WD CONSULTING LLC | B= | C | 12/06/2018 | All other required Final inspections are complete. (This is a computer generated result) | NICK | NICK | | B= | C | 6044285 |
WD CONSULTING LLC | B= | P | 11/28/2018 | . Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet. | NICK | NICK | | B= | P | 6036015 |
WD CONSULTING LLC | B= | P | 10/19/2018 | Temp CO: TCO OK per Nick & Sally. Awaiting fire alarm dialer inspection. ( Expires: 11/18/2018 12:00:00 AM) | DBURGESS | DBURGESS | | B= | P | 5999761 |
WD CONSULTING LLC | B= | P | 09/21/2018 | Temp CO: TCO OK per Nick, SWR & CSFD ( Expires: 10/21/2018 12:00:00 AM) | DBURGESS | DBURGESS | | B= | P | 5972895 |
WD CONSULTING LLC | B= | P | 09/13/2018 | Building final OK pending all other finals complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet, External Agency Inspection Z= by WOODLAND PARK is not Completed yet (Contact: Dave Burgess at 719-687-5202), FOSTER ELECTRIC CORP Electrical Final Inspection is not Completed yet, RESCUE MECHANICAL, INC. Mechanical Final Inspection is not Completed yet, TRI-STAR MECHANICAL Plumbing Final Inspection is not Completed yet. | NICK | NICK | | B= | P | 5964822 |
WD CONSULTING LLC | BFR | C | 09/13/2018 | | NICK | NICK | | BFR | C | 5964805 |
WD CONSULTING LLC | BFR | P | 04/23/2018 | Frame OK / Reviewed accessible elements / Need all MEP's complete | NICK | NICK | | BFR | P | 5823706 |
FOSTER ELECTRIC CORPORATION | E= | C | 10/01/2018 | | BRIAN | BRIAN | | E= | C | 5982149 |
FOSTER ELECTRIC CORPORATION | E= | P | 09/11/2018 | label where transformer is fed from, panel schedules, voltage colors, AIC on panels above 10K, strap flex on humidifier, cb filler plates on R1F6C, furniture not installed on 2nd,4th floors, | JOHNN | JOHNN | | E= | P | 5961948 |
FOSTER ELECTRIC CORPORATION | EP | P | 08/03/2018 | studio transformer needs #2cu ssb to sec panel, at least 8 handle ties,-------label all panel schedules,label AIC at each panel above 10k, confirm proper branch cb AIC rating,------looked at panels: studio, I.T., R2D5A, R3D6A | JOHNN | JOHNN | | EP | P | 5924066 |
FOSTER ELECTRIC CORPORATION | ER | P | 08/01/2018 | walls and ceilings complete, panels:R1D6B, has 22k cb's, need AIC label on panel and check size, R1F6C, has 10k cb's, label AIC on panel, and check size, | JOHNN | JOHNN | | ER | P | 5921370 |
FOSTER ELECTRIC CORPORATION | ER | C | 08/01/2018 | FIRE ALARM INSPECTION: | JOHNN | JOHNN | | ER | C | 5921368 |
FOSTER ELECTRIC CORPORATION | E= | C | 08/01/2018 | FIRE ALARM INSPECTION: | JOHNN | JOHNN | | E= | C | 5921369 |
FOSTER ELECTRIC CORPORATION | ER | P | 07/26/2018 | FIRE ALARM INSPECTION: 1st floor: server rm not ready, need boxes and support wires, do not set tile, rm 119,126, need boxes and support wires, 2nd floor: not ready, missing 3 boxes and support wires, leave tiles open, 3rd,4th floors,ok. | JOHNN | JOHNN | | ER | P | 5915702 |
FOSTER ELECTRIC CORPORATION | ER | P | 07/26/2018 | 1st floor: missing large j box cover,leave tile open, bath rm missing large cover, leave tile open, server rm not ready:open boxes and pipes need wires pulled, do not set tiles, 2nd floor:2 lights in break rm need clips or screws, leave tiles open, 3rd,4th floor,ok | JOHNN | JOHNN | | ER | P | 5915701 |
FOSTER ELECTRIC CORPORATION | ER | P | 07/25/2018 | FIRE ALARM INSPECTION: see plans: west of highlighted, support FA cables up off grid, all FA boxes need support wires, end of hall has large coil of FA cable, where is this being run to? | JOHNN | JOHNN | | ER | P | 5914255 |
FOSTER ELECTRIC CORPORATION | ER | P | 07/25/2018 | see plans: west of highlight, support mc cable,FA,data/com up off grid, any ceiling boxes need support wire, missing exit box,cable hanging, many T grids missing on 2/2 fixtures, 1 room locked, walk entire project before inspections to make sure areas are ready. | JOHNN | JOHNN | | ER | P | 5914252 |
FOSTER ELECTRIC CORPORATION | E= | R | 06/25/2018 | not ready for final. | JOHNN | JOHNN | | E= | R | 5884988 |
FOSTER ELECTRIC CORPORATION | ER | P | 06/25/2018 | consult, not ready for electrical grid inspection, FA not installed in grid. | JOHNN | JOHNN | | ER | P | 5884986 |
FOSTER ELECTRIC CORPORATION | ER | P | 04/25/2018 | FIRE ALARM INSPECTION: all walls,1,2,3 floors, ok to close walls | JOHNN | JOHNN | | ER | P | 5826254 |
FOSTER ELECTRIC CORPORATION | ER | P | 04/24/2018 | all walls:1,2,3 floors, need to attach FA permit, all FA stub ups,ok | JOHNN | JOHNN | | ER | P | 5826016 |
FOSTER ELECTRIC CORPORATION | ER | P | 04/23/2018 | ----------------------------------Partial ER for areas identified by John under previous inspection, Foster to attach for FA work. Boxes and conduit stubs at this time only. Ok to rock these walls-------------------------------- | DEAN | DEAN | | ER | P | 5824646 |
FOSTER ELECTRIC CORPORATION | ER | R | 04/20/2018 | need fire alarm permit attached before proceeding with sheet rock, 1st floor: S.W walls,power and FA stub ups,complete, approx 8 boxes need grd screw,check next time out, 2nd floor,walls,see plans,FA not ready, 3rd floor see plans,FA not ready, Discussed accessibly requirements with contractor / | JOHNN | JOHNN | | ER | R | 5823394 |
RESCUE MECHANICAL, INC. | H= | C | 10/11/2018 | ENGINEER LETTER FOR TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5991563 |
RESCUE MECHANICAL, INC. | H= | P | 09/14/2018 | SEVERAL READINGS OUTSIDE +/- 10% NEED ENGINEER TO APPROVE STAMP AND APPROVE OR SUBMIT NEW TAB REPORT | JERRYF | JERRYF | | H= | P | 5965023 |
RESCUE MECHANICAL, INC. | H= | P | 07/26/2018 | PARTIAL PENDING TAB REPORT NOTES: NO RAILING REQUIRED AT CONDENSER - ALL SA / RA GRILLES IN ALL AREA'S ARE COMPLETE | JERRYF | JERRYF | | H= | P | 5914932 |
RESCUE MECHANICAL, INC. | HD | P | 05/17/2018 | ABOVE CEILING SA / RA MAINS AND RUN OUTS OK PER REVISED PLAN BDA PAGE 109 FOR BASEMENT LEVEL SERVER / PRINTING AND IT ROOMS - SA DUCT THROUGH FLOOR TO MAIN FLOOR PER REVISED PLAN ON BDA PAGE 109 | JERRYF | JERRYF | | HD | P | 5847897 |
RESCUE MECHANICAL, INC. | HWP+ | P | 05/17/2018 | PRESSURE TEST OK AND PIPING PER PLAN FOR CARC UNIT IN SERVER ROOM | JERRYF | JERRYF | | HWP+ | P | 5847896 |
RESCUE MECHANICAL, INC. | HD | P | 04/25/2018 | ABOVE CEILING SA MAINS AND RUN OUTS OK TO WRAP FROM VAV BOXES IN PRODUCTION AREA AND CORRIDOR ON BASEMENT 1ST FLOOR | JERRYF | JERRYF | | HD | P | 5826717 |
RESCUE MECHANICAL, INC. | HRP | P | 04/20/2018 | PRESSURE TEST AND PIPING OK TO INSULATE AT CRAC UNIT - STILL NEED ALL TIE INS - ADD HUMIDIFIER TO PERMIT | JERRYF | JERRYF | | HRP | P | 5822467 |
RESCUE MECHANICAL, INC. | HD | P | 04/20/2018 | ABOVE CEILING SUPPLY MAIN AND RUN OUTS AT TEMPERING FCU UNIT 24 OK TO WRAP | JERRYF | JERRYF | | HD | P | 5822461 |
RESCUE MECHANICAL, INC. | HD | P | 04/16/2018 | ABOVE CEILING LOW PRESSURE SA / RA MAINS AND RUN OUTS IN THE FOLLOWING ROOMS OK - 128 - 132 - 131 - 133 - 134 - 135 - 130C - STUDIO | JERRYF | JERRYF | | HD | P | 5817749 |
RESCUE MECHANICAL, INC. | HD | P | 04/02/2018 | UPDATE FROM 4-2-18 INSPECTION, PLANS TO BE REVISED FOR ALL CHANGES ON PIPING AND DUCTWORK DID NOTICE A CHANGE FOR INTERIOR UNIT 1 ON PIPING, MAY BE MORE REVISIONS TO FOLLOW. OK TO WRAP ALL DUCTWORK EVENT AREA ONLY THAT MATCHES PLANS. WILL NEED TO SEE ALL FLEX AND DIFFUSERS BEFORE COVER AND ALL MATERIALS TO BE PLENUM RATED.... NO PLANS ON SITE, PLANS NOT AVAILABLE ON COMPUTER. NEED REVIEW PLANS AT OFFICE AND ADD INSPECTION RESULTS AT THAT TIME | JON | JON | | HD | P | 5804998 |
RESCUE MECHANICAL, INC. | HWP | P | 04/02/2018 | TEST AND PIPING OK TO INSULATE ON NOTE 16 FOR RELOCATED VAV. PIPING TO BE ADDED TO SCOPE OF WORK SHEET MH-100 | JON | JON | | HWP | P | 5808786 |
TRI-STAR MECHANICAL | P= | C | 10/09/2018 | Corrections made, images received | SHANEN | SHANEN | | P= | C | 5989298 |
TRI-STAR MECHANICAL | P= | P | 08/29/2018 | Need lav guards and mixing valves at lavs per fixture schedule. | SHANEN | SHANEN | | P= | P | 5949628 |
TRI-STAR MECHANICAL | PTO | P | 05/17/2018 | PP101, grid C2 - D4 domestic water test and design OK per splice | SHANEN | SHANEN | | PTO | P | 5847836 |
TRI-STAR MECHANICAL | PTO | P | 04/05/2018 | lavs at mens restroom 111, 3/4 inch condensate and 2 inch pump discharge lines ok for humidifiers. | TAYLOR | TAYLOR | | PTO | P | 5809336 |
TRI-STAR MECHANICAL | XPS | T | 05/02/2018 | PAID (REC#1500850): PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 5-2-18 | TCRIPPEN | TCRIPPEN | | XPS | T | 5833256 |
RESCUE MECHANICAL, INC. | XMS | P | 05/01/2018 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Revised CRAC unit schedule and layout revisions | JUSTINC | JUSTINC | | XMS | P | 5832870 |
FOSTER ELECTRIC CORPORATION | XES | T | 04/30/2018 | PAID (REC#1508568) PLAN SPLICE FEE: $75 by: BERTHA for Electrical: Numerous power and lighting revisions. Updated panel schedules. | BERTHA | BERTHA | | XES | T | 5831605 |