BOB MCGRATH CONSTRUCTION LLC | B= | C | 01/11/2019 | items corrected | NATHAN | NATHAN | | B= | C | 6076235 |
BOB MCGRATH CONSTRUCTION LLC | B= | P | 01/09/2019 | fine grade at exterior, insulation at rim in basement. remaining okay, post installed -- Schedule a new Building Final when above items are complete. | NATHAN | NATHAN | | B= | P | 6073950 |
BOB MCGRATH CONSTRUCTION LLC | BIN | P | 10/08/2018 | Insulation for main level OK / Still need to inspect basement insulation / Check attic at final | NICK | NICK | | BIN | P | 5989162 |
BOB MCGRATH CONSTRUCTION LLC | BFR | P | 10/08/2018 | Strapping at top plate of balloon framed walls OK / Still need to inspect post in basement | NICK | NICK | | BFR | P | 5989159 |
BOB MCGRATH CONSTRUCTION LLC | BIN | R | 10/05/2018 | Not ready for inspection, insulation being installed at time of inspection / Please recall / Still need open hole report | NICK | NICK | | BIN | R | 5987511 |
BOB MCGRATH CONSTRUCTION LLC | BFN | P | 10/04/2018 | need open excavation paperwork, engineers letter for foundation observation on file. | NATHAN | NATHAN | | BFN | P | 5986133 |
BOB MCGRATH CONSTRUCTION LLC | BFT | C | 10/04/2018 | engineers letter for footer observation on file | NATHAN | NATHAN | | BFT | C | 5986127 |
BOB MCGRATH CONSTRUCTION LLC | BFR | P | 10/04/2018 | need open excavation paperwork, strap plate top plates at balloon walls, need post installed at pad in basement at raised wall and floor pad okay, complete plumbing inspections. engineering picked up for conditions discovered at frame, | NATHAN | NATHAN | | BFR | P | 5986121 |
BOB MCGRATH CONSTRUCTION LLC | BSP | P | 09/17/2018 | no sheer needed | NATHAN | NATHAN | | BSP | P | 5967458 |
BOB MCGRATH CONSTRUCTION LLC | BFD | C | 08/01/2018 | drain is perimeter to sump, need plans spliced to show new basement not crawlspace and foundation plan | NATHAN | NATHAN | | BFD | C | 5921012 |
THE CORE ELECTRIC GROUP, LLC | E= | C | 12/27/2018 | corrections made / | MIGUEL | MIGUEL | | E= | C | 6063224 |
THE CORE ELECTRIC GROUP, LLC | E= | R | 12/20/2018 | see rough notes---no A/C at this time--- | MIGUEL | MIGUEL | | E= | R | 6059973 |
THE CORE ELECTRIC GROUP, LLC | ER | R | 12/20/2018 | need to secure nm cable at basement sub panel / | MIGUEL | MIGUEL | | ER | R | 6059970 |
THE CORE ELECTRIC GROUP, LLC | ER | P | 10/02/2018 | upper level of addition ok---waiting on basement work / | MIGUEL | MIGUEL | | ER | P | 5983350 |
WESTERN FIREPLACE SUPPLY, INC. | H= | C | 01/02/2019 | mantel ok. | PAULO | PAULO | | H= | C | 6066752 |
GENE'S HEATING AND AIR LLC | H= | C | 12/20/2018 | note: partial finished basement, direct vent furnace in unfinished portion of basement, mantel ok, (WATER HEATER IN UNFINISHED PORTION OF BASEMENT HAS BEEN DELETED AND A NEW ADDED ELECTRIC WATER HEATER HAS BEEN INSTALLED). | PAULO | PAULO | | H= | C | 6059813 |
GENE'S HEATING AND AIR LLC | HSP | P | 10/17/2018 | READ HRR NOTES FOR FINAL INSPECTION. | PAULO | PAULO | | HSP | P | 5997216 |
RESCUE MECHANICAL, INC. | H= | C | 10/17/2018 | ok. | PAULO | PAULO | | H= | C | 5997180 |
RESCUE MECHANICAL, INC. | HC | C | 10/17/2018 | added 67,500k to load. | PAULO | PAULO | | HC | C | 5997179 |
RESCUE MECHANICAL, INC. | HO | C | 10/17/2018 | 10# test ok. note: added 210' of 1 1/4" poly to addition (67,500k) and future underground stub (not to exceed a total of 240k), tracer wire installed. | PAULO | PAULO | | HO | C | 5997173 |
GENE'S HEATING AND AIR LLC | HRR | C | 10/02/2018 | Need at final: Inspect 3 bath exhaust ducts above ceiling, Heat calcs required and Inspect furnace (Not installed at rough) Also will need access to complete furnace vent for inspection. Combustion air to mechanical. | MARK | MARK | | HRR | C | 5983040 |
RESCUE MECHANICAL, INC. | HI | C | 09/27/2018 | 10 lb test ok. Note: 3/4" main. Water heater, fireplace. | MARK | MARK | | HI | C | 5978684 |
WESTERN FIREPLACE SUPPLY, INC. | HV | C | 09/25/2018 | Fireplace and vent ok, gas coming later per builder. | MARK | MARK | | HV | C | 5975787 |
JOLLY PLUMBING & HEATING INC. | P= | C | 01/09/2019 | correction made see image (aav's) | JOSEPHD | JOSEPHD | | P= | C | 6072676 |
JOLLY PLUMBING & HEATING INC. | P= | P | 01/08/2019 | previous pto inspection calls for aav @ both master lavs, and need to change scope of work to show electric water heater not gas, can submit photos of corrections, rest ok | JOSEPHD | JOSEPHD | | P= | P | 6071336 |
JOLLY PLUMBING & HEATING INC. | P= | P | 12/20/2018 | not complete, re inspect all. NOTE: vtr verified | JOHNS | JOHNS | | P= | P | 6060164 |
JOLLY PLUMBING & HEATING INC. | P= | P | 12/20/2018 | not complete, re inspect all. NOTE: vtr verified | JOHNS | JOHNS | | P= | P | 6059136 |
JOLLY PLUMBING & HEATING INC. | PB | C | 10/15/2018 | Test OK | SHANEN | SHANEN | | PB | C | 5994490 |
JOLLY PLUMBING & HEATING INC. | PTO | C | 10/15/2018 | Unfinished basement, check water heater at final | SHANEN | SHANEN | | PTO | C | 5994486 |
JOLLY PLUMBING & HEATING INC. | PTO | P | 10/03/2018 | ok for main level addition 4pc mstr, pwdr, washing machine, and laundry sink only. NOTE: vtr (2 new), aav @ both mstr lavs, check water htr @ final **inspector note - still need to inspect bsmnt plbg | JOHNS | JOHNS | | PTO | P | 5983953 |
WESTERN FIREPLACE SUPPLY, INC. | XMS | P | 11/26/2018 | PLAN SPLICE FEE: $0 by: JUSTINC for Mechanical: Revised design and calculations for basement in lieu of crawlspace | JUSTINC | JUSTINC | | XMS | P | 6033287 |
BOB MCGRATH CONSTRUCTION LLC | XBS | T | 08/24/2018 | PAID (REC#1530377) PLAN SPLICE FEE: $50 by: BPHILLIPS for Construction: Revised header support. | BPHILLIPS | BPHILLIPS | | XBS | T | 5944713 |
BOB MCGRATH CONSTRUCTION LLC | XBS | T | 06/28/2018 | PAID (REC#1511570) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: modified foundation plan | MICHAELA | MICHAELA | | XBS | T | 5888154 |