City Engr | Original | A | 3/3/2025 | HVO | HVO | EDRD has no comments on this item. | | City Engr | 2126277 |
CO Springs DRE | Original | D | 2/28/2025 | MAMBUUL | MAMBUUL | 1. Need to upload final irrigation plan set to permit, city file number LAPN-24-0048 2. Need to upload recorded plat to permit. 3. Need to pay PLDO fees per approval letter, DEPN-24-0073, contact DREplanninginfo@coloradosprings.gov to pay fees. 4. Need to provide financial assurances for public and private improvements prior to building permit approval. | | CO Springs DRE | 2125957 |
CSU Water | Original | D | 2/26/2025 | CSUREVIEW | CSUREVIEW | Note on P111 stating "Unit A & B meter location may be located on the outside of structure...." not reflected on approved USP or DP. Only Units 1 through 36 labeled. Please clarify or modify plumbing note. Refer to 2023 Colorado Springs Utilities WaterLESS details B4-1 through B4-8 and select the correct meter detail to include on the plumbing plans after approval of the Commercial Water Meter Sizing Form. Also refer to details B4-16 through B4-22 and select an appropriate meter clearance detail to include on the plumbing plans.MDA | malcuran | CSU Water | 2125330 |
CSU Waste Water | Original | D | 2/26/2025 | CSUREVIEW | CSUREVIEW | Note on P111 stating "Unit A & B meter location may be located on the outside of structure...." not reflected on approved USP or DP. Only Units 1 through 36 labeled. Please clarify or modify plumbing note. Refer to 2023 Colorado Springs Utilities WaterLESS details B4-1 through B4-8 and select the correct meter detail to include on the plumbing plans after approval of the Commercial Water Meter Sizing Form. Also refer to details B4-16 through B4-22 and select an appropriate meter clearance detail to include on the plumbing plans.MDA | malcuran | CSU Waste Water | 2125329 |
Energy | Original | A | 2/26/2025 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2124926 |
Plumbing | Original | A | 2/26/2025 | SHANEN | SHANEN | | | Plumbing | 2124925 |
Zoning/Planning | Original | / | 2/26/2025 | MAMBUUL | MAMBUUL | In Current Review by MAMBUUL | | Zoning/Planning | 2124919 |
Construction | Original | A | 2/26/2025 | BPHILLIPS | BPHILLIPS | 30# roof snow - no tile option 2 options (no charge) | | Construction | 2124911 |
Mechanical | Original | A | 2/26/2025 | TCRIPPEN | TCRIPPEN | Approved | | Mechanical | 2124891 |
Electrical | Original | A | 2/26/2025 | RICHG | RICHG | | | Electrical | 2124860 |
Electronic Plan | Original | / | 2/26/2025 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2124853 |
Enumeration | Original | A | 2/25/2025 | BECKYA | BECKYA | 1 plan 5 permits | | Enumeration | 2124726 |
Electronic Plan | Original | / | 2/25/2025 | BECKYA | BECKYA | In Current Review by BECKYA | | Electronic Plan | 2124694 |
Floodplain | Original | N | 2/25/2025 | KEITH | KEITH | | | Floodplain | 2124675 |
Submittal 3 | Original | / | 2/25/2025 | JAY | JAY | Submittal #3: Revised from Master to Duplex - 1 plan Multiple permits | | Submittal 3 | 2124654 |
Electronic Plan | Original | / | 2/25/2025 | BECKYA | BECKYA | In Current Review by BECKYA | | Electronic Plan | 2124643 |
Energy | Original | D | 2/25/2025 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2124407 |
Electrical | Original | A | 2/25/2025 | RICHG | RICHG | | | Electrical | 2124406 |
Electronic Plan | Original | / | 2/25/2025 | RICHG | RICHG | In Current Review by RICHG | | Electronic Plan | 2124404 |
Construction | Original | D | 2/24/2025 | BPHILLIPS | BPHILLIPS | Provide 1-hr rated assembly for walls serving as supporting construction for 1-hr floor/ ceiling assembly. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2123923 |
Electronic Plan | Original | / | 2/24/2025 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2123920 |
Energy | Original | / | 2/21/2025 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2123541 |
Plumbing | Original | A | 2/21/2025 | SHANEN | SHANEN | | | Plumbing | 2123388 |
Submittal 2 | Original | / | 2/21/2025 | BRIANNAM | BRIANNAM | Submittal #2 | | Submittal 2 | 2123365 |
Energy | Original | D | 2/20/2025 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2122818 |
Electrical | Original | D | 2/20/2025 | RICHG | RICHG | SHOW LOCATION OF EMERGENCY DISCONNECT.
COMPLY WITH 240.24 (D)
COMPLY WITH R404.3 IECC 2021 EXTERIOR LIGHTING
COMPLY WITH R404.2 IECC 2021 INTERIOR LIGHTING
* Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2122817 |
Electronic Plan | Original | / | 2/20/2025 | RICHG | RICHG | In Current Review by RICHG | | Electronic Plan | 2122780 |
Mechanical | Original | A | 2/19/2025 | TCRIPPEN | TCRIPPEN | Approved | | Mechanical | 2122286 |
Construction | Original | D | 2/13/2025 | BPHILLIPS | BPHILLIPS | Fire protection, truss labels. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2120512 |
Electronic Plan | Original | / | 2/13/2025 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2120447 |
Plumbing | Original | D | 2/12/2025 | SHANEN | SHANEN | P111: Show the water meter location. Reference 2021 IPC and/or 2021 IRC. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Plumbing | 2119849 |
Plumbing | Original | / | 2/11/2025 | WEBSITE | WEBSITE | Overtime Authorized for Plumbing by JENNIFER COOPER | jennifercooper | Plumbing | 2119800 |
Electrical | Original | / | 2/11/2025 | WEBSITE | WEBSITE | Overtime Authorized for Electrical by JENNIFER COOPER | jennifercooper | Electrical | 2119799 |
Mechanical | Original | / | 2/11/2025 | WEBSITE | WEBSITE | Overtime Authorized for Mechanical by JENNIFER COOPER | jennifercooper | Mechanical | 2119798 |
Construction | Original | / | 2/11/2025 | WEBSITE | WEBSITE | Overtime Authorized for Construction by JENNIFER COOPER | jennifercooper | Construction | 2119797 |
Energy | Original | / | 2/10/2025 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2119239 |