Construction | Original | A | 11/4/2024 | DOUGC | DOUGC | | | Construction | 2080950 |
Out to Review | Original | / | 11/4/2024 | JANE | JANE | Shelly 7193326645 | | Out to Review | 2080837 |
Finished Bin (Main) | Original | / | 11/1/2024 | | SCANNING | Location = Finished Bin (Main) by SCANNING | | Finished Bin (Main) | 2080800 |
City Engr | Original | A | 11/1/2024 | JDAGNILLO | JDAGNILLO | No geological hazard report or waiver will be required.
plans routed to RBD | | City Engr | 2080782 |
City Engr (SERT) | Original | / | 10/29/2024 | | MAMBUUL | Location = City Engr (SERT) by MAMBUUL | | City Engr (SERT) | 2078977 |
CO Springs DRE | Original | D | 10/29/2024 | MAMBUUL | MAMBUUL | 1. Proposed square footage of garage addition(355), in addition to existing garage space on lot(1,352) exceeds the total square footage allowed for lot of 1,650 square feet per UDC 7.3.304 subsection C. Recommend pre-application meeting at coloradosprings.gov/preapp 2. Please correct setbacks on site plan, setbacks appeared to have been scaled. (see full review) | | CO Springs DRE | 2078976 |
Zoning/Planning | Original | / | 10/29/2024 | MAMBUUL | MAMBUUL | In Current Review by MAMBUUL | | Zoning/Planning | 2078884 |
Zoning/Planning | Original | / | 10/29/2024 | | SCANNING | Location = Zoning/Planning by SCANNING | | Zoning/Planning | 2078841 |
Plan Coordinator (North) | Original | / | 10/29/2024 | | RICHG | Location = Plan Coordinator (North) by RICHG | | Plan Coordinator (North) | 2078474 |
Plumbing | Original | N | 10/29/2024 | RICHG | RICHG | No plumbing in scope | | Plumbing | 2078473 |
Mechanical | Original | N | 10/29/2024 | RICHG | RICHG | No mechanical in scope | | Mechanical | 2078472 |
Electrical | Original | A | 10/29/2024 | RICHG | RICHG | | | Electrical | 2078470 |
Electrical (North) | Original | / | 10/28/2024 | | CHRISTINEH | Location = Electrical (North) by CHRISTINEH | | Electrical (North) | 2078142 |
Construction | Original | D | 10/28/2024 | CHRISTINEH | CHRISTINEH | Trusses designed for 40 psf - Structure designed for 30 psf - Need to match / Label trusses on roof framing plan 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2078141 |
Energy | Original | N | 10/28/2024 | SYSTEM | SYSTEM | Energy Department review not required under 2023 PPRBC when IECC is N/A | | Energy | 2078140 |
Construction (North) | Original | / | 10/28/2024 | CHRISTINEH | CHRISTINEH | In Current Review by CHRISTINEH | | Construction (North) | 2078139 |
Construction (North) | Original | / | 10/28/2024 | | JACKIEP | Location = Construction (North) by JACKIEP | | Construction (North) | 2078091 |
Energy | Original | / | 10/28/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2078089 |
Floodplain | Original | N | 10/28/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6308019019) | | Floodplain | 2078088 |