CO Springs DRE | Original | D | 8/20/2025 | SSADLER | SSADLER | Architectural plans show that this is a tiny home. The structural plans show a shed. This appears to be a conversion to an ADU. Please provide the foundation plans.
These plans have reached the maximum allotted plan reviews, and a re-review fee has been assessed. Fees must be paid prior to further reviews. To pay fees for permit review please follow the link provided. https://aca-prod.accela.com/COSPRINGS/Default.aspx
Click on “Building” tab and enter record number BLDREV-25-00859 or enter required information in fields provided. | | CO Springs DRE | 2199758 |
Zoning/Planning | Original | / | 8/18/2025 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2198572 |
Mechanical | Original | A | 8/18/2025 | DALEH | DALEH | Unconditioned Approval for bath fan | | Mechanical | 2198500 |
Construction | Original | D | 8/18/2025 | SHELLEY | SHELLEY | Still need structural plans. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2198440 |
| Original | / | 8/15/2025 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2198024 |
| Original | / | 8/14/2025 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2197804 |
Submittal 4 | Original | / | 8/14/2025 | QUINTONW | QUINTONW | Submittal #4 | | Submittal 4 | 2197803 |
CO Springs DRE | Original | D | 8/6/2025 | SSADLER | SSADLER | Previous comments not addressed. | | CO Springs DRE | 2194161 |
Zoning/Planning | Original | / | 8/1/2025 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2192560 |
Mechanical | Original | D | 8/1/2025 | DALEH | DALEH | Waiting on construction plan review Provide mechanical documents as required * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2192452 |
Construction | Original | D | 8/1/2025 | SHELLEY | SHELLEY | Required items still not addressed. CORRECT ALL NECESSARY ITEMS PRIOR TO RESUBMITTAL. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2192449 |
| Original | / | 8/1/2025 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2192414 |
| Original | / | 8/1/2025 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2192360 |
Submittal 3 | Original | / | 8/1/2025 | QUINTONW | QUINTONW | Submittal #3 | | Submittal 3 | 2192359 |
CO Springs DRE | Original | D | 8/1/2025 | SSADLER | SSADLER | Provide engineered foundation plans. All ADU's must be on an engineered foundation. Upload the required notarized affidavit | | CO Springs DRE | 2192257 |
Zoning/Planning | Original | / | 7/29/2025 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2190810 |
Mechanical | Original | D | 7/29/2025 | DALEH | DALEH | Waiting on construction plan review Provide mechanical documents as required * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2190797 |
Construction | Original | D | 7/29/2025 | SHELLEY | SHELLEY | Most previous comments not addressed. See plan. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2190772 |
Submittal 2 | Original | / | 7/29/2025 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 2190690 |
CO Springs DRE | Original | D | 6/17/2025 | SSADLER | SSADLER | Upload a scaled site plan showing setback, easements, and property lines making sure that the existing and proposed structures are to scale. The one that is upload is not to scale. Upload the required affidavit for the ADU. You will need to pick up and pay for the placard to post in the yard for 14 days | | CO Springs DRE | 2172870 |
Zoning/Planning | Original | / | 6/11/2025 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2170353 |
Mechanical | Original | D | 6/11/2025 | DALEH | DALEH | Waiting on building plan review comments * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2170082 |
Construction | Original | D | 6/11/2025 | SHELLEY | SHELLEY | Several clarifications needed - see plans. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2170068 |
Electronic Plan | Original | / | 6/11/2025 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Electronic Plan | 2170064 |
Energy | Original | N | 6/6/2025 | SYSTEM | SYSTEM | Energy Department review not required under 2023 PPRBC when IECC is N/A | | Energy | 2168340 |
Floodplain | Original | N | 6/6/2025 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6311204024) | | Floodplain | 2168339 |