THOMAS GENERAL CONTRACTORS, INC. | B= | C | 11/20/2018 | Frozen Gold okay all final inspections completed | NATHAN | NATHAN | | B= | C | 6030726 |
THOMAS GENERAL CONTRACTORS, INC. | B= | P | 11/19/2018 | Temp CO: extension ( Expires: 12/19/2018 12:00:00 AM) | GITA | GITA | | B= | P | 6029160 |
THOMAS GENERAL CONTRACTORS, INC. | B= | P | 10/12/2018 | Temp CO: Extension ( Expires: 11/11/2018 12:00:00 AM) | GITA | GITA | | B= | P | 5993688 |
THOMAS GENERAL CONTRACTORS, INC. | B= | P | 08/27/2018 | need core shell permit completed, ice cream shop not ready for final inspection, remaining items in Atomic Cowboy section corrected. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): COOLING CUBED, LLC. Mechanical Final Inspection is not Completed yet, ENVIRONMENTAL HTG & AIR COND Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 5946256 |
THOMAS GENERAL CONTRACTORS, INC. | B= | P | 08/14/2018 | Temp CO: all subs has partials on finals and external agencies are complete ( Expires: 9/13/2018 12:00:00 AM) | GITA | GITA | | B= | P | 5934084 |
THOMAS GENERAL CONTRACTORS, INC. | B= | P | 08/13/2018 | need all completed required inspections, need hardware installed at outside stair door free swinging at this time / ice cream store area blocked off and not ready, need letter for steel canopies over patio / install 2nd handrail at servers stairs / need handrails at ends of platforms and ramped floors / complete all restroom signage / complete upstairs restroom. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, COOLING CUBED, LLC. Mechanical Final Inspection is not Completed yet, DILLER ELECTRIC Electrical Final Inspection is not Completed yet, ENVIRONMENTAL HTG & AIR COND Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is | NATHAN | NATHAN | | B= | P | 5931863 |
THOMAS GENERAL CONTRACTORS, INC. | BFR | P | 08/01/2018 | upper level garage door to patio framed sills / discussed core/shell permit and tenant finish TCO possible phased and plan needed for phased CO, discussed CO2 deferred submittal still not done. | NATHAN | NATHAN | | BFR | P | 5920825 |
THOMAS GENERAL CONTRACTORS, INC. | BIN | C | 08/01/2018 | insulation at upper stair doghouse walls and ceiling okay / remaining insulation completed. | NATHAN | NATHAN | | BIN | C | 5920805 |
THOMAS GENERAL CONTRACTORS, INC. | BFR | P | 06/28/2018 | 2nd floor interior non bearing wall light steel frame okay with completed required inspections, | NATHAN | NATHAN | | BFR | P | 5888273 |
THOMAS GENERAL CONTRACTORS, INC. | BFR | P | 05/11/2018 | 1st floor non structural light steel and wood framing with completed required inspections okay, Reviewed Accessible Elements / | NATHAN | NATHAN | | BFR | P | 5842585 |
DILLER ELECTRIC LLC | E= | C | 08/16/2018 | | GARYL | GARYL | | E= | C | 5935962 |
DILLER ELECTRIC LLC | E= | P | 08/15/2018 | 2--RTU's, #1 100 amp., fuses and breaker, #2 50 amp fuses, 60 amp breaker, 4-exhaust fans, only left to do is label main panel for restaurant RTU's etc,,,, | GARYL | GARYL | | E= | P | 5935363 |
DILLER ELECTRIC LLC | E= | P | 08/09/2018 | Need more info about splice, | GARYL | GARYL | | E= | P | 5929074 |
DILLER ELECTRIC LLC | E= | P | 08/08/2018 | Went over various areas needed for partial inspection to be able to train, recept's in food prep area--all gfci and okay NOT READY for any kind of personal training | GARYL | GARYL | | E= | P | 5927357 |
DILLER ELECTRIC LLC | EUG | P | 08/02/2018 | all slab work in Patio is okay to cover | GARYL | GARYL | | EUG | P | 5922288 |
DILLER ELECTRIC LLC | ER | P | 07/16/2018 | Kitchen ceilings only, marked/dated on Markos prints | GARYL | GARYL | | ER | P | 5904053 |
DILLER ELECTRIC LLC | ER | P | 06/29/2018 | 2nd floor, patio ceiling lights, mc rerouted under beams and okay | GARYL | GARYL | | ER | P | 5890315 |
DILLER ELECTRIC LLC | ER | P | 06/26/2018 | second floor for office / bathrooms / bar area for walls only | CRAIG | CRAIG | | ER | P | 5885438 |
DILLER ELECTRIC LLC | EP | P | 06/06/2018 | PANELS: A, K2, K1, MSB, H--Hse | GARYL | GARYL | | EP | P | 5866355 |
DILLER ELECTRIC LLC | ER | P | 05/29/2018 | one wall only, moved switches and same wall has a panel in it | GARYL | GARYL | | ER | P | 5857546 |
DILLER ELECTRIC LLC | ER | P | 05/25/2018 | marked in pink and dated on prints | GARYL | GARYL | | ER | P | 5856279 |
DILLER ELECTRIC LLC | ER | P | 05/08/2018 | walls/ceilings, hard lids, marked/dated on prints | GARYL | GARYL | | ER | P | 5839166 |
DILLER ELECTRIC LLC | ESL | P | 04/19/2018 | seating and bar slab | GARYL | GARYL | | ESL | P | 5821779 |
DILLER ELECTRIC LLC | ESL | P | 04/03/2018 | all eug on inside of building EXCEPT 1 run of pvc from sales (POS) to outside sign lighting | GARYL | GARYL | | ESL | P | 5806119 |
LANDMARK PLUMBING AND HEATING, INC. | H= | C | 11/19/2018 | | JERRYF | JERRYF | | H= | C | 6029100 |
LANDMARK PLUMBING AND HEATING, INC. | HI | C | 11/19/2018 | ALL LABELS / REGULATORS AND PLAN SPLICE ARE COMPLETE | JERRYF | JERRYF | | HI | C | 6029095 |
LANDMARK PLUMBING AND HEATING, INC. | H= | P | 10/12/2018 | STILL NEED PLAN SPLICE - | JERRYF | JERRYF | | H= | P | 5993693 |
ALNOR INC. | H= | C | 09/05/2018 | | JERRYF | JERRYF | | H= | C | 5954738 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | H= | C | 08/28/2018 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5947454 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HSP | P | 08/22/2018 | ALL PLAN REVISIONS ARE COMPLETE - STILL NEED TAB REPORT | JERRYF | JERRYF | | HSP | P | 5942414 |
ALNOR INC. | H= | P | 08/22/2018 | ALL COMPLETE | JERRYF | JERRYF | | H= | P | 5942400 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | H= | P | 08/16/2018 | PARTIAL PENDING REVIEWING ALL PLAN SPLICES / TAB REPORT AND CONSULT WITH SENIOR INSPECTOR | JERRYF | JERRYF | | H= | P | 5936601 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HV | C | 08/16/2018 | NEED CONSULT WITH SENIOR INSPECTOR PREVIOUS NOTES AND REVIEW ALL PLAN SPLICES - MORE NOTES TO FOLLOW ON 8/17 NOTES: WATER HEATER VENTS OK | JERRYF | JERRYF | | HV | C | 5936579 |
LANDMARK PLUMBING AND HEATING, INC. | HC | C | 08/10/2018 | OK FOR 2# METER RELEASE | JERRYF | JERRYF | | HC | C | 5929986 |
LANDMARK PLUMBING AND HEATING, INC. | HI | P | 08/09/2018 | STILL NEED ALL LABELS AT INTERIOR PIPING - WATER HEATERS / VENTS AND GAS TO SAME - NEED PLAN REVISED DELETING GAS TO PIZZA OVENS NOTES: COOK LINE IS COMPLETE | JERRYF | JERRYF | | HI | P | 5928906 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | H= | P | 08/08/2018 | NEED THE FOLLOWING - ALL PLAN REVISIONS APPROVED - CORRECT GREASE WRAP PILLOWS AT GREASE DUCT ACCESS DOOR AND INSTALL STEEL PLATE ON SAME - UNDER CUT ALL RESTROOM AND OFFICE DOORS 1" FOR RETURN AIR PATH - TAB REPORT NOTES: INTERLOCKS ARE COMPLETE | JERRYF | JERRYF | | H= | P | 5927361 |
ALNOR INC. | H= | P | 08/08/2018 | PARTIAL PENDING THE FOLLOWING - COMPLETE 2 ICE MAKERS AND CLAIM ON PERMIT AND CALL INSPECTIONS - COMPLETE ALL DRAINS | JERRYF | JERRYF | | H= | P | 5927356 |
ALNOR INC. | HRP | P | 07/30/2018 | 5 PRESSURE TESTS AND PIPING OK PER PLAN | JERRYF | JERRYF | | HRP | P | 5917670 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 07/13/2018 | ALL SA / RA RUN OUTS AND GRILLES IN GRID CEILING AREA'S | JERRYF | JERRYF | | HD | P | 5902226 |
LANDMARK PLUMBING AND HEATING, INC. | H= | P | 07/13/2018 | PRESSURE TEST OK / STILL NEED ALL COOK LINE - REGS. LABELS AND VENTS | JERRYF | JERRYF | | H= | P | 5902223 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 07/12/2018 | RECEIVED MANUFACTURE LETTER FOR CHEESE MELTER / NEED TO VERIFY WITH SENIOR IF LETTER IS OK .GREASE DUCT WRAP IS STILL QUESTIONABLE AT SPLIT FITTING / HOW IS THIS GOING TO BE SECURED TO GREASE DUCT ? NEED DETAIL ON HOW THE TWO HOOD WILL BE CONNECTED AND SECURED TOO EACH AND HOW THE CHEESE MELTER SHELF WILL BE INSTALLED AND SECURED AND HOW THE SPACE BETWEEN THE HOODS WILL COVERED . DUCT ROUGH ABOVE 2ND FLOOR BATHROOMS 203 , 204 HARD LID OK | LIDO | LIDO | | HD | P | 5900464 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HSP | P | 06/11/2018 | PLANS DO NOT INDICATE TYPE 1 DOUBLE CANOPY HOOD INSTALLATION WITH 8 INCHES OF SPACE BETWEEN HOODS. THIS CHANGES OVER ALL HOOD AND CANOPY FOOTPRINT. NEED ENGINEER TO ADDRESS THIS INSTALLATION. APPEARS A GAS FIRED SALAMANDER WILL BE INSTALLED BETWEEN HOODS WITH NO DETAILS FOR THIS INSTALLATION. ALSO QUESTION GREASE DUCT WRAP AT THE GREASE DUCT SPLIT FITTING ON TOP OF HOODS. | JON | JON | | HSP | P | 5871069 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 06/11/2018 | OK TO WRAP MAKE UP AIR ONLY. SEE HSP INSPECTION ENTRY DATED TODAY. | JON | JON | | HD | P | 5871063 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 06/06/2018 | GREASE DUCT LIGHT TEST OK ON SMALL HOOD OK FOR WRAP - NEED ALL NEW INSTALLED MATERIALS IN RA PLENUM PROTECTED TO 25/50 | JERRYF | JERRYF | | HD | P | 5866363 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | L | 06/05/2018 | NEED CONSULT WITH SENIOR INSPECTOR ON RETURN PLENUM IN KITCHEN AREA - FOUND SEVERAL HOLES STOPPED INSPECTION | JERRYF | JERRYF | | HD | L | 5864853 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HSP | P | 06/05/2018 | NEED CONTRACTOR ADDRESS AND ENGINEER TO ADDRESS SHEET M4.2 ON HOOD DRAWINGS THAT SHOWS HOODS ARE BUTTED TOGETHER WHERE AS INSTALLED THERE IS AN 8" GAP BETWEEN HOODS | JERRYF | JERRYF | | HSP | P | 5864145 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | L | 06/04/2018 | NEED CONSULT WITH SENIOR INSPECTOR ON LARGE GAP AT CENTER OF HOODS AND MIDDLE HOOD WALL SYSTEM AND PLAN SHOWS HOODS TIGHT TOGETHER - NEED GREASE DUCT TO HAVE SMOOTH INTERIOR FINISH / HAS GREASE DAMS AT BOTTOM OF DROP THROUGH ROOF - STOPPED INSPECTION - WILL NEED PLANS REVISED TO SHOW GREASE DUCT SIZING AS INSTALLED | JERRYF | JERRYF | | HD | L | 5863080 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 05/24/2018 | LIGHT TEST OK ON DOUBLE HOOD OK FOR WRAP | JERRYF | JERRYF | | HD | P | 5854765 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | L | 05/23/2018 | STOPPED INSPECTION SEVERAL HOLES - CONTRACTOR WILL NEED TO DARKEN AREA AT FRONT HOOD FOR LIGHT TEST - RE INSPECT ALL | JERRYF | JERRYF | | HD | L | 5853458 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 05/17/2018 | NEED CONSULT WITH SENIOR INSPECTOR ON GREASE DUCT INSPECTION ((((( SA AND EXHAUST ABOVE HARD LID AREAS IN ICE CREAM AREA AND RESTROOMS OK | JERRYF | JERRYF | | HD | P | 5848275 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 04/26/2018 | LIGHT TEST OK ON ROOF DROPS OK TO WRAP | JERRYF | JERRYF | | HD | P | 5828054 |
LANDMARK PLUMBING AND HEATING, INC. | P= | C | 11/20/2018 | Correction made
| SHANEN | SHANEN | | P= | C | 6030460 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 11/19/2018 | Need splice in system | SHANEN | SHANEN | | P= | P | 6029149 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 10/12/2018 | Splice still in plans cannot final until released | SHANEN | SHANEN | | P= | P | 5992948 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 08/17/2018 | Still need revisions for roof drains, rest OK | SHANEN | SHANEN | | P= | P | 5937566 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | C | 08/10/2018 | Upper level restroom under floor DWV test OK | SHANEN | SHANEN | | PTO | C | 5930175 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 08/10/2018 | Partial for TCO, no hot water re-inspect all | SHANEN | SHANEN | | P= | P | 5930174 |
LANDMARK PLUMBING AND HEATING, INC. | PRD | P | 08/09/2018 | Need engineer approval and plan splice for changes to piping. 4" over head piping not shown on drawings. (P2.0). Drawing shows each drain stubbing out individually. | DANR | DANR | | PRD | P | 5928773 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 08/09/2018 | Need inspection dwv under bathrooms, rest ok. | DANR | DANR | | PTO | P | 5928735 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 08/09/2018 | Field cancel not ready, no water, re-inspect all. | DANR | DANR | | P= | P | 5928713 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 06/20/2018 | Upper level rest rooms domestic water test OK | SHANEN | SHANEN | | PTO | P | 5879499 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 06/19/2018 | Upper and lower level bar area in wall water distribution test OK, upper level restrooms in wall DWV test OK | SHANEN | SHANEN | | PTO | P | 5878247 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 06/18/2018 | Field canceled | SHANEN | SHANEN | | PTO | P | 5876961 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 05/10/2018 | 1" water lines from water heater to keyed note 9 page P3.1 test OK | SHANEN | SHANEN | | PTO | P | 5840779 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 05/09/2018 | Grid C.1 -1 to C.1 - 4 DWV and water distribution test OK, secure closet flanges, | SHANEN | SHANEN | | PTO | P | 5839816 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | L | 05/08/2018 | Field canceled | SHANEN | SHANEN | | PTO | L | 5838440 |
LANDMARK PLUMBING AND HEATING, INC. | PB | C | 04/24/2018 | sleeve ok, revise plans by final. | TAYLOR | TAYLOR | | PB | C | 5825053 |
LANDMARK PLUMBING AND HEATING, INC. | PB | P | 04/19/2018 | H2O and 3 inch stack at westside ok. | TAYLOR | TAYLOR | | PB | P | 5821134 |
LANDMARK PLUMBING AND HEATING, INC. | PB | P | 04/12/2018 | drinking fountain drain ok, H2O under floor at dishwashing station, hand sink, drinking fountain, and seating area 3 ok, note: need to revise plans for drinking fountain connecting to 2 inch G.W. | TAYLOR | TAYLOR | | PB | P | 5815059 |
LANDMARK PLUMBING AND HEATING, INC. | PB | P | 03/28/2018 | kitchen and cooler area's ok, note: need minimum 5 inch sleeve for 3 inch stack for 2nd floor. | TAYLOR | TAYLOR | | PB | P | 5801069 |
LANDMARK PLUMBING AND HEATING, INC. | PB | P | 03/19/2018 | S.S and grease risers ok, mens, womens, serving counter, and mop sink also ok. | TAYLOR | TAYLOR | | PB | P | 5792085 |
LANDMARK PLUMBING AND HEATING, INC. | PB | P | 03/16/2018 | DWV at bar area ok. | TAYLOR | TAYLOR | | PB | P | 5790799 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | XMS | P | 11/16/2018 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: no revisions to mechanical under this splice | DALEH | DALEH | | XMS | P | 6027739 |
LANDMARK PLUMBING AND HEATING, INC. | XPS | P | 09/17/2018 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Plumbing: plumbing splice 9-17-18 | TCRIPPEN | TCRIPPEN | | XPS | P | 5967275 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | XMS | T | 08/16/2018 | PAID (REC#1527773) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: delta 10 | DALEH | DALEH | | XMS | T | 5935929 |
DILLER ELECTRIC LLC | XES | T | 08/10/2018 | PAID (REC#1526054) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Added 3 pizza ovens and KEF. | BERTHA | BERTHA | | XES | T | 5930261 |
DILLER ELECTRIC LLC | XES | T | 08/10/2018 | PAID (REC#1526054) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Added POS, revised lighting, revised Panel A. | BERTHA | BERTHA | | XES | T | 5930102 |
THOMAS GENERAL CONTRACTORS, INC. | XBS | P | 04/24/2018 | PLAN SPLICE: (No Fee) by: DANM for Construction: Revised number of can lights on RCP | DANM | DANM | | XBS | P | 5825183 |
DILLER ELECTRIC LLC | XES | T | 04/11/2018 | PAID (REC#1493251) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: As builts | SHELBY | SHELBY | | XES | T | 5814408 |
THOMAS GENERAL CONTRACTORS, INC. | XMS | P | 04/11/2018 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Mechanical: plumbing splice 4-11-18 | TCRIPPEN | TCRIPPEN | | XMS | P | 5814314 |
THOMAS GENERAL CONTRACTORS, INC. | XBS | P | 04/11/2018 | PLAN SPLICE: (No Fee) by: SHELLEY for Construction: Eliminated door 107, add entry wall, revise 2nd level restroom ceiling height | SHELLEY | SHELLEY | | XBS | P | 5814238 |