AFFORDABLE COMMERCIAL CONSTRUCTION, LLC | B= | C | 05/30/2018 | final OK pending other finals | DANE | DANE | | B= | C | 5858462 |
AFFORDABLE COMMERCIAL CONSTRUCTION, LLC | B= | P | 05/23/2018 | Temp CO: 5/23/2018 ( Expires: 6/22/2018 12:00:00 AM) | JANE | JANE | | B= | P | 5854059 |
AFFORDABLE COMMERCIAL CONSTRUCTION, LLC | B= | P | 05/22/2018 | items corrected / final OK pending other finals. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), BEACON PLUMBING, LLC Plumbing Final Inspection is not Completed yet, FOSTER ELECTRIC CORP Electrical Final Inspection is not Completed yet, MAGNUM EDGE,INC. Mechanical Final Inspection is not Completed yet, REFRIGERATION PLUS, LLC Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5852000 |
AFFORDABLE COMMERCIAL CONSTRUCTION, LLC | B= | P | 05/21/2018 | need to complete Core and Shell permit to complete this permit / women's restroom mirror is above 40" to reflective surface and rear grab bar is in wrong position (must be minimum 12' toward corner from CL of toilet and minimum 24" toward the open side of the toilet from the CL of the toilet) / men's restroom mirror is above 40" to reflective surface and rear grab bar is in wrong position (must be minimum 12' toward corner from CL of toilet and minimum 24" toward the open side of the toilet from the CL of the toilet) / need to complete all other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, BEACON PLUMBING, LLC Plumbing Final Inspection is not Completed yet, FOSTER EL | DANE | DANE | | B= | P | 5850798 |
AFFORDABLE COMMERCIAL CONSTRUCTION, LLC | BFR | P | 04/05/2018 | stamped detail for hard lids and soffits received / hard lids and soffits now OK / grab bar backing installed OK / discussed accessible elements / all framing now OK pending other roughs | DANE | DANE | | BFR | P | 5808843 |
AFFORDABLE COMMERCIAL CONSTRUCTION, LLC | BFR | P | 04/02/2018 | need stamped detail for for how to build and attach all soffits and how to build and attach bathroom hard lids as there is no detail on plans / need to install restroom grab bar backing in both restrooms / all other interior light gauge framing OK pending other rough inspections | DANE | DANE | | BFR | P | 5804829 |
FOSTER ELECTRIC CORPORATION | E= | C | 05/23/2018 | Corrections complete / | ROB | ROB | | E= | C | 5854054 |
FOSTER ELECTRIC CORPORATION | E= | R | 05/22/2018 | DW GFCI not working--2 Refrigs not GFCI protected--All IG recpts under front counter need GFCI protection--Dead FrontsB2-2,B2-35,B2-37 C2-1 not being used and/or not working properly---Installed recpt to replace extension cord in cooler / | ROB | ROB | | E= | R | 5852781 |
FOSTER ELECTRIC CORPORATION | E= | R | 05/21/2018 | can not use extension cord for permanent wiring method in cooler------looked at dining area, rooftop units except exhaust fan, 3 sign lights, em light moved from side to front of building, coolers were ok except extension cord | RANDY | RANDY | | E= | R | 5850906 |
FOSTER ELECTRIC CORPORATION | ER | P | 05/18/2018 | Rough in ok for grid ceiling in kitchen area and front counter wall / | ROB | ROB | | ER | P | 5849878 |
FOSTER ELECTRIC CORPORATION | ER | P | 04/02/2018 | Rough in ok for exterior walls--highlited and dated in pink / | ROB | ROB | | ER | P | 5805662 |
FOSTER ELECTRIC CORPORATION | ER | P | 03/28/2018 | wall and lid partial see plans for locations | BRET | BRET | | ER | P | 5801305 |
MAGNUM EDGE,INC. | H= | C | 05/25/2018 | MECHANICAL FINAL OK. TEST AND BALANCE FOR EF-3 RECEIVED, SEE IMAGES. | NANCY | NANCY | | H= | C | 5855691 |
REFRIGERATION PLUS, LLC | H= | C | 05/22/2018 | REFRIGERATION FINAL OK. | NANCY | NANCY | | H= | C | 5852080 |
MAGNUM EDGE,INC. | H= | P | 05/22/2018 | MECHANICAL FINAL OK PENDING RECEIPT OF BALANCE REPORT FOR EF-3. | NANCY | NANCY | | H= | P | 5852061 |
MAGNUM EDGE,INC. | HD | P | 05/21/2018 | BAGEL OVEN B-VENT MUST BE 1 CONTINUOUS PIECE THROUGH ROOF AND TERMINATE 10' AWAY OR 3' ABOVE ECONOMIZER. LABEL THERMOSTATS TO RTU'S. NEED TO SEE INTERLOCKS FOR BAGEL OVEN. INSTALL REMOTE INDICATORS FOR DUCT DETECTORS. TEST AND BALANCE REPORT FOR EF-3. | DUSTINS | DUSTINS | | HD | P | 5850587 |
MAGNUM EDGE,INC. | HSP | P | 05/21/2018 | TEST AND BALANCE REPORT NEEDS TO SHOW CFM READINGS FOR EF-3. | DUSTINS | DUSTINS | | HSP | P | 5850360 |
MAGNUM EDGE,INC. | HSP | P | 05/18/2018 | LETTER FROM ENGINEER APPROVING GALVANIZED SPIRAL PIPE WITH HIGH TEMPERATURE SEALANT FOR EXHAUST BAGEL OVEN RECEIVED, SEE IMAGES. | NANCY | NANCY | | HSP | P | 5850145 |
MAGNUM EDGE,INC. | HD | P | 05/18/2018 | NO INSPECTION OF BAGEL OVEN OR BAGEL OVEN VENT TODAY. WHEN INSTALLING BAGEL OVEN VENT, VENT MUST TERMINATE 10 FEET AWAY OR 3 FEET ABOVE RTU ECONOMIZER. SUPPORT WATER HEATER VENT PIPES EVERY FOUR FEET PER MANUFACTURER. CHECK ALL JOINTS ON VENT PIPES, ONE ELBOW ON NORTH HEATER APPEARS TO LACK PROPER PRIMER AND GLUE. INSTALL T-STATS, REMOTE INDICATORS, PROVIDE TEST AND BALANCE REPORT. | NANCY | NANCY | | HD | P | 5849353 |
MAGNUM EDGE,INC. | HD | P | 05/11/2018 | CONTRACTOR NEEDS TO LIST COMPLETE SCOPE OF WORK. COMPLETE BAGEL OVEN PER MANUFACTURERS INSTRUCTIONS. CONTACT OVEN MANUFACTURER TO FIND OUT WHAT TYPE OF POSITIVE PRESSURE VENT NEEDS TO BE INSTALLED ON OUTLET SIDE OF INDUCED DRAFT BLOWER. CALL FOR INSPECTION OF WATER HEATER VENTS, HAVE WATER HEATER INSTALLATION INSTRUCTIONS ON SITE AT TIME OF INSPECTION. | NANCY | NANCY | | HD | P | 5842740 |
AMEN PLUMBING- HEATING | HD | P | 05/04/2018 | COMPLETE BAGEL OVEN. SUPPORT FLEX OFF OF GRID CEILING. NEED WATER HEATER VENTS INSTALLED AND INSPECTED. NO ROOF INSPECTION TODAY. | DUSTINS | DUSTINS | | HD | P | 5836115 |
AMEN PLUMBING- HEATING | HI | C | 04/17/2018 | 10 LB TEST OK. INSTALLED AS PER PLAN. STILL NEED TO SEE CONNECTION TO WATER HEATERS AND BAGEL OVEN. BAGEL OVEN MANUFACTURER STATES TO HARD PIPE GAS LINE, NO GAS FLEX ALLOWED. STILL NEED TO SEE ROOF. NOTE: REGULATOR IN CEILING OK. | NANCY | NANCY | | HI | C | 5819605 |
AMEN PLUMBING- HEATING | HD | P | 04/04/2018 | RTU-S 2 AND 3 TRUNK LINES AND LATERALS OK, OK TO WRAP. EXHAUST ABOVE BATHROOMS OK, NO BAGEL OVEN YET, CALL FOR INSPECTION WHEN OVEN ARRIVES ON SITE. NO FLEX, DIFFUSERS OR ROOF YET. | NANCY | NANCY | | HD | P | 5807860 |
AMEN PLUMBING- HEATING | HD | P | 04/02/2018 | NEED REVISED/APPROVED PRINTS FOR NEW WATER HEATERS LOCATION, CORRECT ROOF TOP SCHEDULE AND GAS. NEED REFRIGERATION CONTRACTOR ATTACHED TO PERMIT. THIS CONTRACTOR MUST ADD GAS TO THEIR SCOPE OF WORK. CO2 TANKS BEING INSTALLED? WALL NEAR BAGEL OVEN HAS A PEX WATER LINE INSTALLED IN IT. CAN NOT FIND ANYTHING ON PRINT SHOWING WHAT THE CLEARANCE TO COMBUSTIBLES IS FOR THE BAGEL OVEN. BAGEL OVEN INSTALLATION INSTRUCTIONS NOT ON SITE. COVER WALL AT OWN RISK. RTU-1 SUPPLY AND RETURN OK. BY FINAL INSTALL REMOTE INDICATORS FOR ALL RTU SMOKE DETECTORS.
| NANCY | NANCY | | HD | P | 5805604 |
BEACON PLUMBING, LLC | P= | C | 05/29/2018 | Corrections made. | DANR | DANR | | P= | C | 5857518 |
BEACON PLUMBING, LLC | P= | P | 05/29/2018 | Back flow engineer letter up loaded. | DANR | DANR | | P= | P | 5856921 |
BEACON PLUMBING, LLC | P= | P | 05/21/2018 | Dipper well - ice maker - 3-comp sink - mop sink need back flow protection per drawings P2.0 and P4.1 or engineer change letter, need trap guard in front floor sink. | DANR | DANR | | P= | P | 5850582 |
BEACON PLUMBING, LLC | P= | P | 05/17/2018 | Indirect waste needs proper air gap and run to floor sinks, need backflow for soda, 3 - comp sink needs piped per drawing detail (P4.23 detail 1), leak ice maker supply, ice maker drains need proper grade and air gap, leak coffee supply, support mixing valve by softner, need proper support for all drain lines by softner, access door for valve in wall by 3 comp sink. | DANR | DANR | | P= | P | 5847774 |
BEACON PLUMBING, LLC | P= | R | 05/15/2018 | Not ready, left list with contractor. | DANR | DANR | | P= | R | 5845521 |
AMEN PLUMBING- HEATING | PTO | C | 04/02/2018 | per plan. note: vtr (2), trap primer @ both bath floor drains and water entry floor drains (total of 4), check FINAL WATER CONNECTIONS, WATER HTRS (X2), SOFTNER, R O SYSTEM, ESPRESSO, AND DIPPER SINK @ FINAL | JOHNS | JOHNS | | PTO | C | 5804800 |
AMEN PLUMBING- HEATING | PB | C | 03/05/2018 | ok for test and design per plan for g.w. and s.s. | JOHNS | JOHNS | | PB | C | 5780287 |
BEACON PLUMBING, LLC | XPS | T | 05/08/2018 | PAID (REC#1498896) PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 5-8 -18 | TCRIPPEN | TCRIPPEN | | XPS | T | 5839042 |
REFRIGERATION PLUS, LLC | XMS | P | 05/03/2018 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Revised gas system | JUSTINC | JUSTINC | | XMS | P | 5835315 |
FOSTER ELECTRIC CORPORATION | XES | T | 05/01/2018 | PAID (REC#1498897) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Power and lighting revisions. | BERTHA | BERTHA | | XES | T | 5832586 |
AFFORDABLE COMMERCIAL CONSTRUCTION, LLC | XBS | T | 04/27/2018 | PAID (REC#1498895) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: ove door - add platform on roof | MICHAELA | MICHAELA | | XBS | T | 5830152 |