Construction | Original | A | 9/18/2012 | SHELLEY | SHELLEY | | | Construction | 586927 |
CO Springs Fire | Original | A | 9/17/2012 | CSFIRE | CSFIRE | (see full review) | csfdit | CO Springs Fire | 586765 |
Construction | Original | D | 9/17/2012 | MICHAELA | MICHAELA | Truss has been replaced; still need emergency escape window in basement. Walk o.k. | | Construction | 586740 |
Mechanical | Original | A | 9/17/2012 | DALEH | DALEH | | | Mechanical | 586716 |
Out to Review | Original | / | 9/17/2012 | KIM | KIM | KEITHN 473-4735 | | Out to Review | 586709 |
Finished Bin | Original | / | 9/13/2012 | | MINDY | Location = Finished Bin by MINDY | | Finished Bin | 586205 |
Plan Coordinator | Original | / | 9/13/2012 | | RUSSELL | Location = Plan Coordinator by RUSSELL | | Plan Coordinator | 586190 |
Mechanical | Original | D | 9/13/2012 | RUSSELL | RUSSELL | If building back the same house duct design is not required, only heat loss calculations and iecc, however, since it's provided, don't know if it's the same house, so duct design reviewed, furnace and coil numbers don't match between plans submitted and the heat loss calculation sheets, it appears the plan numbers are incorrect, also furnace sizing shown on sheet 2 of the plan submittal doesn't match the heat loss calculations. is hi-efficiency furnace vent and c.a. pvc vents to be routed out rim jiost or up through roof in same chase as the water heater vent ? water heat will be a separate vent since it's a "B" vent up. | | Mechanical | 586189 |
Mechanical | Original | / | 9/13/2012 | RUSSELL | RUSSELL | In Current Review by RUSSELL | | Mechanical | 586166 |
Mechanical | Original | / | 9/12/2012 | | JANE | Location = Mechanical by JANE | | Mechanical | 585726 |
Plan Coordinator | Original | / | 9/12/2012 | | SHELLEY | Location = Plan Coordinator by SHELLEY | | Plan Coordinator | 585722 |
Construction | Original | D | 9/12/2012 | SHELLEY | SHELLEY | unfinished basement over 500 sf required emergency escape and rescue opening; AE truss not designed for exposure; see plans; walk ok. | | Construction | 585721 |
Construction | Original | / | 9/12/2012 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Construction | 585714 |
Construction | Original | / | 9/10/2012 | | JANE | Location = Construction by JANE | | Construction | 585357 |
Scanned/Finished Bin | Original | / | 9/10/2012 | | JEANNINE | Location = Scanned/Finished Bin by JEANNINE | | Scanned/Finished Bin | 585352 |
Enumeration | Original | A | 9/10/2012 | JEANNINE | JEANNINE | | | Enumeration | 585351 |
CO Springs DRE | Original | A | 9/10/2012 | KIM | KIM | 9/4/12 JBG | | CO Springs DRE | 585348 |
Floodplain | Original | N | 9/10/2012 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain | | Floodplain | 585345 |