 | RICHG | RICHG | Comply with 250.122 (G) NEC 2023 * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2085815 |
Construction | Original | A | 11/14/2024 | SHELLEY | SHELLEY | | | Construction | 2085449 |
Submittal 2 | Original | / | 11/14/2024 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 2085418 |
Electrical | Original | D | 11/5/2024 | RICHG | RICHG | Provide all manufacture specification sheets see link below
https://www.pprbd.org/File/ByAlias/AlternativeEnergyResidential
Comply with 250.122 (G) NEC 2023.
1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 2081754 |
Electronic Plan | Original | / | 11/5/2024 | RICHG | RICHG | In Current Review by RICHG | | Electronic Plan | 2081658 |
Construction | Original | D | 10/25/2024 | SHELLEY | SHELLEY | Incorrect snow load, above 7000' 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2077554 |
Electronic Plan | Original | / | 10/25/2024 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Electronic Plan | 2077551 |
Energy | Original | N | 10/24/2024 | SYSTEM | SYSTEM | Energy Department review not required under 2023 PPRBC when IECC is N/A | | Energy | 2076653 |
Zoning | Original | N | 10/24/2024 | SYSTEM | SYSTEM | Zoning review is not required for roof-mounted PV solar projects in El Paso County. | | Zoning | 2076650 |
Floodplain | Original | N | 10/24/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 5215002036) | | Floodplain | 2076648 |