GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 06/02/2011 | | MIKE | MIKE | | B= | C | 4158101 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 06/01/2011 | Need access to SKIF Room, Inspect hardware operation on rear exit door -- Schedule a new Building Final when above items are complete. | MIKE | MIKE | | B= | P | 4157239 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/27/2011 | reopen permit, project on hold | BLAKE | BLAKE | | BSP | P | 4155660 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 10/05/2010 | Rated walls at the SKIF room have been deleted from the approved plans | MIKE | MIKE | | BSP | P | 4051329 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | C | 10/05/2010 | | MIKE | MIKE | | BFR | C | 4051327 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/01/2010 | Need electric & mechanical rough inspections | MIKE | MIKE | | BFR | P | 4033402 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/17/2010 | SCIF wall framing ok | MIKE | MIKE | | BFR | P | 3996950 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | T | 05/25/2010 | PAID (REC#911333) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Splice to reconfigure scif room | SHELBY | SHELBY | | BSP | T | 3986365 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | T | 05/25/2010 | PAID (REC#911334) ADDITIONAL PLAN REVIEW TIME: $50 From: SHELLEY revise office layout | SHELLEY | SHELLEY | | BSP | T | 3986309 |
MECHONE, INC. | BSP | T | 05/25/2010 | PAID (REC#911335) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: splice for new mechanical sheet | DALEH | DALEH | | BSP | T | 3986284 |
DYNALECTRIC COMPANY | E= | C | 10/04/2010 | | MIKEC | MIKEC | | E= | C | 4050260 |
DYNALECTRIC COMPANY | ER | P | 07/21/2010 | SKIF AREA | MIKEC | MIKEC | | ER | P | 4012651 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 01/11/2011 | HWP FINAL. | LYNNS | LYNNS | | H= | C | 4096738 |
MECHONE, INC. | H= | C | 01/10/2011 | RECEIVED BALANCE REPORT. | LYNNS | LYNNS | | H= | C | 4096370 |
OLSON PLUMBING & HEATING COMPANY | HE | C | 12/06/2010 | NEEDS MORE TIME TO COPLETE | REBECCA | REBECCA | | HE | C | 4081145 |
MECHONE, INC. | H= | P | 09/27/2010 | HVAC FINAL PENDING BALANCE REPORT. | LYNNS | LYNNS | | H= | P | 4046435 |
MECHONE, INC. | HD | P | 08/25/2010 | ROUGH DUCT OK. | LYNNS | LYNNS | | HD | P | 4029695 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 07/09/2010 | TWO 100 LB TESTS OK, CHILLED WATER SUPPLY AND RETURN, SCIF. TEST GAUGES ON 2ND FLOOR. ONE 100 LB TEST OK ON HOT WATER LINES, SUPPLY AND RETURN TIED TOGETHER FOR TEST, SCIF. TEST GAUGES ON 2ND FLOOR. OK TO INSULATE. | NANCY | NANCY | | HWP | P | 4007145 |
MECHONE, INC. | HD | P | 06/04/2010 | FIRE/ SMOKE DAMPER FRAMING OK.
| LYNNS | LYNNS | | HD | P | 3990564 |