Construction | Original | A | 8/20/2007 | RICH | RICH | approved added beam at second floor support , spliced | | Construction | 288737 |
Out to Review | Original | A | 5/31/2007 | MINDY | MINDY | Scott Harvey 528-1557 | | Out to Review | 288750 |
Scanned/Finished Bin | Original | / | 5/31/2007 | | SHARON | Location = Scanned/Finished Bin by SHARON | | Scanned/Finished Bin | 288754 |
To Be Scanned Bin | Original | / | 5/31/2007 | | SHELLEY | Location = To Be Scanned Bin by SHELLEY | | To Be Scanned Bin | 288755 |
Plan Coordinator | Original | / | 5/30/2007 | | RUSSELL | Location = Plan Coordinator by RUSSELL | | Plan Coordinator | 288753 |
Mechanical | Original | A | 5/30/2007 | RUSSELL | RUSSELL | | | Mechanical | 288746 |
Mechanical | Original | / | 5/30/2007 | SHELLEY | SHELLEY | Given to RUSSELL by SHELLEY | | Mechanical | 288745 |
Mechanical | Original | / | 5/30/2007 | | SHELLEY | Location = Mechanical by SHELLEY | | Mechanical | 288744 |
Plan Coordinator | Original | / | 5/29/2007 | | RONW | Location = Plan Coordinator by RONW | | Plan Coordinator | 288752 |
Construction | Original | A | 5/29/2007 | RONW | RONW | Revised 5/29/07 | | Construction | 288736 |
Construction | Original | / | 5/29/2007 | SHELLEY | SHELLEY | Given to RONW by SHELLEY | | Construction | 288735 |
Construction | Original | / | 5/24/2007 | | SHELLEY | Location = Construction by SHELLEY | | Construction | 288734 |
Construction | Original | / | 5/24/2007 | SHELLEY | SHELLEY | 2nd resubmittal | | Construction | 288733 |
Out to Review | Original | A | 5/22/2007 | RONW | RONW | Mike Delmonico = 278-0344 | | Out to Review | 288749 |
Construction | Original | D | 5/21/2007 | RONW | RONW | See greenline corrections needed. | | Construction | 288739 |
Construction | Original | / | 5/18/2007 | SHELLEY | SHELLEY | Given to RONW by SHELLEY | | Construction | 288732 |
Construction | Original | / | 5/16/2007 | | ANGELA | Location = Construction by ANGELA | | Construction | 288731 |
Mechanical | Original | / | 5/16/2007 | ANGELA | ANGELA | revised for construction and mechanical. | | Mechanical | 288743 |
Construction | Original | / | 5/16/2007 | ANGELA | ANGELA | | | Construction | 288730 |
Out to Review | Original | A | 5/11/2007 | MINDY | MINDY | Mike Delmonico 495-7113 | | Out to Review | 288748 |
Finished Bin | Original | / | 5/10/2007 | | SHELLEY | Location = Finished Bin by SHELLEY | | Finished Bin | 288740 |
Mechanical | Original | D | 5/10/2007 | TCRIPPEN | TCRIPPEN | 1-show an detailed mech room , with furnace location , vent path , and required floor and elevated if need be 2-provide new heat loss calculations to match new res check , state furnace size only one not more than 30% over size 3-need an approved res check from construction | | Mechanical | 288747 |
Mechanical | Original | / | 5/10/2007 | SHELLEY | SHELLEY | Given to TCRIPPEN by SHELLEY | | Mechanical | 288742 |
Mechanical | Original | / | 5/7/2007 | | SHELLEY | Location = Mechanical by SHELLEY | | Mechanical | 288741 |
Plan Coordinator | Original | / | 5/7/2007 | | RICH | Location = Plan Coordinator by RICH | | Plan Coordinator | 288751 |
Construction | Original | D | 5/7/2007 | RICH | RICH | detached mono poured garage not shown on site plan, appears that h/o may be converting mono poured garage tp heated living space with 2nd floor , need additional deails, provide full buiiding layout of existing residence , other corrections, see pprbd.org for plan submittal policies, no walk thru, rich | | Construction | 288738 |
Construction | Original | / | 5/4/2007 | SHELLEY | SHELLEY | Given to RICH by SHELLEY | | Construction | 288729 |
Construction | Original | / | 4/12/2007 | | SHELLEY | Location = Construction by SHELLEY | | Construction | 288728 |
Zoning/Planning | Original | A | 4/12/2007 | SHELLEY | SHELLEY | 4/2/07 - lh | | Zoning/Planning | 288756 |