CRADDOCK DEVELOPMENT COMPANY, INC. | B= | C | 04/10/2018 | | NICK | NICK | | B= | C | 5812950 |
CRADDOCK DEVELOPMENT COMPANY, INC. | BFR | C | 04/10/2018 | | NICK | NICK | | BFR | C | 5812949 |
CRADDOCK DEVELOPMENT COMPANY, INC. | BE | L | 04/04/2018 | Renewed for Full Fee at 4/4/2018 10:03:35 AM (Receipt#1491661) | RITA | RITA | | BE | L | 5807226 |
CRADDOCK DEVELOPMENT COMPANY, INC. | BE | L | 10/02/2017 | Renewed at 10/2/2017 10:39:57 AM | BECKYA | BECKYA | | BE | L | 5641880 |
RCS ELECTRIC | BSP | P | 04/21/2017 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised one-line diagram. | BERTHA | BERTHA | | BSP | P | 5483097 |
MARLER'S PLUMBING & HEATING | BSP | T | 04/17/2017 | PAID (REC#1417685) PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 4-17-17 | TCRIPPEN | TCRIPPEN | | BSP | T | 5477972 |
CRADDOCK DEVELOPMENT COMPANY, INC. | BFR | P | 03/31/2017 | need center restroom spliced and inspected / with completed required inspections frame of office and 2 outside corner restrooms okay. Reviewed Accessible Elements / | NATHAN | NATHAN | | BFR | P | 5461312 |
CRADDOCK DEVELOPMENT COMPANY, INC. | BSP | T | 03/13/2017 | PAID (REC#1409007) ADDITIONAL PLAN REVIEW TIME: $50 From: SHELBY | SHELBY | SHELBY | | BSP | T | 5439228 |
CRADDOCK DEVELOPMENT COMPANY, INC. | BSP | P | 02/27/2017 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Plumbing: plumbing splice 2-27-17 | TCRIPPEN | TCRIPPEN | | BSP | P | 5426289 |
RCS ELECTRIC | BSP | T | 02/27/2017 | PAID (REC#1405602) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Add house panel | SHELBY | SHELBY | | BSP | T | 5426171 |
CRADDOCK DEVELOPMENT COMPANY, INC. | BSP | T | 02/27/2017 | PAID (REC#1405601) PLAN SPLICE FEE: $50 by: BPHILLIPS for Construction: added restroom | BPHILLIPS | BPHILLIPS | | BSP | T | 5425600 |
RCS ELECTRIC | E= | C | 04/05/2018 | OK PER PIC | BRIAN | BRIAN | | E= | C | 5808295 |
RCS ELECTRIC | E= | P | 02/12/2018 | need panel fillers in house panel and units a & b---breaker locks on all units for b.b. heaters----label the panel a.b . ... and label where they feed from----ok to send pics | BRIAN | BRIAN | | E= | P | 5762978 |
RCS ELECTRIC | E= | P | 09/22/2017 | ONLY UNIT B HAS BEEN INSPECTED---NEED BREAKER LOCK ON B.B HEATER--- | BRIAN | BRIAN | | E= | P | 5634344 |
RCS ELECTRIC | EUG | P | 09/22/2017 | FEED TO POLE LIGHTS---AND LIGHT TO LIGHT--OK | BRIAN | BRIAN | | EUG | P | 5634343 |
RCS ELECTRIC | ER | P | 09/22/2017 | SOFFIT OK-- | BRIAN | BRIAN | | ER | P | 5634339 |
RCS ELECTRIC | ES | P | 07/31/2017 | Commercial Service: 400 AMP 4 W --PRE RELEASE ONLY----- | BRIAN | BRIAN | | ES | P | 5580633 |
RCS ELECTRIC | ER | P | 02/22/2017 | WALLS AND HARD LIDS----- | BRIAN | BRIAN | | ER | P | 5421500 |
HOMELAND MECHANICAL LLC | H= | C | 07/19/2017 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5568508 |
HOMELAND MECHANICAL LLC | H= | P | 05/22/2017 | PARTIAL PENDING TAB REPORT FOR OFFICE AREA PER PLAN - REST OK | JERRYF | JERRYF | | H= | P | 5513125 |
HOMELAND MECHANICAL LLC | H= | P | 03/07/2017 | HEATING CONTRACTOR NEEDS TO ATTACH TO REMODEL PERMIT FOR NEW MECHANICAL ITEMS BEING INSTALLED ALSO REMOVE EXHAUST FANS AND TWO VENTS FROM THIS PERMIT.. NOTE: UNIT HEATERS ARE OK AND VENTS.. | LUKE | LUKE | | H= | P | 5433779 |
HOMELAND MECHANICAL LLC | H16 | C | 01/27/2017 | H16 ENTRY FOR RBD NOTES ONLY. RECEIVED CALL FROM DAVE ORAZUM AT CSU AND HE THOUGHT THERE WAS NEW GAS PIPING. INSPECTOR TO CHECK THIS OVER WHEN INSPECTION CALLED. PERMITS WERE OBTAINED AS REPLACEMENTS ONLY.
| JON | JON | | H16 | C | 5433778 |
LANDMARK PLUMBING AND HEATING, INC. | P= | C | 09/28/2017 | corrections made, see images. | TAYLOR | TAYLOR | | P= | C | 5639051 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 09/26/2017 | need approved closet flange, install floor drain receptor, still need 16-18 inches from wall to center of toilet, rest ok. | TAYLOR | TAYLOR | | P= | P | 5637379 |
LANDMARK PLUMBING AND HEATING, INC. | P= | R | 09/21/2017 | PTO inspection was never complete ( need to verify all water piping in ceiling ), re- grade 2 inch vent, need 16-18 from wall to center of toilet, need to verify anchors at closet flange, re- inspect all. | TAYLOR | TAYLOR | | P= | R | 5633024 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 07/10/2017 | in wall DWV and H2O ok. | TAYLOR | TAYLOR | | PTO | P | 5559587 |
LANDMARK PLUMBING AND HEATING, INC. | PB | C | 07/10/2017 | | TAYLOR | TAYLOR | | PB | C | 5559584 |
MARLER'S PLUMBING & HEATING | P= | P | 06/14/2017 | east and west restrooms ok. | TAYLOR | TAYLOR | | P= | P | 5535765 |
MARLER'S PLUMBING & HEATING | P= | P | 06/08/2017 | need trap guards at floor drains, install drain for backflow, need 15 inches from side wall to center of lav at west restroom, terminate pan drain to an approved location at east restroom, expansion needs to be between check valve and water heater. | TAYLOR | TAYLOR | | P= | P | 5529959 |
MARLER'S PLUMBING & HEATING | PTO | P | 03/30/2017 | DWV AND WATER IN WEST BATH AND LAUNDRY ON TEST TO PLAN | GABE | GABE | | PTO | P | 5460364 |
MARLER'S PLUMBING & HEATING | PB | P | 03/30/2017 | DWV TO WEST BATH AND TRENCH DRAIN ON TEST OK TO COVER , | GABE | GABE | | PB | P | 5460362 |
MARLER'S PLUMBING & HEATING | PTO | P | 03/23/2017 | in walls and above hard lid at east unisex restroom ok, note: revise plans to show added utility sink. | TAYLOR | TAYLOR | | PTO | P | 5454395 |
MARLER'S PLUMBING & HEATING | PB | P | 03/23/2017 | east unisex restroom ok, note: revise plans to show added utility sink. | TAYLOR | TAYLOR | | PB | P | 5454394 |