EXECUTIVE CUSTOM CONSTRUCTION, INC. | B= | C | 10/03/2017 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 5642974 |
EXECUTIVE CUSTOM CONSTRUCTION, INC. | B= | P | 09/29/2017 | final OK pending other finals. Additional Inspections Required (computer generated): BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, FRONTIER MECHANICAL SYSTEMS INC Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5640885 |
FRONTIER MECHANICAL SYSTEMS INC | BSP | T | 09/19/2017 | PAID (REC#1454073) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: splice to remove AHU and associated duct | DALEH | DALEH | | BSP | T | 5630008 |
BIBLE ELECTRIC, INC. | BSP | T | 09/18/2017 | PAID (REC#1453493) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised feeder #5 to indicate AL, Panel L indicated as new. | BERTHA | BERTHA | | BSP | T | 5628799 |
EXECUTIVE CUSTOM CONSTRUCTION, INC. | BFR | P | 09/14/2017 | penetrations on west side of wall and head of wall OK / this completes the framing for this job pending other roughs | DANE | DANE | | BFR | P | 5626300 |
EXECUTIVE CUSTOM CONSTRUCTION, INC. | BFR | P | 09/06/2017 | hilti listings for all penetrations and head of wall received / all penetrations on east side of wall OK / still need to inspect all penetrations and head of wall on west side of wall | DANE | DANE | | BFR | P | 5617747 |
EXECUTIVE CUSTOM CONSTRUCTION, INC. | BFR | P | 08/29/2017 | met contractor on site to discuss rated assembly for tenant separation wall / new listed assembly received for 1 hour wall (UL V489) this assembly does work with the american rock that is installed on both sides of wall / discussed need for listings for all types of penetrations in wall and need for engineer judgment for large holes that have been cut in wall and need to be repaired and for steel bracing for bar joists on roof / backing for grab bars now installed OK / discussed accessible elements with contractor / Training with Justin L on VB construction separated use rated assemblies and accessible elements | DANE | DANE | | BFR | P | 5610817 |
EXECUTIVE CUSTOM CONSTRUCTION, INC. | BSP | P | 08/29/2017 | Training with Dane on 5B construction with B occupancy, Separated use and rated assemblies and accessible components | JUSTINL | JUSTINL | | BSP | P | 5610813 |
EXECUTIVE CUSTOM CONSTRUCTION, INC. | BFR | R | 08/28/2017 | tenant separation wall is called out as a U419 1 hour wall and has national gyp installed when the listed assembly calls for USG type X rock / need listings for all penetrations in rated wall including wires, bar joist, sprinkler pipes and also need head of wall detail / need listing for large cut out areas that need to be repaired per the listing / missing backing in both restrooms at 54" from corner on side walls for side wall grab bars / no superintendent on site / need to have electrical inspection | DANE | DANE | | BFR | R | 5609295 |
BIBLE ELECTRIC, INC. | E= | C | 09/29/2017 | | BRET | BRET | | E= | C | 5640919 |
BIBLE ELECTRIC, INC. | E= | P | 09/28/2017 | 15 amp breaker for exhaust fan or provide spec sheet on mop @20 amps, gfci receptacle cannot be behind washer/dryer stack unit use gfci breaker. | BRET | BRET | | E= | P | 5639822 |
BIBLE ELECTRIC, INC. | ER | C | 09/14/2017 | except mc to exhaust fan. | BRET | BRET | | ER | C | 5626090 |
BIBLE ELECTRIC, INC. | ES | P | 09/11/2017 | Commercial Service: 225 amp service needs meter set. INSPECTOR NOTES: change plans cu to al conductors. 225 amp fuses at main not installed at this time. | BRET | BRET | | ES | P | 5621758 |
BIBLE ELECTRIC, INC. | ER | P | 08/29/2017 | walls complete | BRET | BRET | | ER | P | 5610178 |
BIBLE ELECTRIC, INC. | ESL | C | 08/15/2017 | | BRET | BRET | | ESL | C | 5596301 |
FRONTIER MECHANICAL SYSTEMS INC | HC | C | 10/03/2017 | EXISTING METER. | LIDO | LIDO | | HC | C | 5642975 |
FRONTIER MECHANICAL SYSTEMS INC | H= | C | 10/03/2017 | CONFLICTING INFORMATION ON SPLICE ABOUT ROOF TOP UNIT SHOWING NEW , THIS IS A EXISTING UNIT . GAS OK. | LIDO | LIDO | | H= | C | 5642973 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 10/02/2017 | ENGINEER WILL NEED TO CLARIFY WHAT IS GOING ON WITH ROOF TOP AND IF THIS IS NOT A NEW ROOF TOP THE PLANS WILL HAVE TO SHOW ON THE REVISED PLAN AND GO THROUGH PLANS AND REVIEW FOR APPROVAL . SCHEDULE ON NEW SPLICE SHOWS NEW - DATED SEPT/19/2017 | LIDO | LIDO | | H= | P | 5641638 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | C | 09/29/2017 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5640118 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 09/27/2017 | ENGINEER WILL NEED TO CLARIFY WHAT IS GOING ON WITH ROOF TOP . SCHEDULE ON NEW SPLICE SHOWS NEW - SEPT/19/2017 | LIDO | LIDO | | H= | P | 5638959 |
FRONTIER MECHANICAL SYSTEMS INC | HI | C | 09/27/2017 | 10 lb TEST OK . GAS SYSTEM INSTALLED PER PLAN .GAS ON ROOF OK. | LIDO | LIDO | | HI | C | 5638958 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 09/21/2017 | PARTIAL PENDING TAB REPORT - REST OK - PLAN HAS BEEN REVISED | JERRYF | JERRYF | | H= | P | 5633318 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 09/11/2017 | ABOVE CEILING SA / RA AND EXHAUST OK TO WRAP - NEED PLAN REVISED DELETING AHU 1 AND CONDENSER AND SHOWING DUCT AS INSTALLED - WILL NEED ROOF INSPECTION AT FUTURE INSPECTION | JERRYF | JERRYF | | HD | P | 5622218 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | L | 09/06/2017 | CONTRACTOR INSTALLING WATER HEATER VENTS NEEDS TO ADD THEM TO SCOPE OF WORK AND CALL FOR INSPECTION WHEN READY. ONLY LOCK BOX FOUND ON SITE WAS ON FRONT DOOR OF ADJACENT UNIT. CODE GIVEN DID NOT UNLOCK BOX. | NANCY | NANCY | | HD | L | 5618128 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 09/28/2017 | NOTE : ALL HAIR SINKS AND LAVS TEMPERED , AAV FOR ISLAND AT WALL SINK W/ACCESS . ALL TO PLAN | GABE | GABE | | P= | C | 5639826 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | C | 08/29/2017 | NOTE : ALL WATER ON TEST , TO PLAN . AAV AT LOOP VENT , | GABE | GABE | | PTO | C | 5609997 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | P | 08/28/2017 | DWV ON TEST , CHECK VENT TERMINATION AND WATER AT NEXT INSPECTION | GABE | GABE | | PTO | P | 5609005 |
FRONTIER MECHANICAL SYSTEMS INC | PB | C | 08/17/2017 | DWV ON TEST , CORRECTIONS MADE | GABE | GABE | | PB | C | 5598484 |
FRONTIER MECHANICAL SYSTEMS INC | PB | P | 08/16/2017 | LOW TEST , NEED TO CHECK ALL PIPING , WAIVED TRIP FEE THIS TIME ONLY | GABE | GABE | | PB | P | 5598024 |
FRONTIER MECHANICAL SYSTEMS INC | PB | P | 08/15/2017 | low test on main dwv , rest ok . dwv to plan , under slab water ok | GABE | GABE | | PB | P | 5595620 |