DOUBLE DIAMOND ENTERPRISES, INC | B= | C | 07/13/2020 | Pics of building final inspection corrections on file. Building final complete. | CHUCK | CHUCK | | B= | C | 6634492 |
DOUBLE DIAMOND ENTERPRISES, INC | B= | P | 07/08/2020 | Thermostat > 48" AFF (55") - owner states he will install a locked enclosure for unit / Accessible mirror installed > 40" to reflective surface AFF (42") - Will accept uploaded pics for corrections // Rest of building final OK. -- Schedule a new Building Final when above items are complete. | CHUCK | CHUCK | | B= | P | 6631255 |
DOUBLE DIAMOND ENTERPRISES, INC | BSP | P | 01/31/2020 | Rock and rock attachment ok | TIMOTHYS | TIMOTHYS | | BSP | P | 6471553 |
DOUBLE DIAMOND ENTERPRISES, INC | BIN | C | 01/02/2020 | Received spray foam es report and installers certificate - Insulation matches revised comcheck requirements | TIMOTHYS | TIMOTHYS | | BIN | C | 6441652 |
DOUBLE DIAMOND ENTERPRISES, INC | BIN | R | 12/17/2019 | Spray foam installed on envelope of entire building (roof/walls) - Continuous spray foam and fiberglass insulation do not match ComCheck as submitted and approved - Please update and re-submit to RBD. | CHUCK | CHUCK | | BIN | R | 6430414 |
DOUBLE DIAMOND ENTERPRISES, INC | BSP | P | 12/17/2019 | Shower membrane/liner OK. | CHUCK | CHUCK | | BSP | P | 6430413 |
DOUBLE DIAMOND HOMES, INC. | BFR | C | 12/11/2019 | Received engineers letter approving framing changes called out 8/29/19 | TIMOTHYS | TIMOTHYS | | BFR | C | 6423332 |
DOUBLE DIAMOND ENTERPRISES, INC | BFR | R | 08/29/2019 | Framing is detailed to be 2x4 wood stud construction at 16" o.c. for all interior partitions with a suspended ceiling system in the B occupancy area - Wall framing on site is a combination of light/heavy 18 gauge metal studs at 16" o.c. with an 18 gauge ceiling joists bearing on heavy gauge walls - Framing layout mirrors plan on file - Need to update plans to show change of material and load path for walls and ceilings / Discussed accessible elements. | CHUCK | CHUCK | | BFR | R | 6319369 |
DOUBLE DIAMOND HOMES, INC. | BFI | C | 11/15/2018 | R10 installed / | BOBF | BOBF | | BFI | C | 6026586 |
DOUBLE DIAMOND HOMES, INC. | BFR | P | 11/14/2018 | exterior steel structure okay / Reviewed Accessible Elements / | BOBF | BOBF | | BFR | P | 6025619 |
DOUBLE DIAMOND HOMES, INC. | BFN | C | 11/14/2018 | open hole 5000# and letter for pilasters and piers on file | BOBF | BOBF | | BFN | C | 6025608 |
POLARIZED ELECTRIC INC | E= | C | 05/27/2020 | | TOMC | TOMC | | E= | C | 6583975 |
POLARIZED ELECTRIC INC | EUG | C | 05/15/2020 | 2 - 3/4" pvc , 1 - 1" for future | TOMC | TOMC | | EUG | C | 6573075 |
POLARIZED ELECTRIC INC | ES | C | 08/19/2019 | Commercial Service: 300 amp ---- no action needed 2 - main lug panels and 2 sub-panels | TOMC | TOMC | | ES | C | 6305206 |
POLARIZED ELECTRIC INC | ER | C | 08/19/2019 | walls and ceilings ---- 2 - 100 amp sub-panels | TOMC | TOMC | | ER | C | 6305203 |
POLARIZED ELECTRIC INC | EE | C | 07/01/2019 | | TERRI | TERRI | | EE | C | 6249687 |
POLARIZED ELECTRIC INC | ES | C | 01/09/2019 | Commercial Service: 300 amp--- ok to main disconnect per Tom; went to wrong utility company | MATTHEW | MATTHEW | | ES | C | 6073029 |
POLARIZED ELECTRIC INC | ES | P | 12/17/2018 | Commercial Service: 300 amp ---- ok to main disconnect | TOMC | TOMC | | ES | P | 6054965 |
POLARIZED ELECTRIC INC | ES | R | 12/14/2018 | seal nipple, gec to building steel and ground rods must terminate at main disconnect, where is the ufer connection no history of ufer inspection | BRET | BRET | | ES | R | 6053266 |
POLARIZED ELECTRIC INC | ESL | C | 11/12/2018 | east end of building done in GRC | TOMC | TOMC | | ESL | C | 6022660 |
RESCUE MECHANICAL, INC. | H= | C | 07/08/2020 | GAS AND MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6629786 |
RESCUE MECHANICAL, INC. | H= | P | 07/07/2020 | CONTRACTOR PROVIDED STAMPED ENGINEER LETTER FOR GAS PRESSURE AND COMBUSTION AIR. INSTALLED COMBUSTION AIR GRILLES ARE LARGER THAN MINIMUM ENGINEER CALLS FOR. WILL SCAN ON TO PERMIT IN THE MORNING. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | P | 6628957 |
RESCUE MECHANICAL, INC. | H= | P | 06/11/2020 | MECHANICAL FINAL PENDING: NEED LETTER FROM ENGINEER REMOVING NOTE 7 FROM SHEET M1.1-R, GAS IS REGULAR PRESSURE, NOT 14 INCHES. WATER HEATER LACKS COMBUSTION AIR, NEED ENGINEER TO ADDRESS. | DUSTINS | DUSTINS | | H= | P | 6600959 |
RESCUE MECHANICAL, INC. | H= | P | 06/11/2020 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. STILL NEED LETTER FROM ENGINEER REMOVING NOTE 7 FROM SHEET M1.1-R, GAS IS REGULAR PRESSURE, NOT 14 INCHES, AS NOTED AT HI INSPECTION ON 12-2-19. | DUSTINS | DUSTINS | | H= | P | 6600763 |
RESCUE MECHANICAL, INC. | HD | C | 12/03/2019 | RECEIVED PICTURE OF WATER HEATER VENTING SUPPORTED ABOVE CEILING, SEE IMAGES. MECHANICAL ROUGH ABOVE CEILING OK. | DUSTINS | DUSTINS | | HD | C | 6413747 |
RESCUE MECHANICAL, INC. | HC | C | 12/02/2019 | OK TO SET METER. | NANCY | NANCY | | HC | C | 6413472 |
RESCUE MECHANICAL, INC. | HI | C | 12/02/2019 | BY FINAL PROVIDE LETTER FROM ENGINEER REMOVING NOTE 7 FROM SHEET M1.1-R, GAS IS REGULAR PRESSURE, NOT 14 INCHES. 10 LB TEST OK. INSTALLED AS PER PRINT. | NANCY | NANCY | | HI | C | 6413468 |
RESCUE MECHANICAL, INC. | HD | P | 12/02/2019 | STRAP/SUPPORT WATER HEATER VENT ABOVE CEILING. BY FINAL INSTALL MANUAL VOLUME DAMPER IN OUTSIDE AIR DUCT. REST OF SUPPLY, RETURN, EXHAUST, LINESET AND FURNACE VENTS ABOVE CEILING OK. | NANCY | NANCY | | HD | P | 6413463 |
CORNERSTONE PLUMBING INC | P= | C | 05/28/2020 | Ok. | DANR | DANR | | P= | C | 6586002 |
CORNERSTONE PLUMBING INC | PTO | C | 08/30/2019 | Add water heater to scope of work by final. | TAYLOR | TAYLOR | | PTO | C | 6320627 |
CORNERSTONE PLUMBING INC | PTO | P | 08/21/2019 | undersized cold water piping for bathroom, shower does not meet accessibility requirements, need to revise plans for added H&C hose bib and 1/2 inch supply lines that feed both front and rear hose bibs (cover at own risk ), note: check toilet clearances by final. | TAYLOR | TAYLOR | | PTO | P | 6309263 |
CORNERSTONE PLUMBING INC | PB | C | 10/18/2018 | need engineers letter for 3 inch trunk line, cover at own risk. | TAYLOR | TAYLOR | | PB | C | 5998974 |
DOUBLE DIAMOND HOMES, INC. | PWO | C | 10/17/2018 | need certificate of potable water by final. | TAYLOR | TAYLOR | | PWO | C | 5997613 |
DOUBLE DIAMOND ENTERPRISES, INC | XBS | P | 12/20/2019 | PLAN SPLICE: (No Fee) by: BPHILLIPS for Construction: Revised Comcheck. | BPHILLIPS | BPHILLIPS | | XBS | P | 6433483 |
DOUBLE DIAMOND ENTERPRISES, INC | XMS | T | 11/15/2019 | PAID (REC#1644681) PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: see note on plan set | TCRIPPEN | TCRIPPEN | | XMS | T | 6400345 |