R. E. ALLEN CONSTRUCTION | B= | C | 12/27/2017 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 5723263 |
R. E. ALLEN CONSTRUCTION | B= | P | 12/02/2016 | spoke with Rod on the phone and told him that it is still OK pending the completion of the H=. Additional Inspections Required (computer generated): External Agency Inspection HD= by HEALTHDEPT is not Completed yet. | DANE | DANE | | B= | P | 5358769 |
R. E. ALLEN CONSTRUCTION | BE | L | 12/01/2016 | Renewed at 12/1/2016 11:38:47 AM | NELIDA | NELIDA | | BE | L | 5357577 |
R. E. ALLEN CONSTRUCTION | B= | P | 01/08/2016 | building OK per Dan F. on 1/6/16 pending all other final inspections / discussed needing H= with contractor on phone / no site visit made. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, PREMIER MECHANICAL Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5112568 |
R. E. ALLEN CONSTRUCTION | B= | R | 01/07/2016 | 1) need fire final 2) need other MEPs finals completed. Building OK. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, JLC ELECTRIC LLC Electrical Final Inspection is not Completed yet, PREMIER MECHANICAL Mechanical Final Inspection is not Completed yet. | DAN | DAN | | B= | R | 5111985 |
R. E. ALLEN CONSTRUCTION | BFR | C | 01/07/2016 | | DAN | DAN | | BFR | C | 5111982 |
PREMIER MECHANICAL | BSP | T | 12/29/2015 | PAID (REC#1305981) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical | JUSTINC | JUSTINC | | BSP | T | 5106500 |
R. E. ALLEN CONSTRUCTION | BSP | P | 12/29/2015 | PLAN SPLICE: (No Fee) by: DANM for Construction: Relocating makeup air unit with supporting engineer letter | DANM | DANM | | BSP | P | 5106484 |
JLC ELECTRIC LLC | E= | C | 01/07/2016 | | BRET | BRET | | E= | C | 5112042 |
JLC ELECTRIC LLC | E= | P | 12/23/2015 | not ready for final | BRET | BRET | | E= | P | 5105313 |
JLC ELECTRIC LLC | ER | P | 12/23/2015 | relocate receptacles above ceiling. cannot have cord run thru suspended ceiling rest of ceiling ok. | BRET | BRET | | ER | P | 5105311 |
JLC ELECTRIC LLC | ER | P | 10/30/2015 | walls ok | BRET | BRET | | ER | P | 5069654 |
PREMIER MECHANICAL | H= | C | 02/17/2016 | MECHANICAL FINAL OK. TEST AND BALANCE REPORT RECEIVED. | NANCY | NANCY | | H= | C | 5135554 |
PREMIER MECHANICAL | H= | P | 02/11/2016 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5132974 |
PREMIER MECHANICAL | H16 | C | 02/11/2016 | NEED NEBB TEST AND BALANCE REPORT FOR KITCHEN EQUIPMENT, KITCHEN HOODS AND RESTAURANT. | NANCY | NANCY | | H16 | C | 5132278 |
PREMIER MECHANICAL | H= | P | 01/06/2016 | LABEL EQUIPMENT ON ROOF. INSTALL EXTENSION ON TYPE I FAN. PROVIDE TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5111463 |
PREMIER MECHANICAL | HD | P | 12/31/2015 | COMPLETE GREASE WRAP AS PER OUR CONVERSATION. MAKE-UP AIR AND SUPPLIES ABOVE CEILING ALL OK. | NANCY | NANCY | | HD | P | 5108387 |
PREMIER MECHANICAL | HD | P | 12/21/2015 | GREASE DUCTS ALL OK, OK TO WRAP. OK FOR TWO LAYERS OF WRAP ON BOTH HOODS EXCEPT WHERE DUCTS CONNECT TO HOODS, STILL NEED TO SEE FIRST LAYER PROPERLY INSTALLED AROUND ELECTRICAL BOXES. | NANCY | NANCY | | HD | P | 5103043 |
PREMIER MECHANICAL | HD | P | 12/17/2015 | OK FOR FIRST LAYER OF GREASE WRAP UP TO FIRST WELD ON HOOD#1 DUCT TO HOOD COLLAR NEED TO FIX HOLES IN WELD, RE LIGHT TEST. | LUKE | LUKE | | HD | P | 5100855 |
PREMIER MECHANICAL | HD | P | 12/16/2015 | NOT READY. REPAIR HOLES IN GREASE DUCTS. | NANCY | NANCY | | HD | P | 5099907 |
PREMIER MECHANICAL | HC | C | 12/11/2015 | OK TO SET NEW METER. 1053 MBH TOTAL LOAD. | NANCY | NANCY | | HC | C | 5097035 |
PREMIER MECHANICAL | HI | C | 12/11/2015 | 10 LB TEST OK ON ALL GAS LINES. BY FINAL NEED REVISED/APPROVED PRINTS SHOWING NEW EQUIPMENT LOCATIONS AND NEW GAS LINES INSTALLED. | NANCY | NANCY | | HI | C | 5097025 |
PREMIER MECHANICAL | HD | P | 12/11/2015 | GREASE FAN IS WITHIN 10 FEET OF A PARAPET WALL. WILL NEED FACTORY EXTENSION INSTALLED ON FAN. | NANCY | NANCY | | HD | P | 5097022 |
PREMIER MECHANICAL | HD | P | 12/07/2015 | GREASE DUCT DROP THROUGH CURB OK, OK TO INSTALL WRAP ON THIS PIECE OF DUCT ONLY. | NANCY | NANCY | | HD | P | 5093168 |
PREMIER MECHANICAL | HD | P | 12/04/2015 | REPAIR HOLE IN GREASE DUCT. | NANCY | NANCY | | HD | P | 5092451 |
PREMIER MECHANICAL | HD | P | 11/12/2015 | HOOD WALLS OK. OK TO HANG HOODS. PLAN ON DOING AS MUCH LIGHT TEST ON GREASE DUCTS AS POSSIBLE WHEN DUCTS ARE ON THE GROUND. | NANCY | NANCY | | HD | P | 5077920 |
PREMIER MECHANICAL | HD | P | 11/09/2015 | INSTALL METAL ON WALL ON THE RIGHT SIDE OF HOOD ONE. CLOSE UP AND SEAL ALL GAPS IN STAINLESS. NO DRYWALL SCREWS TO ATTACH METAL TO WALL. CALL FOR ANOTHER INSPECTION BEFORE HOODS ARE INSTALLED. | NANCY | NANCY | | HD | P | 5075327 |
PREMIER MECHANICAL | HI | P | 10/30/2015 | 10 LB TEST OK ON TWO 1 1/2 INCH GAS LINES IN WALLS. NEED REVISED/APPROVED PRINTS, NO MEDIUM PRESSURE GAS BEING INSTALLED. SHOW NEW GAS LINE SIZING AND LOCATIONS (MAKE-UP AIR BEING MOVED?). | NANCY | NANCY | | HI | P | 5069270 |
CASCADE PLUMBING & HEATING | P= | C | 01/04/2016 | | JOEL | JOEL | | P= | C | 5109304 |
CASCADE PLUMBING & HEATING | PTO | C | 12/31/2015 | | JOEL | JOEL | | PTO | C | 5108657 |
CASCADE PLUMBING & HEATING | P= | P | 12/31/2015 | secure h2o lines in ceilng | JOEL | JOEL | | P= | P | 5108639 |
CASCADE PLUMBING & HEATING | P= | R | 12/30/2015 | NO PTO INSPECTION, UNABLE TO VERIFY WORK THAT WAS DONE | JOEL | JOEL | | P= | R | 5107879 |