GERALD H PHIPPS INC | B= | C | 10/10/2018 | All other required Final inspections are complete. (This is a computer generated result) | NATHAN | NATHAN | | B= | C | 5990820 |
GERALD H PHIPPS INC | B= | P | 09/26/2018 | Outstanding final correction items from phase 1-3 corrected. Additional Inspections Required (computer generated): External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977). | NATHAN | NATHAN | | B= | P | 5977777 |
GERALD H PHIPPS INC | B= | P | 06/25/2018 | Temp CO: Finals are pending or done ( Expires: 7/25/2018 12:00:00 AM) | GITA | GITA | | B= | P | 5884142 |
GERALD H PHIPPS INC | B= | P | 06/25/2018 | Temp CO: Finals are pending or done ( Expires: 7/25/2018 12:00:00 AM) | GITA | GITA | | B= | P | 5884140 |
GERALD H PHIPPS INC | B= | P | 03/16/2018 | Temp CO: TEMP Co: Pending Engineering/Elevator/HEating/Building FInal ( Expires: 4/15/2018 12:00:00 AM) | MATTHEWM | MATTHEWM | | B= | P | 5790852 |
GERALD H PHIPPS INC | B= | P | 11/28/2017 | Temp CO: TCO extension - Engineering, HVAC, Elevator, Electric, Bldg finals pending, discussed same w/ contractor ( Expires: 12/28/2017 12:00:00 AM) | MINDY | MINDY | | B= | P | 5696413 |
GERALD H PHIPPS INC | B= | P | 08/24/2017 | Final inspection for phase 3 (4th floor) / Need to move accessible sign for men's restroom to latch side of door / All other aspects for phase 3 OK -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), DYNALECTRIC COMPANY Electrical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Mechanical Final Inspection is not Completed yet, THYSSENKRUPP ELEVATOR CORP. Mechanical Final Inspection is not Completed yet. | NICK | NICK | | B= | P | 5605404 |
GERALD H PHIPPS INC | B= | P | 08/01/2017 | Phase 2 building final inspection / All aspects of phase 2 final OK / Need to complete exterior elements per phase 1 comments / Work on going for phase 1 items / Need all other finals complete for phase 2 -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, DYNALECTRIC COMPANY Electrical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Mechanical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Plumbing Final Inspection is not Completed yet, THYSSENKRUPP ELEVATOR CORP. Mechanical Final Inspection is not Completed yet. | NICK | NICK | | B= | P | 5582421 |
GERALD H PHIPPS INC | B= | P | 07/13/2017 | On site phone conference call with architect and contractor / No need for guard rail at existing non conforming drop at south side of building per last inspection / Reviewed need for occ load signs and where in project / Reviewed need for hand rails as per last inspection for exterior areas of project / Still need to inspect outstanding items and last 2 phases of project -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, DYNALECTRIC COMPANY Electrical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Mechanical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Plumbing Final Inspection is not | NICK | NICK | | B= | P | 5563726 |
GERALD H PHIPPS INC | B= | P | 06/29/2017 | Temp CO: all partial - good to go per Nick M ( Expires: 7/29/2017 12:00:00 AM) | JANE | JANE | | B= | P | 5550341 |
GERALD H PHIPPS INC | B= | P | 06/23/2017 | Inspection for phase #1 / Need to finish installing all exterior siding / Need to finish installing all exterior hand rails for stairs and ramps / Need to install guard rail at north exterior where greater than 30" of fall to grade / Need to install occ load signs throughout / Need to inspect all penetrations in elevator equipment rooms / Need to inspect all penetrations in south stairway / Need letter for how to protect steel penetration in south stairway / Need to finish installing all capping for roof / Need access to upper roof for inspection / Need to block access to elevator not in phase 1 / Need to remove thumb turns for doors throughout / Need to finish installing all door hardware throughout / Need all eng for footing, foundation, bond beams, and structural -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 3 | NICK | NICK | | B= | P | 5545649 |
GERALD H PHIPPS INC | B16 | P | 06/08/2017 | Met in office with Jim from GH Phipps, Bert W, and John W / Reviewed requirements for phasing TCO of project / Need phase plans to show areas of being phased / Need a partial for all outside agencies and internal for TCO / Need to barricade one elevator that will not be in use | NICK | NICK | | B16 | P | 5529140 |
GERALD H PHIPPS INC | BSP | P | 06/07/2017 | Site visit / Walked job site / Still need to do inspection for penetrations in stair tower | NICK | NICK | | BSP | P | 5528343 |
GERALD H PHIPPS INC | BSP | P | 05/25/2017 | All plumbing moved out of 2hr rated wall at stairs / All 4 layers of sheet rock OK per listing for stairwell / Still need to inspect penetrations through wall | NICK | NICK | | BSP | P | 5516999 |
GERALD H PHIPPS INC | BSP | R | 04/25/2017 | Met on site with Jim and Dale / Need to stop work on north stair tower / Not being built per approved plans or listing / New framed pop out shaft at stairs sitting on landings with 4 layers being installed / Need continuity for south west corner of stairs, many penetrations through all layers of sheet rock, will need Eng judgment for sprinkler penetration / Need detail from architect on how to protect penetrations of steel through rated wall | NICK | NICK | | BSP | R | 5486701 |
GERALD H PHIPPS INC | BSP | P | 04/21/2017 | In progress inspection of WP 7125 2nd layer / 2nd layer being installed per listing / Still need design from Eng or architect of record for how to keep continuity of wall at corner where mono coat beam is interrupting | NICK | NICK | | BSP | P | 5483501 |
GERALD H PHIPPS INC | BSP | P | 04/20/2017 | In progress inspection of WP 7125 2nd layer / 2nd layer being installed per listing / Still need design from Eng or architect of record for how to keep continuity of wall at corner where mono coat beam is interrupting | NICK | NICK | | BSP | P | 5481738 |
GERALD H PHIPPS INC | BSP | P | 04/19/2017 | Inspection for 1st layer of sheet rock for north stair tower per GA File NO. WP 7125 / Need to run sheet rock all the way to corner at landings per plans, contractor may want to have architect design new detail for this section / Need to inspect all penetrations for wall / Need to see three other layers for wall / Need new head wall detail, mono coat installed at roof | NICK | NICK | | BSP | P | 5480669 |
GERALD H PHIPPS INC | BSP | P | 04/13/2017 | Need to fire caulk around plumbing penetrations in south restroom wall / All other penetrations OK | NICK | NICK | | BSP | P | 5474205 |
GERALD H PHIPPS INC | BFR | P | 04/13/2017 | Detail in RBD binder for soffits / 4th floor soffit framing OK | NICK | NICK | | BFR | P | 5474196 |
HEATING & PLUMBING ENGINEERS, INC | BSP | T | 04/12/2017 | PAID (REC#1416889) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: REVISED LAYOUTS, GAS, SNOWMELT | JUSTINC | JUSTINC | | BSP | T | 5472313 |
GERALD H PHIPPS INC | BSP | P | 04/11/2017 | Inspection for stair cabinet unit heaters back rock / Architect stamped detail in RBD binder on site / Rock installed per design for both units in north stair tower in 2hr wall | NICK | NICK | | BSP | P | 5471845 |
DYNALECTRIC COMPANY | BSP | P | 04/11/2017 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: RFI-0366 Sheet E401 and PR4 Sheet E402 | BERTHA | BERTHA | | BSP | P | 5471669 |
HEATING & PLUMBING ENGINEERS, INC | BSP | T | 04/11/2017 | PAID (REC#1416889) PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 4-11-17 | TCRIPPEN | TCRIPPEN | | BSP | T | 5471239 |
GERALD H PHIPPS INC | BSP | R | 04/07/2017 | Inspection for space heaters installed inside 2hr rated wall at north stair tower / Need to have RFI design stamped by architect or Eng of record / Detail shows 4 layers of rock installed log cabin style, not installed correctly per design at time of inspection / Please recall inspection with GA listing per design and fix sheet rock | NICK | NICK | | BSP | R | 5467924 |
GERALD H PHIPPS INC | BFR | P | 04/05/2017 | Walked 3rd and 4th floor for frame / All walls for both levels OK / Reviewed accessible elements / Need to inspect floor penetrations for structure both levels / Need detail for soffit framing of 4th floor / Framing for fired out walls at west stair towers OK / Still need to inspect all aspects of shaft wall 4th floor | NICK | NICK | | BFR | P | 5465563 |
GERALD H PHIPPS INC | BSP | P | 04/04/2017 | Walked job with Dale / Need frame inspection for 3rd and 4th floors / Need to inspect shaft for 4th floor / Need listing for cable bundle penetration | NICK | NICK | | BSP | P | 5464581 |
GERALD H PHIPPS INC | BIN | P | 04/04/2017 | Exterior insulation for 4th floor walls OK | NICK | NICK | | BIN | P | 5464567 |
GERALD H PHIPPS INC | BSP | P | 03/31/2017 | Met Jim on site / Reviewed requirements for hand rail at mechanical room garden level for return / Reviewed need for letter for headering off king studs at 4th level bathroom where mechanical goes through | NICK | NICK | | BSP | P | 5461718 |
GERALD H PHIPPS INC | BFR | P | 03/08/2017 | Frame inspection for remaining 2nd level interior framing / All framing OK / Need to inspect rated walls for rated enclosure to new addition / U415 wall at east stairs OK / Reviewed accessible elements | NICK | NICK | | BFR | P | 5435442 |
GERALD H PHIPPS INC | BSP | P | 03/01/2017 | Inspection for sprinkler pipe penetrations of stair towers / Stair tower #1 OK for penetrations through CMU from garden level to 2nd level / Stair tower #2 OK at garden level only / Listing in binder in trailer | NICK | NICK | | BSP | P | 5428177 |
GERALD H PHIPPS INC | BFR | P | 02/28/2017 | All other framing for south side interior non rated partition walls for garden level OK, need to see spray foam for special books area / U493 sheet rock for mechanical equipment room OK, double layer 5/8 type X USG used / 3rd floor shaft for chase OK, all penetrations OK / Floor penetrations in 3rd level bathrooms OK for structure / Exterior walls OK as built / | NICK | NICK | | BFR | P | 5427243 |
GERALD H PHIPPS INC | BFR | P | 02/17/2017 | Frame inspection for lid in bathrooms garden level and 1st floor / Framing OK, need to inspect penetrations at east restrooms garden level through horizontal assembly for structure, not installed at time of inspection / Penetrations for west restroom garden level floor OK / Penetrations in shaft wall at elevator OK / Still need letter from architect or Eng for concrete pored at shaft wall garden level / Stud framing for U493 walls of elevator equipment room 1st level OK, need to inspect all aspects of rock for this area / Double layer 5/8 rock for garden level elevator equipment room OK / Sprinkler line moved out of shaft wall for 1st level | NICK | NICK | | BFR | P | 5418800 |
GERALD H PHIPPS INC | BFR | P | 02/16/2017 | Frame inspection for garden level and 1st floor / light gage frame for garden level from elevator to exterior wall at north end OK / All 1st level light gage wall frame OK / Reviewed accessible elements with Dale / Eng judgment on file for top track of UL 428 shaft wall / Need inspection for rock wook and spray per judgment / Do not interfier with dampers / Need to know gage of all exterior walls | NICK | NICK | | BFR | P | 5417148 |
GERALD H PHIPPS INC | BIN | P | 02/13/2017 | insulation at AV-IT room 2nd floor has not been inspected / remaining 2nd floor exterior wall R19 batts okay / DISCUSSED WALL DETAILS FOR EXTERIOR WALL ON PAGE A5.11 / | NATHAN | NATHAN | | BIN | P | 5413781 |
GERALD H PHIPPS INC | BFR | P | 02/10/2017 | Inspection for penetrations through 2hr shaft on garden, 1st and 2nd floor / Walked job site with Roger and Alex, Dale out / Garden, 1st and 2nd level bathroom, electrical rooms at shaft OK for penetrations / Need detail for removal of shaft at garden level where concrete pored in place / Need to fire caulk plumbing penetrations at elevator all levels / Need to move sprinkler line that sits in rated 2hr assembly on east side 1st level / | NICK | NICK | | BFR | P | 5412467 |
GERALD H PHIPPS INC | BFR | R | 02/09/2017 | Inspection for penetrations though 2hr shaft / Missing fire caulk at multiple areas all levels, not ready for inspection / Anular space needs to be corrected for multiple penetrations / Walked with Dale S / Please recall inspection | NICK | NICK | | BFR | R | 5411060 |
GERALD H PHIPPS INC | BIN | P | 02/02/2017 | Inspection for insulation on exterior walls 1st floor / R-19 installed in all new walls / Need to install R-8 continuous insulation per energy calc sheet / Reviewed need for wall type of exterior walls / Reviewed requirements for 1hr wall at attrium with Dale and Alex / Training with Nick M | NICK | NICK | | BIN | P | 5405055 |
GERALD H PHIPPS INC | BSP | P | 01/31/2017 | training with Nick Type 2A building / | NATHAN | NATHAN | | BSP | P | 5403175 |
GERALD H PHIPPS INC | BFR | P | 01/31/2017 | Met Dale S and Alex on site / Frame inspection for exterior framed walls of 1st and 2nd floor / Need wall detail for all exterior walls / All 6" wall on main floor with 18GA steel / 2nd floor exterior fired in walls 6" 25ga studs / Interior frame for garden level group study and special collections OK / Reviewed need for letters of 3rd party for mono coat / Still need to inspect all penetrations / Training with Nathan | NICK | NICK | | BFR | P | 5403190 |
GERALD H PHIPPS INC | BFR | P | 01/24/2017 | framing for furr-out walls ok @ garden level west and south light gauge ok/1st floor mens #116 and womens @114A restroom framing ok-need to address AC linesets that penetrate type 2A construction 1hr floors through penetrations in same restroom areas floor above/need specs for access panel to valves in 2hr shaft wall firebarriers @ same restroom areas and all other floors they occur @ on how to maintain continuity of shaftwall sheetrocking/garden level mech shaft need all through penetration firestopping details and inspections from all trades-cast pipes and metalic condiuts run at a oblong hole in rated 2hr shaftwalls/met Alex frmaer and drywaller rep on site and set expectations for needed to see all framing before covered up and not to install any double systems until inspected/need reinspection of all penetrations and need listings in RBD binder | BERTW | BERTW | | BFR | P | 5397102 |
GERALD H PHIPPS INC | BSP | P | 01/20/2017 | training with rebecca on Tutt Library expansion, rated assemblies and steel stud framing | BERTW | BERTW | | BSP | P | 5393956 |
GERALD H PHIPPS INC | BFR | P | 01/12/2017 | Walked job site with Dale / American Core bored being installed for U428 wall / All core bored OK for garden level and 1st floor / Need to inspect all penetrations / Need to make sure mechanical has inspected framing for dampers | NICK | NICK | | BFR | P | 5387512 |
GERALD H PHIPPS INC | BSP | P | 01/10/2017 | Walked job site / New framing installed on all levels of existing building / New framing on multiple levels of new addition / Need listings for all penetrations through horizontal assembly / All exterior box headers are being pre insulated | NICK | NICK | | BSP | P | 5385612 |
GERALD H PHIPPS INC | BSP | P | 01/06/2017 | Met on site with Dale / Correct shaft liner being installed for shaft / All foundation walls for addition complete / Framing for all levels of existing building being started | NICK | NICK | | BSP | P | 5383851 |
GERALD H PHIPPS INC | BSP | P | 12/15/2016 | Met Architects on site Stephanie Kingsnorth and Jeremy Brunel from Pfeiffer Partners also Dale Spencer from GH Phipps/UL 428 as noted per Inspector Nick M needs to have the correct sheetrock coreboard installed and reinspected for mech shaft near elevator area | BERTW | BERTW | | BSP | P | 5369295 |
GERALD H PHIPPS INC | BFR | P | 12/13/2016 | Met on site with Alex ( framing ) / Backing installed for bathrooms / Want to use U415 for 2hr shaft, plans call for U428, need letter from architect to change to U415 / Still need to inspect all penetrations through horizontal assembly for construction type / Still need listing and Eng for all in fill / OK to rock hallway walls for north garden level area / | NICK | NICK | | BFR | P | 5366827 |
GERALD H PHIPPS INC | BFR | P | 12/07/2016 | training with Nick / non bearing walls at garden level grid XB-XE, 3.2-1 / need backing installed at all restrooms / provide printed listings for all referenced rated wall and floor ceiling assemblies and penetrating items / still need all inspections on penetrating items at floor, ceiling and walls / need listing and engineering for 2 floor in fills at elevator equipment room and mens restroom shaft / provide horizontal assembly listing for elevator equipment room over rated wall / | NATHAN | NATHAN | | BFR | P | 5362614 |
GERALD H PHIPPS INC | BFR | P | 12/07/2016 | Training with Nathan R on IIA construction / Training on reading plans and UL listings for project / All framing notes for garden level done by Nathan R / Nathan and Dale traded contact information / Walked job site / Reviewed with Dale pre insulation for headers / Reviewed accessible elements | NICK | NICK | | BFR | P | 5362602 |
GERALD H PHIPPS INC | BSP | P | 10/20/2016 | Met on site with Dale / Walked job site / Talked about pre insulating box headers and trimmers for exterior / All structural steel being installed | NICK | NICK | | BSP | P | 5323495 |
GERALD H PHIPPS INC | BSP | P | 10/13/2016 | On site training with Bert W / Talked to Josh about pre insulation box headers and studs / Training on fire rated materials in type 1 construction / Walked job site | NICK | NICK | | BSP | P | 5318432 |
GERALD H PHIPPS INC | BBB | P | 09/28/2016 | Met on sit with Dale / OK to use Eng for bond beam inspections / Looked at strairway #2, no bond beam needed at time of inspection / #4 vertical bar at 4' oc OK | NICK | NICK | | BBB | P | 5304633 |
GERALD H PHIPPS INC | BSP | P | 09/12/2016 | Met on site with Dale, needed to pick up sheets S001 thorugh S301 to be scanned | NICK | NICK | | BSP | P | 5290239 |
GERALD H PHIPPS INC | BSP | P | 09/02/2016 | Met on site with Dale / He said approved plans for addition and interior remodel permited today, will need to schedule pre construction meeting / Still need to install north wall at west side addition | NICK | NICK | | BSP | P | 5284601 |
GERALD H PHIPPS INC | BSP | P | 08/24/2016 | Met on site with Dale / Plan on having pre construction meeting after plans are approved for build out | NICK | NICK | | BSP | P | 5276729 |
GERALD H PHIPPS INC | BSP | P | 08/10/2016 | On site visit with Dale / Walked job site / Will need all Eng reports for observation in RBD folder | NICK | NICK | | BSP | P | 5265871 |
GERALD H PHIPPS INC | BSP | P | 08/05/2016 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Revised to show addition of motorized dampers at elevators | JUSTINC | JUSTINC | | BSP | P | 5263120 |
GERALD H PHIPPS INC | BFN | P | 08/05/2016 | OK for Eng to do inspections | NICK | NICK | | BFN | P | 5262296 |
GERALD H PHIPPS INC | BFT | P | 08/05/2016 | OK for Eng to do inspections | NICK | NICK | | BFT | P | 5262294 |
GERALD H PHIPPS INC | BFT | P | 07/25/2016 | lines XB-A,7-2 ok/pending letter for south mech room garden level footing is 1'4" wide per rfi not on plans | BERTW | BERTW | | BFT | P | 5253416 |
GERALD H PHIPPS INC | BFT | P | 07/19/2016 | Horizontal grade beam at northeast corner OK | NICK | NICK | | BFT | P | 5248078 |
GERALD H PHIPPS INC | BFN | P | 07/12/2016 | Eng design for blockout on west wall of tunnel on file / Clearances to forms OK for north tunnel | NICK | NICK | | BFN | P | 5242455 |
GERALD H PHIPPS INC | BFN | P | 07/11/2016 | north tunnel walls rebar ok pending engineering for blockouts @ S1 detail facing west not on plans and reinspection needed /set up clearances to forms and button up and recall inspection for Tuesday | BERTW | BERTW | | BFN | P | 5241841 |
GERALD H PHIPPS INC | BSP | T | 07/08/2016 | PAID (REC#1340517) PLAN SPLICE FEE: $50 by: DANM for Construction: Minor foundation revisions | DANM | DANM | | BSP | T | 5240373 |
GERALD H PHIPPS INC | BFN | P | 07/06/2016 | Eng letter on file to bend #5 rebar hooks for tunnel lid on file / Clearance for south and central walls of tunnel OK / No more inspections until revised plans in to RBD | NICK | NICK | | BFN | P | 5238155 |
GERALD H PHIPPS INC | BFN | R | 07/05/2016 | Need revised plans to RBD per previous comments/ tunnel walls for mech tunnel lacking proper clearance to inside face of forms, letter for ok to bend #5 rebar hooks for tunnel lid rebar needed from engineer | BERTW | BERTW | | BFN | R | 5237222 |
GERALD H PHIPPS INC | BFN | P | 06/29/2016 | Clearance to forms for SE stair tower OK | NICK | NICK | | BFN | P | 5233802 |
GERALD H PHIPPS INC | BFN | P | 06/28/2016 | SE stair and elevator tower and shaft ok to garden level pour/recall inspection to check clearance to forms after buttoned up/rebar ok pending plans revised for changes | BERTW | BERTW | | BFN | P | 5233055 |
GERALD H PHIPPS INC | BFI | P | 06/23/2016 | mech tunnel footing ok page S122 still need section with 3 pads inspected | BERTW | BERTW | | BFI | P | 5229403 |
GERALD H PHIPPS INC | BFT | P | 06/17/2016 | met Engineer Steve Horner on site/all previous comments from yesterday are corrected/open hole field copy good for 4000psf/SE footings ok @ elevator areas/need all S100 to S300 pages spliced into RBD foundation only permit for revisions/Notice to future inspector that Jim Martin has the revisions on his office blu-beam for inspection purposes | BERTW | BERTW | | BFT | P | 5224734 |
GERALD H PHIPPS INC | BFT | R | 06/16/2016 | met with Dale Phipps rep and Ray rebar setting foreman/steel not per plans,missing verts,clearance issues,footing sizing,numerous items need to be reworked and reinspected/called Steve Horner structural engineer and left message there is a foundation only structural plan that doesn't match the uprgrade to finish plan @ the stair tower,reviewed elevator sump with Dale/need 4000psf open hole verification from soils engineer before reinspection or ok to use engineer to do inspections ok by Bert W | BERTW | BERTW | | BFT | R | 5224384 |
GERALD H PHIPPS INC | B16 | P | 05/17/2016 | on site meeting with Jim,Dale GH Phipps construction managers/reviewed construction scheduling/when upgrade to finish permit is pulled Jim would like an on site meeting to review approved plan sets | BERTW | BERTW | | B16 | P | 5201151 |
DYNALECTRIC COMPANY | E= | C | 02/21/2018 | | BRET | BRET | | E= | C | 5770108 |
DYNALECTRIC COMPANY | E= | P | 12/12/2017 | working space at chp disconnects and control panels | BRET | BRET | | E= | P | 5709708 |
DYNALECTRIC COMPANY | E= | P | 11/20/2017 | working space at chp disconnects and control panel ( gas pipe needs relocated to obtain working space). conduit running thru west elevator equipment room not associated with elevator (build soffit to enclose them). cannot use center screw for sole support of receptacles in an industrial cover ( 4th floor mech room) install double barrel lugs to correct grounding issue in light poles around building. | BRET | BRET | | E= | P | 5690329 |
DYNALECTRIC COMPANY | E= | P | 11/15/2017 | need to walk thru building have exterior lighting on, open pole light hand holes, panel schedules. need to inspect elevator equipment rooms. working space at disconnects. | BRET | BRET | | E= | P | 5685928 |
DYNALECTRIC COMPANY | ES | C | 11/15/2017 | Commercial Service: 400 amps ct and disconnect for chp needs rec meter set | BRET | BRET | | ES | C | 5685919 |
DYNALECTRIC COMPANY | ER | C | 08/18/2017 | | BRET | BRET | | ER | C | 5600026 |
DYNALECTRIC COMPANY | E= | P | 08/18/2017 | 4th floor except panel schedules, industrial covers, gfci receptacle in break room. | BRET | BRET | | E= | P | 5599978 |
DYNALECTRIC COMPANY | ER | C | 08/18/2017 | | BRET | BRET | | ER | C | 5599975 |
DYNALECTRIC COMPANY | ES | C | 08/08/2017 | Commercial Service: 225 - amp 4 Wire service installed 109080 watts pv solar ok to set rec meter | CRAIG | CRAIG | | ES | C | 5588715 |
DYNALECTRIC COMPANY | E= | P | 07/21/2017 | garden level floor boxes ok note: need proper working space at chp1 | BRET | BRET | | E= | P | 5571679 |
DYNALECTRIC COMPANY | ER | P | 07/21/2017 | ceilings see plans for locations. 2nd 3rd and 4th. secure whips fixtures not mechanically fasten to grid (grid opening to small for fixture) remove temp lighting. open box. | BRET | BRET | | ER | P | 5571666 |
DYNALECTRIC COMPANY | ER | P | 06/27/2017 | On first floor floor boxes as marked on approved plan sheet E 201----On second floor room 215 and 220 as marked E 202 and floor boxes in room 229 exclusive of those on ckt 4 which where not energized | SHELBY | SHELBY | | ER | P | 5548152 |
DYNALECTRIC COMPANY | E= | P | 06/26/2017 | 2ND FLOOR SEE PLANS --NEED 220 --215 --FLOOR BOXES AND GFCI PROTECTION ON DRINKING FOUNTAINS ---PANEL SCH ----MOTION DETECTORS NOT WORKING | BRIAN | BRIAN | | E= | P | 5546370 |
DYNALECTRIC COMPANY | E= | P | 06/23/2017 | partial 1st floor. phase 1 except bath, electric rooms, ig recepts, furniture feeds, floor boxes, entry lights, millwork receptacles lobby desk. center screw cannot be sole support floor receptacles. panel schedules and rooms marked not ready on plans. | BRET | BRET | | E= | P | 5544810 |
DYNALECTRIC COMPANY | EP | R | 06/22/2017 | remove bond jumper in chp switch a and b | BRET | BRET | | EP | R | 5543500 |
DYNALECTRIC COMPANY | EP | P | 06/21/2017 | 4 panels one transformer 4th floor electrical room. | BRET | BRET | | EP | P | 5542501 |
DYNALECTRIC COMPANY | ER | P | 06/20/2017 | 2nd and 3rd floor suspended ceilings see plans for locations. | BRET | BRET | | ER | P | 5540399 |
DYNALECTRIC COMPANY | ER | R | 06/16/2017 | 204,215,226,227,231. ceilings ok 205 need tiles removed. if tiles are installed prior to inspection all tiles in room must be removed. I must be able to see all raceways where they enter and leave room. All j-boxes , fixture and equipment termination. | BRET | BRET | | ER | R | 5537846 |
DYNALECTRIC COMPANY | ER | P | 06/15/2017 | 3rd (suspended)and 4th floor(wood) ceilings see plans for locations | BRET | BRET | | ER | P | 5536633 |
DYNALECTRIC COMPANY | ER | R | 06/14/2017 | remove all ceiling tiles in rooms 204 ,205, 215, 226, 227 and 231 tiles installed prior to inspection. unable to inspect off ladder due to the limited space above ceiling. ceiling ok in other areas marked on plans. | BRET | BRET | | ER | R | 5535246 |
DYNALECTRIC COMPANY | E= | C | 06/14/2017 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 5535237 |
DYNALECTRIC COMPANY | E= | C | 06/14/2017 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 5535232 |
DYNALECTRIC COMPANY | ER | C | 06/14/2017 | FIRE ALARM INSPECTION: | BRET | BRET | | ER | C | 5535231 |
DYNALECTRIC COMPANY | E= | R | 06/12/2017 | FIRE ALARM INSPECTION: not ready for final | BRET | BRET | | E= | R | 5532023 |
DYNALECTRIC COMPANY | ER | P | 06/12/2017 | FIRE ALARM INSPECTION: 3 rd floor rough | BRET | BRET | | ER | P | 5532019 |
DYNALECTRIC COMPANY | ER | P | 06/08/2017 | hard lid and grid,see plans,2nd,3rd floors | JOHNN | JOHNN | | ER | P | 5529172 |
DYNALECTRIC COMPANY | ER | C | 06/06/2017 | ceilings see plans for locations | BRET | BRET | | ER | C | 5526666 |
DYNALECTRIC COMPANY | ER | P | 06/02/2017 | Partial final not rough, lights and recept's in: mech rm's 38,39, electric rmm, rm 014, 010 | GARYL | GARYL | | ER | P | 5523887 |
DYNALECTRIC COMPANY | ER | P | 05/25/2017 | 4th floor bath access panels framed | BRET | BRET | | ER | P | 5516692 |
DYNALECTRIC COMPANY | ER | P | 05/24/2017 | FIRE ALARM INSPECTION: see drawings in the generals trailer , high lighted in yellow above ceiling OK 4th floor restrooms need access framed in | CRAIGS | CRAIGS | | ER | P | 5515703 |
DYNALECTRIC COMPANY | ER | P | 05/24/2017 | see drawings in generals trailer , high lighted in yellow --- above ceilings 4th floor rest rooms need access panels framed in | CRAIGS | CRAIGS | | ER | P | 5515687 |
DYNALECTRIC COMPANY | ER | P | 05/17/2017 | panel l4m transformer lp4, ceilings, 10,16,17,18,18a,105,201 soffit, 300. | BRET | BRET | | ER | P | 5508854 |
DYNALECTRIC COMPANY | ER | P | 05/17/2017 | FIRE ALARM INSPECTION: ceiling 10,105,201 east soffit, and 300. do not cover 016-018a low volt and control cables on grid. | BRET | BRET | | ER | P | 5508853 |
DYNALECTRIC COMPANY | ER | P | 05/15/2017 | 2nd floor lids, 3rd floor walls see plans for locations. | BRET | BRET | | ER | P | 5506225 |
DYNALECTRIC COMPANY | ER | P | 05/09/2017 | garden level ceiling see plans for locations. | BRET | BRET | | ER | P | 5500143 |
DYNALECTRIC COMPANY | ER | P | 05/09/2017 | FIRE ALARM INSPECTION: garden level ceilings see plans for locations. | BRET | BRET | | ER | P | 5500129 |
DYNALECTRIC COMPANY | EP | P | 05/02/2017 | panel and tranformer ld1.ld2,ld3 and lgit | BRET | BRET | | EP | P | 5493253 |
DYNALECTRIC COMPANY | ER | P | 05/02/2017 | lids 207,229, walls open area 3 | BRET | BRET | | ER | P | 5493252 |
DYNALECTRIC COMPANY | ER | P | 05/02/2017 | FIRE ALARM INSPECTION: lid 229,207 | BRET | BRET | | ER | P | 5493249 |
DYNALECTRIC COMPANY | ER | P | 04/19/2017 | STAIR WAYS --LIGHTS AND HEATERS---OK | BRIAN | BRIAN | | ER | P | 5479688 |
DYNALECTRIC COMPANY | ER | P | 04/19/2017 | FIRE ALARM INSPECTION: PIPE AND WIRE IN STAIR WAYS--OK | BRIAN | BRIAN | | ER | P | 5479680 |
DYNALECTRIC COMPANY | ER | P | 04/12/2017 | FIRE ALARM INSPECTION: 2nd floor lid 4th floor walls | BRET | BRET | | ER | P | 5472724 |
DYNALECTRIC COMPANY | ER | P | 04/12/2017 | walls 4th and 2 lids on 2nd see plans for locations. | BRET | BRET | | ER | P | 5472718 |
DYNALECTRIC COMPANY | ER | P | 04/10/2017 | walls 3rd and 4th floor see plans for location. access added for 211 | BRET | BRET | | ER | P | 5469790 |
DYNALECTRIC COMPANY | EP | P | 04/06/2017 | panel LDG, TRANSFORMER LDG, Panel LGA, LGB and LGC | BRET | BRET | | EP | P | 5466463 |
DYNALECTRIC COMPANY | ER | P | 03/29/2017 | FIRE ALARM INSPECTION: same area as electrical rough see plans. | BRET | BRET | | ER | P | 5458856 |
DYNALECTRIC COMPANY | ER | P | 03/29/2017 | garden level reading room hard lid, lobby 101 soffit, 201 reading room exterior wall, and wall 240. | BRET | BRET | | ER | P | 5458855 |
DYNALECTRIC COMPANY | EP | P | 03/20/2017 | panel hdm, transformer and panel lgm. | BRET | BRET | | EP | P | 5445321 |
DYNALECTRIC COMPANY | ES | P | 03/20/2017 | Commercial Service: 1200 amp and 600 amp service made to main ok to energize. | BRET | BRET | | ES | P | 5445309 |
DYNALECTRIC COMPANY | ER | P | 03/14/2017 | walls 2nd floor see plans for location | BRET | BRET | | ER | P | 5440152 |
DYNALECTRIC COMPANY | ER | P | 03/07/2017 | walls garden,2 nd and 3rd floor see plans for locations marked 3-7-2017 | BRET | BRET | | ER | P | 5433044 |
DYNALECTRIC COMPANY | ER | P | 02/28/2017 | hard lid hallway 119 and room 129 remove temp power in lid 129 | BRET | BRET | | ER | P | 5426693 |
DYNALECTRIC COMPANY | ER | P | 02/28/2017 | FIRE ALARM INSPECTION: lid 119 and 129. | BRET | BRET | | ER | P | 5426690 |
DYNALECTRIC COMPANY | ER | P | 02/15/2017 | walls garden and 1st floor walls see plans | BRET | BRET | | ER | P | 5416001 |
DYNALECTRIC COMPANY | ER | P | 02/14/2017 | 2nd floor s.e area walls ok install nail plates s.e wall at stairwell | BRET | BRET | | ER | P | 5414516 |
DYNALECTRIC COMPANY | ER | P | 02/09/2017 | 2nd floor exterior wall only | BRET | BRET | | ER | P | 5410742 |
DYNALECTRIC COMPANY | ER | P | 02/08/2017 | garden level west soffit, half wal mech room. main floor s.w wall to center glass see plans for locations | BRET | BRET | | ER | P | 5409541 |
DYNALECTRIC COMPANY | ER | P | 01/31/2017 | g.l and 1st floor walls marked on plans | BRET | BRET | | ER | P | 5402519 |
DYNALECTRIC COMPANY | ER | P | 01/19/2017 | partial walls all 3 floors see plans for locations. | BRET | BRET | | ER | P | 5392595 |
DYNALECTRIC COMPANY | ER | P | 12/06/2016 | north basement walls see plans for locations. | BRET | BRET | | ER | P | 5361013 |
DYNALECTRIC COMPANY | ESL | P | 11/23/2016 | floor boxes northwest basement | BRET | BRET | | ESL | P | 5352234 |
DYNALECTRIC COMPANY | EUG | P | 11/08/2016 | eug ct to building service a and b , pv conduits and chp conduits all on north side of building | BRET | BRET | | EUG | P | 5338725 |
DYNALECTRIC COMPANY | ESL | P | 10/25/2016 | slab wall to wall only basement main electrical room | BRET | BRET | | ESL | P | 5326876 |
DYNALECTRIC COMPANY | ESL | P | 10/06/2016 | n.e basement mech room. conduit between mdp-a and rcs-a | BRET | BRET | | ESL | P | 5311728 |
DYNALECTRIC COMPANY | EUG | C | 09/23/2016 | basement south floor boxes | BRET | BRET | | EUG | C | 5301004 |
DYNALECTRIC COMPANY | EUG | P | 09/12/2016 | ufer center north | BRET | BRET | | EUG | P | 5290078 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | C | 08/31/2018 | ALL CORRECTIONS MADE | ERIC | ERIC | | HE= | C | 5952001 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | R | 08/10/2018 | (SOUTH LOBBY ELEVATOR) - DRAIN PAN INSTALLATION ABOVE 480 DISCONNECT NEEDS SECURED PROPERLY AND WILL NOT ACCOMMODATE WATER DRAINAGE, AND ALSO HAS NO DRAIN TO FLOOR. SUMP PUMPS DO NOT WORK WITH CURRENT FLOAT INSTALLATION. EMERGENCY POWER CONTENTS IN HALL CALL FIXTURE STILL INSTALLED. NEW HOLES IN MACHINE ROOM WALL ABOVE DOOR. (NORTH LOBBY ELEVATOR) - SUMP PUMPS DO NOT WORK WITH CURRENT FLOAT INSTALLATION. EMERGENCY POWER CONTENTS IN HALL CALL FIXTURE STILL INSTALLED. NEED ELEVATOR # DESIGNATION AT EGRESS FLOOR ELEVATOR DOOR JAMB | ROBERTV | ROBERTV | | HE= | R | 5930730 |
THYSSENKRUPP ELEVATOR CORPORATION | HE | L | 08/09/2018 | Renewed at 8/9/2018 8:47:39 AM | ERIC | ERIC | | HE | L | 5928632 |
HEATING & PLUMBING ENGINEERS, INC | H= | C | 07/19/2018 | ALL ITEMS ARE COMPLETE | JERRYF | JERRYF | | H= | C | 5907330 |
HEATING & PLUMBING ENGINEERS, INC | H= | L | 03/15/2018 | TAB REPORT RECEIVED - CONTRACTOR PLEASE CALL THIS INSPECTOR AT 327 - 2982 APPEARS THERE MAY BE MORE ITEMS TO INSPECT? | JERRYF | JERRYF | | H= | L | 5789151 |
HEATING & PLUMBING ENGINEERS, INC | HE | L | 03/14/2018 | Renewed online for 1/2 Fee at 3/14/2018 9:07:20 AM (RECEIPT #: 1487161) | WEBSITE | WEBSITE | | HE | L | 5788115 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | P | 08/23/2017 | Complete the termination of grounding cable in elevator machine room, Label elevator main disconnect and 110v cab circuit disconnect as to where they are fed from, GFCI outlet in pit must be accessible from the pit floor, Pit lighting must be guarded, Verify sump pump operation and alarms, Install correct braille plates and egress star, Remove emergency power placard from hall call station at egress landing, Fire signs (in case of fire do not use elevator, use exit) need to be mounted adjacent to hall call stations, Secure all hall fixtures, Need maintenance control program and unique procedures on site and entries made
| ERIC | ERIC | | HE= | P | 5604637 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 08/04/2017 | THIS INSPECTION WAS FOR PHASE 2 2ND FLOOR - HWP CONNECTIONS AT RADIANT PANEL OK ONLY | JERRYF | JERRYF | | H= | P | 5586314 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 07/18/2017 | COMPLETE ON THE FOLLOWING - (((( PHASE 1 )))) GARDEN LEVEL AND 1ST FLOOR - MECH#12 CONDENSERS 4A AND 4B - 5A AND 5B - MECHROOM #15 - HEAT PUMP 1A AND 1B - HUMIDIFIER - MECHROOM #38 - CONDENSERS 1A AND 1B - 2A AND 2B 0- 3A AND 3B - MECHROOM #39 - BOILER 1 /2 / 3 - ROOM #40 CHP 1 AND 2 - FLUE CONDENSATE DRAINS - 1ST FLOOR FIN TUBE - (((( PHASE 2)))) - 3TD FLOOR ADDITION ALL FIN TUBE - (((((PHASE 3)))) 4TH FLOOR - MECHROOM ERV 1 - CONDENSERS 6A AND 6B - 7A AND 7B - ALL 4TH FLOOR FIN TUBE | JERRYF | JERRYF | | H= | P | 5568226 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | P | 06/29/2017 | (S. LOBBY ELEVATOR) -- PIT LIGHTING REQUIREMENTS ARE TO ILLUMINATE 10 FOOT CANDLE OF LIGHTING AT ALL SERVICEABLE AREAS ALONG WITH BULB GUARDS, MACHINE ROOM MINI-SPLIT EVAPORATOR ABOVE 480 VOLT DISCONNECT NEEDS AN AUXILIARY DRAIN PAN WITH DRAIN TO MACHINE ROOM FLOOR, SECURE LOOSE WIRING AND COVER OPEN ELECTRICAL J-BOXES IN MACHINE ROOM, PIT ELECTRICAL GFI NEEDS TO BE RELOCATED BELOW SILL AND ACCESSIBLE FROM PIT FLOOR, SUMP PUMP OPERATION WILL BE VERIFIED ON NEXT ELEVATOR INSPECTION, NEED BRAILLE DOOR JAMB ENUMERATION AT ALL FLOORS, EMERGENCY POWER CONTENTS IN HALL CALL FIXTURE NEEDS TO BE REMOVED OR BLANKED OUT, NEED UNIQUE INSPECTION AND MAINTENANCE PROCEDURES ONSITE WITH THE MAINTENANCE CONTROL PROGRAM. -- OK FOR PUBLIC USE. | ROBERTV | ROBERTV | | HE= | P | 5550316 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 06/27/2017 | LEVEL 3 PARTIAL HVAC COMPLETE NEED TEST AND BALANCE REPORT PHASE-1-2 AND LEVEL-4 PARTIAL HVAC COMPLETE NEED TEST AND BALANCE REPORT PHASE-3 OK | LIDO | LIDO | | H= | P | 5547983 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 06/21/2017 | 3 RD FLOOR ABOVE CEILING ALL OK EXCEPT FOR MISSING CO2 CENSOR ROOM 327 . ( NEED REVISED PRINT FOR T/A NOT INSTALLED FROM ROOM 323 TO 323-B TO 327 SHOWN ON PRINT M.113 ) ( 3 RD FLOOR CAFE ABOVE CEILING OK EXCEPT WILL NEED REVISED PRINT TO REFLECT CEILING AND SOFFIT ) ROOM 409 AC FAN COIL OK ,4TH FLOOR ALL ABOVE CEILING OK EXCEPT FOR ROOM GROUP STUDY 412 , NEED REVISED PRINT DELETING ONE SUPPLY AIR IN STUDY SOUTH 400. ( MISSING STATIC PRESSURE CENSOR IN OPEN STUDY 400 M.114 ). LABEL ALL ACCESS DOORS. Still need final for all mechanical rooms and outside of building. | LIDO | LIDO | | H= | P | 5542370 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 06/05/2017 | NEED TO HIGH LIGHT PRINTS AT NEXT INSPECTION. M113: ABOVE CEILING ALL OK EXCEPT LIBRARY INSTRUCTION, CAFE, GROUP STUDY 310, LIBRARIAN 311 AND AV/IT 307. M111. MEETING ROOM OK. | NANCY | NANCY | | H= | P | 5525412 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 05/18/2017 | 2ND FLOOR RENOVATION AREA - ALL SA / RA GRILLES AND FINAL CONNECTIONS OK | JERRYF | JERRYF | | H= | P | 5510680 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 05/15/2017 | GARDEN LEVEL RENOVATION ABOVE CEILING GRDS OK GRID LINES D-5 TO E-9 AND GRID LINES 1.1 TO 6.5 , NEED SPLICE FOR AC .07 AND AC .09 AND THE DUCT RUNS AND GRDS LEAVE CEILING OPEN .( LABEL ALL CEILING ACCESS DOORS WHEN INSTALLED ) | LIDO | LIDO | | H= | P | 5506943 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 05/11/2017 | M111 LEVEL 1 RENOVATION. ALL COMPLETE EXCEPT QUESTION REGARDING AC-1.21 CONDENSATE PUMP LOCATED OVER THE TOP OF ELECTRICAL PANEL IN ELECTRICAL 121. LABEL ALL CEILING ACCESS DOORS. | NANCY | NANCY | | H= | P | 5502910 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 05/10/2017 | M111 LEVEL 1 ADDITION. ABOVE CEILING ALL OK EXCEPT COMPLETE CONDENSATE DRAIN INSULATION AT AC1.07. | NANCY | NANCY | | H= | P | 5501464 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 05/03/2017 | HIGH LIGHTED PRINTS. DISCUSSED WITH AARON HOW TO PROCEED WITH FINAL INSPECTIONS. | NANCY | NANCY | | HD | P | 5494246 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 05/02/2017 | MECHANICAL AIR INLET WITHIN 10 FEET OF GAS METER REGULATOR. THREE BOILER VENTS OK. GARDEN LEVEL ADDITION OK. | NANCY | NANCY | | H= | P | 5492958 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 04/28/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. M114. GENDER NEUTRAL 408 AND MECHANICAL ROOM 409: ALL OK, OK TO WRAP. | NANCY | NANCY | | HD | P | 5489958 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 04/26/2017 | SEE RECORD OF TEST DATED 4/26/17. 100 LB TEST OK ON SNOW MELT FOR SECOND FLOOR TERRACE. | NANCY | NANCY | | HWP | P | 5488326 |
HEATING & PLUMBING ENGINEERS, INC | HRP | C | 04/26/2017 | SEE RECORD OF TEST DATED 4/26/17. M104. 300 LB TEST OK ON HARD PIPE FROM CU 6A AND 6B TO BC6.1. OK TO INSULATE. ALL ROUGH REFRIGERATION PIPING COMPLETE. | NANCY | NANCY | | HRP | C | 5488320 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 04/25/2017 | SEE RECORD OF TEST DATED 4/25/17. 300 LB TEST OK ON HARD PIPE FROM CU 7A AND 7B TO BC7.1. OK TO INSULATE. | NANCY | NANCY | | HRP | P | 5486076 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 04/20/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. M114 ROUGH DUCTS ABOVE CEILING ALL OK EXCEPT NO INSPECTION OF GENDER NEUTRAL 408 OR MECHANICAL 409. ACCESS DOORS IN CEILINGS REQUIRED BY FINAL. | NANCY | NANCY | | HD | P | 5481307 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 04/17/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. SEE RECORD OF TEST DATED 4/17/17. 300 LB TEST OK ON LINES FROM BC6.1 TO BC6.2. OK TO INSULATE. | NANCY | NANCY | | HRP | P | 5477427 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 04/07/2017 | BC-7.1 AND BC-6.1 300 LB AIR TEST GOOD. | LUKE | LUKE | | HRP | P | 5467942 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 03/30/2017 | 300 LB TEST OK ON BC7.1 TO AC'S 3.24, 3.25 AND 3.04. 300 LB TEST OK ON BC6.1 TO AC 2.25. 300 LB TEST OK ON LINES IN FOURTH FLOOR SHAFT. | NANCY | NANCY | | HRP | P | 5459910 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 03/28/2017 | M111. EXPERIMENTAL CLASSROOM OK, OK TO WRAP. M113. CAFE 301 SUPPLY, RETURN AND OUTSIDE AIR OK, OK TO WRAP. M114. FOUR FIRE/SMOKE DAMPER FRAMES OK EXCEPT NEED TO SCREW ALL TABS OF HORIZONTAL FRAMING TO VERTICAL STUDS. DAMPER INSTALLATION OK. NO ANGLES YET. | NANCY | NANCY | | HD | P | 5457305 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/20/2017 | M103. FOUR 100 LB TESTS OK ON THIRD FLOOR HEATING WATER SUPPLY AND RETURN LINES. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5445451 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/15/2017 | M301. 100 LB TEST OK ON SNOW MELT IN MECH ROOM 38 FROM PUMPS THROUGH AIR SEPARATOR AND HEAT EXCHANGER. OK TO INSULATE AND LABEL. M103 AND M104. 100 LB TEST OK ON HEATING WATER SUPPLY AND RETURN IN THIRD FLOOR CHASE TO BALL VALVES ON THIRD FLOOR AND UP TO FOURTH FLOOR OVER BATH ROOM HARD LIDS TO MECH ROOM 409. | NANCY | NANCY | | HWP | P | 5441406 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 03/14/2017 | M111. SUPPLY AIR, OUTSIDE AIR ALL OK, OK TO WRAP. NO EXPERIMENTAL CLASSROOM YET. | NANCY | NANCY | | HD | P | 5440086 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/13/2017 | M100. LB TEST OK ON RELOCATED SNOW MELT IN SOUTH EAST CORNER OF BUILDING. OK TO INSULATE AND LABEL. NEED REVISED/APPROVED PRINTS BY FINAL. PRINTS ALL CAUGHT UP TODAY. | NANCY | NANCY | | HWP | P | 5438684 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/10/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. 100 LB TEST OK ON SECOND FLOOR HEATING SUPPLY/RETURN RISERS. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5437229 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 03/09/2017 | SEE RECORD OF TEST DATED 3/9/17. M103. 300 LB TEST OK ON BC 6.2 UP TO FOURTH FLOOR, CAPPED AT FOURTH FLOOR. M???. 300 LB TEST OK ON CU-5 SUPPLY AND RETURN LINES, CU-5 COMPLETE. | NANCY | NANCY | | HRP | P | 5436122 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/08/2017 | PLEASE CALL AN INSPECTION FOR EARLY NEXT WEEK TO CATCH UP ON PRINTS. 600 LB TEST OK ON HIGH TEMP SUPPLY, RETURN AND REVERSE SUPPLY/RETURN FROM MAINS IN TUNNEL TO HEAT EXCHANGER AND PUMP IN MECHANICAL ROOM. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5434592 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/07/2017 | 150 LB TEST OK ON HEATING WATER SUPPLY/RETURN FROM MECHANICAL ROOM TO MAINS IN HALLWAY. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5433434 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/03/2017 | 100 LB TEST OK ON CHILLED WATER SUPPLY/RETURN, GEOTHERMAL SUPPLY/RETURN AND CONDENSER WATER SUPPLY/RETURN MAIN STEEL PIPES ONLY. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5430584 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/02/2017 | 4 PRESSURE TESTS AND PIPING PER PLAN ON 2ND FLOOR NEW ADDITION FROM FIN TUBES | JERRYF | JERRYF | | HWP | P | 5430124 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 03/01/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. 100 LB TEST OK ON REVISED SNOW MELT. OK TO INSULATE AND LABEL. WILL NEED REVISED/APPROVED PRINTS BY FINAL. TWO 100 LB TESTS OK ON HEATING WATER SUPPLY AND RETURN MAINS FOR SECOND FLOOR NEW ADDITION. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5427897 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 02/28/2017 | M113. TWO DAMPER FRAMES, DAMPERS AND ANGLES OK. SUPPLY AND OUTSIDE AIR IN RENOVATION OK, OK TO WRAP. M110 AND M111: READING ROOM ALL OK TO WRAP. M112: HIGH LIGHTED INSPECTIONS DATED 2/10 AND 2/23/17. PRINTS UP TO DATE. | NANCY | NANCY | | HD | P | 5426683 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 02/24/2017 | M101. 100 LB TEST OK ON HEATING WATER RETURN IN WALL TO FIN TUBE, FIRST FLOOR RENOVATION. M100. 100 LB TEST OK ON SNOW MELT, GARDEN LEVEL SOUTH LINES TO MAIN. PRINTS CAUGHT UP TODAY. | NANCY | NANCY | | HWP | P | 5423969 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 02/24/2017 | SEE RECORD OF TEST DATED 2/24/17. M102. 300 LB TEST OK ON BC6.2 TO FAN COILS ON SECOND FLOOR. PRINTS CAUGHT UP TODAY. | NANCY | NANCY | | HRP | P | 5423965 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 02/23/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. SEE RECORD OF TEST DATED 2/23/17. 300 LB TEST OK ON BC 3.1 BACK TO CU-3 AND TO ALL A/C'S ON THIRD FLOOR. | NANCY | NANCY | | HRP | P | 5422676 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 02/23/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. SECOND FLOOR SHAFT TWO FIRE DAMPER FRAMES, DAMPERS AND ANGLES OK. SECOND FLOOR WEST ADDITION ALL OK, OK TO WRAP. | NANCY | NANCY | | HD | P | 5422671 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 02/23/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. 100 LB TEST OK ON SNOW MELT FROM FIRST FLOOR "IT" ROOM RISER TO SECOND FLOOR RISER. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5422665 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 02/17/2017 | SEE RECORD OF TEST DATED 2/17/17. M100 AND M101. 300 LB TEST OK ON ALL OF CU-1 INCLUDING BC1.1 AND BC1.2. REPAIR ALL ARMAFLEX. | NANCY | NANCY | | HRP | P | 5417965 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 02/16/2017 | FIRST FLOOR SHAFT, RENOVATION: DAMPER FRAMING OK. SECOND FLOOR SHAFT: PROPERLY FRAME OPENINGS. NO FIRE CAULK ALLOWED AROUND DAMPERS. | NANCY | NANCY | | HD | P | 5416785 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 02/10/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. SECOND FLOOR RENOVATION: SUPPLIES OK, OK TO WRAP. | NANCY | NANCY | | HD | P | 5412010 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 02/08/2017 | NEED TO SIGN RECORD OF TEST AT NEXT INSPECTION. M100. 300 LB TEST OK ON CU-4. 300 LB TEST OK ON BC5.1 FROM MECHANICAL ROOM 012 TO BC5.1 AND ALL FAN COILS. REPAIR ALL ARMAFLEX. | NANCY | NANCY | | HRP | P | 5409607 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 02/03/2017 | M100. 100 LB TEST OK ON SNOW MELT IN GARDEN LEVEL EXCEPT FOR SOUTH WEST RUN. 100 LB TEST OK ON SNOW MELT GARDEN LEVEL COPPER LINES FROM STEEL TO MANIFOLD ON FIRST LEVEL. OK TO INSULATE AND LABEL. M100 AND M102. 100 LB TEST OK ON HEATING SUPPLY/RETURN FOR FIN TUBES AND CABINET UNIT HEATERS, GARDEN LEVEL TO MECH ROOM 15 AND SECOND FLOOR HEATING IN RENOVATION AREA ONLY. FIN TUBE STUBS CAPPED AT SECOND FLOOR, | NANCY | NANCY | | HWP | P | 5406008 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 02/02/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. SEE RECORD OF TEST DATED 2/2/17. 300 LB TEST OK ON BC4.1 FIRST FLOOR A/C. 300 LB TEST OK ON BC2.2, COMPLETE SYSTEM. | NANCY | NANCY | | HRP | P | 5404962 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 02/02/2017 | WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. 100 LB TEST OK ON SNOW MELT SUPPLY AND RETURN, GARDEN LEVEL. OK TO INSULATE AND LABEL. 100 LB TEST OK ON CONDENSER WATER SUPPLY/RETURN FROM MECH ROOM 12 TO MECH ROOM 15. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5404959 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 01/27/2017 | M110 GARDEN LEVEL: SUPPLY AND OUTSIDE AIR OK, OK TO WRAP. M111 LEVEL 1: THREE DAMPER FRAMES OK, ANNULAR SPACE OK. NEED TO SEE ANGLES AND CHECK BREAK AWAY CONNECTIONS. | NANCY | NANCY | | HD | P | 5400194 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 01/27/2017 | SEE RECORD OF TEST DATED 1/27/17. M100, M101 AND M102: 300 LB TEST OK ON BC2.1. 300 LB TEST OK ON BC4.1. REPAIR ALL ARMAFLEX. | NANCY | NANCY | | HRP | P | 5400193 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 01/27/2017 | M100, M103, M104 AND M301: 100 LB TEST OK ON CONDENSER WATER FROM MECH ROOMS 038 AND 039 TO MECH ROOM 012. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5400186 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 01/19/2017 | INSPECTION TO GET PRINTS CAUGHT UP. SEE SHEETS M100, M101 AND M102. | NANCY | NANCY | | HRP | P | 5392663 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 01/19/2017 | INSPECTION TO GET PRINTS CAUGHT UP. SEE SHEETS M100, M101, M102 AND M301. | NANCY | NANCY | | HWP | P | 5392659 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 01/19/2017 | INSPECTION TO GET PRINTS CAUGHT UP. SEE SHEETS M110 AND M111. | NANCY | NANCY | | HD | P | 5392658 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 01/18/2017 | GARDEN LEVEL WEST OF RAMP: SUPPLY AND OUTSIDE AIR DUCTS ALL OK. NO DIFFUSERS YET. | NANCY | NANCY | | HD | P | 5391263 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 01/18/2017 | 100 LB TEST OK ON FIRST FLOOR OVERHEAD PIPING FOR CABINET UNIT HEATERS AND FIN TUBES. NO PIPING CONNECTIONS TO EQUIPMENT OR IN WALLS TO FIN TUBES YET. CAPPED ON SECOND FLOOR. | NANCY | NANCY | | HWP | P | 5391253 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 01/18/2017 | 300 LB TEST OK ON LINES FROM BC4.2 TO SIX UNITS ON SECOND FLOOR. REPAIR ALL TEARS IN INSULATION. | NANCY | NANCY | | HRP | P | 5391251 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 01/13/2017 | 100 LB TEST OK ON HEATING WATER SUPPLY FOR CABINET UNIT HEATERS AND FIN TUBE HEAT. TEST FROM STEEL TO COPPER TRANSITION IN GARDEN LEVEL UP THROUGH CHASE TO SECOND FLOOR. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5388379 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 01/12/2017 | NEED TO SIGN RECORD OF TEST AND HIGH LIGHT PRINTS AT NEXT INSPECTION. TWO 100 LB TESTS OK ON CONDENSER CHILLED WATER SUPPLY AND RETURN FROM MECHANICAL ROOM OVER TO CHASE AND UP CHASE TO THIRD FLOOR. CAPPED AT THIRD FLOOR. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5387433 |
HEATING & PLUMBING ENGINEERS, INC | HI | C | 01/12/2017 | 60 LB TEST OK ON ALL GAS LINE FROM MECHANICAL ROOM TO METER. | NANCY | NANCY | | HI | C | 5387429 |
HEATING & PLUMBING ENGINEERS, INC | HC | C | 01/05/2017 | OK TO SET 2 LB METER. | NANCY | NANCY | | HC | C | 5382881 |
HEATING & PLUMBING ENGINEERS, INC | HI | P | 01/05/2017 | 60 LB TEST OK ON GAS LINE TO AND IN MECH ROOM 039. STILL NEED TO SEE CONNECTION AND TEST ON GAS CONNECTION TO METER. BY FINAL INSTALL MEDIUM PRESSURE LABELS AND REGULATORS. | NANCY | NANCY | | HI | P | 5382872 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 12/23/2016 | WILL NEED 3RD PARTY TESTS VERIFICATIONS ON GROUND SOURCE HEAT PUMP PIPING AND ENGINEERING DESIGN WILL BE VERIFIED BEFOR FINAL FOR DESIGN PER RBC GROUND SOURCE HEAT PUMP AMENDMENT. RENOVATION BUILDING ONLY MAIN LEVEL OK FOR WRAP ON OUTSIDE AIR DUCTS AND LOW PRESSURE ROUND DUCT. ROUGH INSPECTION ON BATH EXHAUST MAIN DUCTS OK. CALL FIRE SMOKE DAMPER INSPECTIONS AT SHAFTS SAME AREA WHEN READY. | JON | JON | | HD | P | 5376257 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 12/12/2016 | GARDEN LEVEL SHAFT. FRAMING FOR TWO FIRE/SMOKE DAMPERS OK. OK TO COVER. | NANCY | NANCY | | HD | P | 5365108 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 12/12/2016 | 300 LB TEST OK ON PIPING FOR CU-1 TO BC1.1 AND BC1.2. 300 LB TEST OK ON PIPING FOR CU-2 UP TO BC2.1. 300 LB TEST OK ON OVER HEAD PIPING ONLY FOR CU-3. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HRP | P | 5365101 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 11/21/2016 | SHEET M110. ROUGH DUCTS OK, OK TO WRAP. NO SHAFT WALL FRAMING AROUND FIRE/SMOKE DAMPERS YET. VERIFY HANGER SPACING ALLOWED BY SMACNA FOR EXPOSED SPIRAL DUCTS. | NANCY | NANCY | | HD | P | 5349637 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 11/14/2016 | NEED TO SIGN RECORD OF TEST AT NEXT INSPECTION. M122. THREE 600 LB TESTS OK ON HI TEMP WATER SUPPLY AND TWO RETURN LINES FROM TUNNEL TO NEW MECHANICAL ROOM. 100 LB TEST OK ON CHILLED WATER SUPPLY AND RETURN FROM TUNNEL TO NEW MECHANICAL ROOM. | NANCY | NANCY | | HWP | P | 5342673 |
HEATING & PLUMBING ENGINEERS, INC | HWP | P | 10/31/2016 | SEE TWO RECORDS OF TEST DATED 10/31/16. HIGH LIGHTED STAMPED SET PAGE M122. THREE 600 LB TESTS OK ON HI TEMP HOT WATER SUPPLY AND TWO RETURN LINES IN TUNNEL TO NEW LIBRARY. OK TO INSULATE AND LABEL. ONE 100 LB TEST OK ON CHILLED WATER SUPPLY AND RETURN IN EXISTING TUNNEL BY TUTT SOUTH. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 5331521 |
HEATING & PLUMBING ENGINEERS, INC | P= | C | 08/04/2017 | level 3 phase 2 cafe area ok. | TAYLOR | TAYLOR | | P= | C | 5585969 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 07/26/2017 | this inspection was for level 3 phase 2 cafe area ( need backflow protection at all equipment, missing hammer arrestors at ice maker and dishwasher ). | TAYLOR | TAYLOR | | P= | P | 5576286 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 07/18/2017 | garden level, level 1, level 4 complete, note: building inspector aware of sink heights at level 4. | TAYLOR | TAYLOR | | P= | P | 5567724 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 06/23/2017 | 2nd level complete, phase 1 level 3 ok. | TAYLOR | TAYLOR | | P= | P | 5544791 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 06/22/2017 | need trap guards through out and manufactures specs for oil alarms at garden level phase 1, need 16-18 inches from side wall to center of toilet at mens restroom and trap guards through out at level 1 phase 1. | TAYLOR | TAYLOR | | P= | P | 5543509 |
HEATING & PLUMBING ENGINEERS, INC | PTO | C | 04/05/2017 | H2O at kitchen area ok, note: check backflows on 4th floor for cold water make- up by final. | TAYLOR | TAYLOR | | PTO | C | 5465416 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 04/04/2017 | 2 inch vent at 4th floor for kitchen area and break sink ok. | TAYLOR | TAYLOR | | PTO | P | 5464482 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 04/03/2017 | DWV and H2O in walls for lavs ok at mens restroom on 4th floor, 2 inch vent for kitchen area on 3rd floor ok, cold water make- up on 4th floor ok. | TAYLOR | TAYLOR | | PTO | P | 5463131 |
HEATING & PLUMBING ENGINEERS, INC | PRD | C | 03/31/2017 | ok 3rd floor primary and secondary roof drains @ rm 302. this completes all phases of roof drains. plans are marked. | JOHNS | JOHNS | | PRD | C | 5461228 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/31/2017 | water in wall ok @ rm 402, water in wall / ceiling ok @ rm 408, ok dwv in wall / ceiling @ rms 405,406,and 408. vtr. plans are marked. | JOHNS | JOHNS | | PTO | P | 5461224 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 03/29/2017 | ok for north and south 4th floor secondary roof drains. plans are marked. | JOHNS | JOHNS | | PRD | P | 5459157 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/29/2017 | dwv in wall and above ceiling ok for rms 405,409,and mech room. in wall water ok for rms 405,406,and 408. plans are marked. NOTE: VTR, HAMMER AERRESTORS @ BATHROOMS 405 AND 408. | JOHNS | JOHNS | | PTO | P | 5459151 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/28/2017 | DWV ONLY IN LAV WALL ON 4TH FLOOR MENS , ROOM 406 . ON TEST , PLANS MARKED | GABE | GABE | | PTO | P | 5457595 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 03/28/2017 | NOTE : ENTIRE PRIMIARY ROOF RAIN 4TH FLOOR , SECONDARY TO SOUTH ROOM 400 , VENT ON TEST IN 414 VESTIBULE . ALL ON TEST , PLANS ARE MARKED | GABE | GABE | | PRD | P | 5457594 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 03/24/2017 | 1st floor roof drains at rooms 102, 105, and 106 ok, plans marked, note: revise plans to show deck drains instead of trench drains by final. | TAYLOR | TAYLOR | | PRD | P | 5454849 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/09/2017 | all floor sinks for mech room 409 complete, 2 inch vents for rooms 22 and 224 complete. | TAYLOR | TAYLOR | | PTO | P | 5435954 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/08/2017 | H2O in walls and 3 inch drain at tutor room 224 ok. | TAYLOR | TAYLOR | | PTO | P | 5434552 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/02/2017 | 2 inch vent for G.I. ok | TAYLOR | TAYLOR | | PTO | P | 5429361 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 03/02/2017 | roof drains at 2nd level ok, plans marked. | TAYLOR | TAYLOR | | PRD | P | 5429358 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 03/01/2017 | partial roof drains at addition area ok, plans marked. | TAYLOR | TAYLOR | | PRD | P | 5428005 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/01/2017 | G.W. and S.S. piping ok at cafe area. | TAYLOR | TAYLOR | | PTO | P | 5428000 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 02/28/2017 | water mains for sink at room 22 and hose bib next to reading room 24 ok. | TAYLOR | TAYLOR | | PTO | P | 5426942 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/23/2017 | storm riser on 1st floor by room 109 ok, all storm and overflow on 3rd floor ok minus addition, plans marked. | TAYLOR | TAYLOR | | PRD | P | 5422674 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 02/23/2017 | floor sinks at mech room 409, waster and vent risers for mens 405/ womens 406 ok. | TAYLOR | TAYLOR | | PTO | P | 5422664 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/22/2017 | partial roof drains on 3rd floor ok, plans marked. | TAYLOR | TAYLOR | | PRD | P | 5421333 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 02/22/2017 | DWV in walls for mens, womens, vestibule, and janitor rooms on 3rd floor ok, plans marked. | TAYLOR | TAYLOR | | PTO | P | 5421326 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/21/2017 | level 1 roof drains next to vestibule room 100 ok, plans marked. | TAYLOR | TAYLOR | | PRD | P | 5419419 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 02/21/2017 | level 3 H2O ok minus addition. | TAYLOR | TAYLOR | | PTO | P | 5419402 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 02/15/2017 | 2 inch drains at north new addition level 1 ok, DWV at tutors room 224 and technical service room 223A ok, plans marked. | TAYLOR | TAYLOR | | PTO | P | 5416060 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/15/2017 | drains at north new addition on level 1 ok, plans marked. | TAYLOR | TAYLOR | | PRD | P | 5416049 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/09/2017 | roof drain in mech room 15 | TIM | TIM | | PRD | P | 5411512 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 02/09/2017 | dwv mech room 39 h20 room 23a h2o mech room 12 to hall 35 collections h2o to wall hydrant as marked on plan | TIM | TIM | | PTO | P | 5411511 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 02/07/2017 | 2" vents at 012 013 014 and 4" under stairs as marked on plan | TIM | TIM | | PTO | P | 5408823 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/07/2017 | drains at reading room 024 014 as marked on plan | TIM | TIM | | PRD | P | 5408820 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 01/12/2017 | 1-4'' and 2-3'' 2nd floor south end r.d o.k see plans | JOEL | JOEL | | PRD | P | 5388111 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 01/11/2017 | 1st and 2nd floor wtr ok, strom drains 2nd floor area b and d as marked on plans | TIM | TIM | | PTO | P | 5386359 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 01/10/2017 | primary and secondary 1st floor remodel | TIM | TIM | | PRD | P | 5385107 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 01/10/2017 | 2nd floor lav and carrier wet walls in remodel | TIM | TIM | | PTO | P | 5385106 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 12/28/2016 | storm drains in 1st floor bathroom area walls and ceiling, strom drain garden level south side ok plan marked | TED | TED | | PTO | P | 5377837 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 12/21/2016 | bathroom area dwv and water 1st floor ceiling and walls ok, water in ceiling through out 1st floor ok | TED | TED | | PTO | P | 5373395 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 12/20/2016 | field canceled, frozen | TED | TED | | PTO | P | 5372223 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 12/14/2016 | north east storm drain in ceiling of garden level, plan marked | TED | TED | | PTO | P | 5367931 |
HEATING & PLUMBING ENGINEERS, INC | PB | C | 12/02/2016 | under ground complete. | TAYLOR | TAYLOR | | PB | C | 5358630 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 12/02/2016 | DWV and H2O ok at mech room 038 and DWV above ceiling ok at hallway 035. | TAYLOR | TAYLOR | | PTO | P | 5358625 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 12/01/2016 | DWV in walls at workroom 022 ok, above ceiling H2O and DWV ok at janitor 032, mens 036, womens 033. | TAYLOR | TAYLOR | | PTO | P | 5357346 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 11/30/2016 | in walls DWV and H2O at janitor 032, mens 036, and womens 033 at garden level ok. | TAYLOR | TAYLOR | | PTO | P | 5356118 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 11/30/2016 | continuation of garden level ok, see plans. | TAYLOR | TAYLOR | | PB | P | 5356107 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 10/25/2016 | water piping, from new meter location on garden level over head connecting back into existing main that will be removed | TED | TED | | PTO | P | 5326843 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 10/19/2016 | garden level bathrooms and mech. room, plan marked | TED | TED | | PB | P | 5322334 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 10/07/2016 | continuation garden level, plan marked | TED | TED | | PB | P | 5313332 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 09/22/2016 | north east garden level mechanical room floor drains, plan marked | TED | TED | | PB | P | 5299806 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 09/15/2016 | storm drain-west addition to lift tank, sanitary- south west corner mech. room traps to inside wall, plan marked | TED | TED | | PB | P | 5294079 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 09/07/2016 | garden level deep base and risers for storm and sanity | TED | TED | | PB | P | 5286660 |