CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | B= | C | 01/11/2019 | All other required Final inspections are complete. (This is a computer generated result) | BRIANB | BRIANB | | B= | C | 6075588 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | B= | P | 01/08/2019 | pending external final inspections / engineering observation letter for trash enclosure masonry and drive up canopy footings on file. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982). | BRIANB | BRIANB | | B= | P | 6071196 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | B= | P | 12/21/2018 | Temp CO: need zoning and fire ( Expires: 1/20/2019 12:00:00 AM) | JANE | JANE | | B= | P | 6060527 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | B= | P | 12/21/2018 | Temp CO: need zoning znd fire finals ( Expires: 1/20/2019 12:00:00 AM) | JANE | JANE | | B= | P | 6060522 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | B= | P | 12/21/2018 | observation letter for drive up canopy structural steel on file / pending external final inspections. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), ANYTHING HVAC, LLC. Mechanical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 6060455 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | B= | P | 12/20/2018 | pending observation letter for drive up canopy structural steel attached to building and other final inspections / note only - still need observation letters to complete all inspections for stand alone drive up canopy to complete permit L91024 and trash enclosure L58254 | BRIANB | BRIANB | | B= | P | 6059382 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BIN | P | 12/20/2018 | plan splice for revised ComCheck completed on 11/9/18 | BRIANB | BRIANB | | BIN | P | 6059350 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BFR | P | 12/06/2018 | received observation letter for structural steel and wood framing from Terracon / pending other rough inspection | BRIANB | BRIANB | | BFR | P | 6044950 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BIN | P | 11/05/2018 | approved Comcheck requires R21 to be installed at the exterior walls / observed R19 installed at exposed sections above grid / pending other rough inspections / Training with PPRBD inspector Lonny / VB construction / A2 occupancy / discussed inspection processes for structure, including reviewing approved design and went over approved Comcheck for insulation inspection / also discussed accessible elements at restrooms | BRIANB | BRIANB | | BIN | P | 6016425 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BSP | P | 11/05/2018 | training with inspector Brian B - A-2 OCC V-B construction / reviewed plan sticker - went over project scope and previous inspections - discussed 3rd party inspections - performed insulation inspection and reviewed com check requirements | LONNYS | LONNYS | | BSP | P | 6016401 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BIN | P | 10/12/2018 | partial insulation only -- exterior thermal ok to 12' AFF/remainder to be completed after framing inspection complete | SCOTTS | SCOTTS | | BIN | P | 5993973 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BFR | P | 10/09/2018 | courtesy visit only / discussed engineering observation letter for structural components to complete frame inspection - see comments from BFR dated 27SEPT18 / also discussed inspection processes - scheduling | BRIANB | BRIANB | | BFR | P | 5990214 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BFR | P | 10/01/2018 | interior non-load bearing wall framing and drop ceiling framing okay / pending observation letter for all structural components, and pending completion of other rough inspections | BRIANB | BRIANB | | BFR | P | 5982175 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BSP | T | 10/01/2018 | PAID (REC#1545664) ADDITIONAL PLAN REVIEW TIME: $50 From: SHELBY As builts | SHELBY | SHELBY | | BSP | T | 5981084 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BFR | R | 09/27/2018 | missing simpson 1460s at 8" o.c at bar joist ledger along exterior metal stud walls per detail B1 on sheet S-401 / missing (2) simpson sdws22400db screws under each joist bearing locations along exterior wood walls - per detail C1 on S-401 / unable to observe bar joist connections along exterior walls per sheet S-401 / inspection stopped - okay for engineer to observe structural components also including welding and bolting - per Dave superintendent with Christofferson observation letter to follow / still need to inspect interior framing components / discussed accessible components with site superintendent and inspections / also went over pre-insulation at box headers - k.s / need to complete mechanical inspections at hood wall / need to complete other rough inspections | BRIANB | BRIANB | | BFR | R | 5979266 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BSP | P | 09/27/2018 | observed exterior shear wall fastening per sheet S-201 detail 3 - shear wall schedule | BRIANB | BRIANB | | BSP | P | 5979231 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BFN | C | 09/27/2018 | received engineer observation letter for foundation | BRIANB | BRIANB | | BFN | C | 5979225 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BFT | C | 09/27/2018 | received engineer observation letter for foundation | BRIANB | BRIANB | | BFT | C | 5979220 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BSP | P | 08/21/2018 | courtesy visit only / met with Christofferson commercial builders superintendent David / discussed inspection processes and scheduling / stamped observation letters for foundation inspections by Teracon to follow / training with PPRBD inspector Chuck | BRIANB | BRIANB | | BSP | P | 5940533 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BFN | P | 07/26/2018 | Authorized third party inspections - Stamped letters to follow | JEREMYA | JEREMYA | | BFN | P | 5914819 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | BFT | P | 07/26/2018 | Authorized third party inspections - Stamped letters to follow | JEREMYA | JEREMYA | | BFT | P | 5914817 |
FIRE AND SECURITY TECHNICAL SERVICE, INC. | E= | C | 12/20/2018 | FIRE ALARM INSPECTION: FA complete / | ROB | ROB | | E= | C | 6060294 |
FIRE AND SECURITY TECHNICAL SERVICE, INC. | E= | C | 12/20/2018 | FIRE ALARM INSPECTION: FA rough complete / | ROB | ROB | | E= | C | 6060293 |
FIRE AND SECURITY TECHNICAL SERVICE, INC. | ER | C | 12/20/2018 | FIRE ALARM INSPECTION: FA rough complete / | ROB | ROB | | ER | C | 6060292 |
FIRE AND SECURITY TECHNICAL SERVICE, INC. | E= | P | 12/18/2018 | FIRE ALARM INSPECTION: Needs horn/strobe at back of bldg. / | ROB | ROB | | E= | P | 6056844 |
FIRE AND SECURITY TECHNICAL SERVICE, INC. | ER | P | 12/18/2018 | FIRE ALARM INSPECTION: Need horn/strobe at back of bldg. / | ROB | ROB | | ER | P | 6056842 |
HERRON ELECTRIC COMPANY | ES | C | 12/17/2018 | Commercial Service: Labels installed on panels / | ROB | ROB | | ES | C | 6054894 |
HERRON ELECTRIC COMPANY | E= | C | 12/17/2018 | Serving Area, Dining Area, Bathrooms complete / | ROB | ROB | | E= | C | 6054885 |
HERRON ELECTRIC COMPANY | E= | P | 12/12/2018 | Need class A GFCI breakers for ice machine heads and 1 30 amp for twist lock plug / | ROB | ROB | | E= | P | 6050843 |
HERRON ELECTRIC COMPANY | ES | P | 12/12/2018 | Commercial Service: All panels ok except fault current ans series rating labels / | ROB | ROB | | ES | P | 6050832 |
HERRON ELECTRIC COMPANY | E= | P | 12/11/2018 | Kitchen complete except 1 30 amp GFCI breaker----Office area complete---Rear entry area complete----Outside recpts. on building ok--- / | ROB | ROB | | E= | P | 6049645 |
HERRON ELECTRIC COMPANY | ER | P | 12/10/2018 | Rough ok for kitchen area grid ceilings / | ROB | ROB | | ER | P | 6047854 |
HERRON ELECTRIC COMPANY | E= | P | 12/06/2018 | RTU's, Hood Fans, Cooler/Freezer Compressors on roof ok--Middle north RTU needs 100 amp OCP in panel----NOTE: Need to check heat trace and GFCI recpt. on roof to complete roof / | ROB | ROB | | E= | P | 6044741 |
HERRON ELECTRIC COMPANY | ER | P | 11/28/2018 | Rough in for grid ceils in dining and drive thru area ok / | ROB | ROB | | ER | P | 6036651 |
FIRE AND SECURITY TECHNICAL SERVICE, INC. | ER | C | 11/27/2018 | FIRE ALARM INSPECTION: Rough ok--Need to complete FA panel, Riser Pipes, and rear Horn/Strobe for final / | ROB | ROB | | ER | C | 6035531 |
HERRON ELECTRIC COMPANY | ES | P | 10/26/2018 | Commercial Service: 1200 amp 4 wire--Comm. UG Ok to energize-----Contractor to coordinate shutdown with CSU------ Note:Only MDP and grounding has been inspected--Additional 250/3 Main Breaker to be added to MDP / | ROB | ROB | | ES | P | 6007202 |
HERRON ELECTRIC COMPANY | ER | P | 09/28/2018 | Rough in ok for dinig area walls / | ROB | ROB | | ER | P | 5980161 |
HERRON ELECTRIC COMPANY | ER | P | 09/27/2018 | Walls and hard lids ok with the exception of dining area receptacles / Recess not AT type / | ROB | ROB | | ER | P | 5978956 |
HERRON ELECTRIC COMPANY | EUG | P | 08/21/2018 | okay underground on 7 site pole lights | CHIPO | CHIPO | | EUG | P | 5940723 |
HERRON ELECTRIC COMPANY | ESL | C | 08/15/2018 | | CRAIGS | CRAIGS | | ESL | C | 5935149 |
HERRON ELECTRIC COMPANY | EUG | P | 08/01/2018 | EUG for 3 pole lights and trash compactor ok--Pipes to sw corner and need to be completed into building / | ROB | ROB | | EUG | P | 5920500 |
ANYTHING HVAC, LLC. | H= | C | 12/27/2018 | HEAT FINAL OK. | LIDO | LIDO | | H= | C | 6063472 |
ANYTHING HVAC, LLC. | H= | P | 12/21/2018 | INTERLOCKS FOR KITCHEN HOODS OK, RECEIVED LETTER FROM ENGINEER ADDRESSING THE INTERLOCKS FOR THE THREE KITCHEN HOODS ( SEE IMAGES ) | LIDO | LIDO | | H= | P | 6060555 |
ANYTHING HVAC, LLC. | H= | P | 12/21/2018 | PARTIAL PENDING FOR- GREASE DUCT ON ROOF IS NOT PAINTED. | LIDO | LIDO | | H= | P | 6061064 |
ANYTHING HVAC, LLC. | H= | P | 12/20/2018 | PARTIAL PENDING FOR- INTERLOCK TEST FOR KITCHEN HOODS : IN UNOCCUPIED MOD WHEN THE TEMPERATURE CENSOR FOR THE HOODS IS TRIGGERED ONLY THE EXHAUST FANS TURN ON . WHAT IS BEING DONE FOR MAKE UP AIR? INTERLOCK SCHEDULE DOES NOT SHOW ANYTHING FOR THE MAKE UP AIR IN UNOCCUPIED MOD WHEN THE HOOD TEMPERATURE CENSOR IS TRIGGERED. ((ENGINEER TO ADDRESS THIS ISSUE.)) GREASE DUCT ON ROOF TO BE PAINTED WITH APPROVED COATING. | LIDO | LIDO | | H= | P | 6059777 |
GOLDEN WAY MECHANICAL, INC. | H= | C | 12/19/2018 | CORRECTIONS COMPLETED. | LIDO | LIDO | | H= | C | 6057886 |
ANYTHING HVAC, LLC. | H= | P | 12/19/2018 | INTERLOCK TEST FOR KITCHEN HOODS : IN UNOCCUPIED MOD WHEN THE TEMPERATURE CENSOR FOR THE HOODS IS TRIGGERED ONLY THE EXHAUST FANS TURN ON . WHAT IS BEING DONE FOR MAKE UP AIR? INTERLOCK SCHEDULE DOES NOT SHOW ANYTHING FOR THE MAKE UP AIR IN UNOCCUPIED MOD WHEN THE HOOD TEMPERATURE CENSOR IS TRIGGERED. ((ENGINEER TO ADDRESS THIS ISSUE.)) CO2 STORAGE VENTILATION OK . | LIDO | LIDO | | H= | P | 6057862 |
ANYTHING HVAC, LLC. | HD | P | 12/19/2018 | RECEIVED TEST AND BALANCE REPORT ( SEE IMAGES) | LIDO | LIDO | | HD | P | 6057551 |
ROGERS PLUMBING, INC. | H= | C | 12/19/2018 | | LIDO | LIDO | | H= | C | 6057451 |
ROGERS PLUMBING, INC. | HV | C | 12/19/2018 | CORRECTIONS MADE ( SEE IMAGES) | LIDO | LIDO | | HV | C | 6057448 |
ERNST ENTERPRISES | H= | C | 12/19/2018 | ALTERNATE METHOD AND MATERIALS FORM FOR R-448 COMPLETED AND SPLICED IN. | LIDO | LIDO | | H= | C | 6057441 |
ANYTHING HVAC, LLC. | HD | P | 12/18/2018 | GREASE DUCT LIGHT TEST ON ROOF OK . | LIDO | LIDO | | HD | P | 6056453 |
ROGERS PLUMBING, INC. | H= | P | 12/18/2018 | PARTIAL PENDING FOR ((NEED TO SECURE WATER HEATER VENTS ON ROOF.))FINAL GAS CONNECTION TO RADIANT HEATERS IN DRIVE THROUGH ON WEST SIDE OK | LIDO | LIDO | | H= | P | 6056452 |
ROGERS PLUMBING, INC. | HV | P | 12/18/2018 | NEED TO ADD SUPPORTS ON ROOF TO SECURE WATER HEATER VENTS IN PLACE . | LIDO | LIDO | | HV | P | 6056451 |
ANYTHING HVAC, LLC. | HD | P | 12/17/2018 | GREASE DUCT LIGHT TEST ON ROOF: 6 HOLES / RE-INSPECT. | LIDO | LIDO | | HD | P | 6055525 |
ROGERS PLUMBING, INC. | HI | P | 12/17/2018 | ((NEED TO CALL IN EAST CANOPY INSPECTION UNDER PERMIT L91024 AND ADD SCOPE OF WORK FOR THAT PERMIT.))NEED TO CALL IN WATER HEATER VENT INSPECTION. 10 LB TEST FOR WEST DRIVE THROUGH CANOPY OK , GAS INSTALLED PER PLAN . NEED FINAL CONNECTIONS TO THE TWO RADIANT HEATERS. FINAL GAS CONNECTION TO EQUIPMENT ON THE ROOF AND TO WATER HEATER OK | LIDO | LIDO | | HI | P | 6055512 |
GOLDEN WAY MECHANICAL, INC. | HSP | P | 12/17/2018 | NEED TO LABEL THE THREE ICE MAKER CONDENSERS ON ROOF. OK TO ATTACH PICTURES TO NEXT INSPECTION REQUEST. | LIDO | LIDO | | HSP | P | 6055483 |
ERNST ENTERPRISES | H= | P | 12/06/2018 | (( SINCE THE THREE ICE MAKERS REQUIRE REFRIGERATION THE CONTRACTOR INSTALLING THESE WILL NEED TO ATTACH TO PERMIT AND CALL FOR INSPECTION . AN AM &M ( ALTERNATE MATERIALS AND METHODS )SHEET IS REQUIRED FOR THE USE OF THE R-448 UNDER THE 2018 IMC CODE. THIS WILL BE REQUIRED AS A SPLICE RAN THROUGH PLAN REVIEW. NEED TO LABEL CONDENSERS ON ROOF FOR THE COOLER / FREEZER THEY SERVE. ( COOLER/ FREEZER OK ) | LIDO | LIDO | | H= | P | 6045562 |
ANYTHING HVAC, LLC. | HD | P | 12/03/2018 | NEED ROOF GREASE DUCT INSPECTED AND ROOF INSPECTED. NEED TO SEE DUCT DETECTORS FOR ALL ROOF TOPS .NEED TO VERIFY KITCHEN HOOD INTERLOCKS . NEED VENTILATION FOR CO2 STORAGE ROOM . NEED TEST AND BALANCE REPORT BY FINAL . (ALL SUPPLY , RETURN AND TRANSFER AIR GRILLS AND REGISTERS FINAL CONNECTION IN DROP CEILING OK . ALL REMOTE SMOKE INDICATORS IN PLACE.)
| LIDO | LIDO | | HD | P | 6041476 |
ANYTHING HVAC, LLC. | HD | P | 11/14/2018 | GREASE DUCT 1ST LAYER AND 2ND LAYER OF FIRE WRAP FOR ALL THREE HOODS OK. STILL NEED ROOF GREASE DUCT INSPECTED. | LIDO | LIDO | | HD | P | 6025599 |
ANYTHING HVAC, LLC. | HD | P | 11/13/2018 | ( TOE SPACING FOR PERMANENT LADDER FOR ROOF ACCESS IS LESS THAN 6" REFER TO 2009 IMC CODE SECTION 307.6.5 # ( 3) . ALL THREE KITCHEN TYPE 1 HOOD INSTALL OK. NEED GREASE DUCT WRAP INSPECTION. KITCHEN -SUPPLY, RETURN GRILLS AND REGISTERS FINAL CONNECTIONS OK. (NEED TO VERIFY KITCHEN HOOD INTERLOCKS AND NEED TEST AND BALANCE REPORT BY FINAL) | LIDO | LIDO | | HD | P | 6024320 |
ROGERS PLUMBING, INC. | HC | C | 11/13/2018 | METER RELEASE. | LIDO | LIDO | | HC | C | 6024309 |
ROGERS PLUMBING, INC. | HI | P | 11/13/2018 | FINAL CONNECTIONS TO ROOF TOPS OK. STILL NEED GAS INSTALLED FOR WEST CANOPY AND EAST CANOPY , STILL NEED 6 RADIANT HEATERS INSTALLED. | LIDO | LIDO | | HI | P | 6024294 |
R & R DITCHING, INC | H= | C | 11/13/2018 | OUTSIDE GAS COMPLETE. | LIDO | LIDO | | H= | C | 6024277 |
R & R DITCHING, INC | HO | C | 11/13/2018 | SPLICE HAS BEEN SCANNED IN FOR OUTSIDE GAS . | LIDO | LIDO | | HO | C | 6024274 |
ANYTHING HVAC, LLC. | HD | P | 11/12/2018 | GREASE DUCT LIGHT TEST FOR ALL THREE HOODS OK / OK TO APPLY FIRE WRAP , OK FOR CONTRACTOR TO TAKE PICTURES OF FIRST LAYER OF WRAP.( STILL NEED ROOF GREASE DUCT LIGHT TEST ) | LIDO | LIDO | | HD | P | 6023011 |
ANYTHING HVAC, LLC. | HSP | P | 11/07/2018 | CONTRACTOR INSTALLING WALK IN COOLER/FREEZER STILL NEEDS TO ATTACH TO PERMIT,AN AMM ( ALTERNATE MATERIALS AND METHODS )SHEET IS REQUIRED FOR THE USE OF THE R-448 UNDER THE 2018 IMC CODE. THIS WILL BE REQUIRED AS A SPLICE RAN THROUGH PLAN REVIEW. | LIDO | LIDO | | HSP | P | 6018081 |
ROGERS PLUMBING, INC. | HI | P | 11/06/2018 | ((WILL RELEASE METER AFTER UNDER GROUND GAS HAS BEEN CORRECTED OR SPLICE IS COMPLETED)) GAS PLAN SPLICE DATED 10/17/18 SHOWS UNDER GROUND 1-1/2" GAS INSTALL TO EAST CANOPY ROUTED ALONG THE WEST SIDE OF THE BUILDING / 1-1/4" WAS INSTALLED AND ROUTED ON THE EAST SIDE OF THE BUILDING , INSTALL PER PLAN OR WILL NEED A REVISED AND APPROVED PLAN. 60 LB TEST OK , GAS INSTALLED ON ROOF AND DOWN TO WATER HEATER PER PLAN , STILL NEED GAS INSTALLED FOR WEST CANOPY AND EAST CANOPY . NEED TO SEE ALL EQUIPMENT FINAL CONNECTIONS . | LIDO | LIDO | | HI | P | 6017698 |
ANYTHING HVAC, LLC. | HD | P | 10/01/2018 | AC# 4 DUCT ROUGH OK / OK TO WRAP. THREE HOOD WALLS OK . LIGHT TEST - THREE GREASE DUCT DROPS OK / OK TO WRAP - NEED TO SEE PICTURES OF FIRST AND SECOND LAYERS OF WRAP . | LIDO | LIDO | | HD | P | 5982142 |
ANYTHING HVAC, LLC. | HD | P | 09/27/2018 | KITCHEN HOOD #2 AND #3 - REMOVE COMBUSTIBLES FROM FROM HOOD WALL. WALL BEHIND HOOD #1 OK . ATTACH THREE TYPE ONE HOODS TO SCOPE OF WORK. CONTRACTOR INSTALLING WALK IN COOLER/FREEZER NEED TO ATTACH TO PERMIT .CONTRACTOR WILL NEED TO PROVIDE INFORMATION ON DAMPERS BEING INSTALLED IN GREASE DUCT / WILL NEED TO RESEARCH THIS .ABOVE CEILING SUPPLY AND RETURN AIR DUCT ROUGH FOR AC # 1,2,3 OK OK TO WRAP . EF-3 DUCT ROUGH OK. | LIDO | LIDO | | HD | P | 5979039 |
R & R DITCHING, INC | H= | P | 09/14/2018 | NOT READY FOR FINAL, SEE HO NOTES. NEED TO CHECK CONNECTION TO EQUIPMENT AT FINAL. | DUSTINS | DUSTINS | | H= | P | 5966009 |
R & R DITCHING, INC | HO | P | 09/14/2018 | NEED APPROVED PLAN FOR GAS LINE FROM METER TO HEATED AWNING AT DRIVE THRU. NEED GAS CONTRACTOR INSTALLING GAS LINES IN BUILDING ATTACHED TO PERMIT. 10 LB TEST OK ON 1 1/4" POLY FROM METER TO HEATED AWNING AT DRIVE THRU. TRACER WIRE INSTALLED. COVER AT OWN RISK UNTIL PLANS ARE APPROVED. | DUSTINS | DUSTINS | | HO | P | 5966004 |
ROGERS PLUMBING, INC. | P= | C | 12/14/2018 | Correction made, image from contractor uploaded. | DANR | DANR | | P= | C | 6052722 |
ROGERS PLUMBING, INC. | P= | P | 12/13/2018 | need yard hydrant backflow protection, rest ok | TED | TED | | P= | P | 6052142 |
ROGERS PLUMBING, INC. | P= | P | 12/12/2018 | Run t&p to floor drain (picture ok), rest ok. | DANR | DANR | | P= | P | 6051088 |
ROGERS PLUMBING, INC. | PTO | P | 09/27/2018 | design and test ok in walls, ceilings and through roof, will check meter room and water heater connections at final, will check water hammer access at final | TED | TED | | PTO | P | 5978817 |
ROGERS PLUMBING, INC. | PB | P | 08/16/2018 | trap primer lines run under slab, irrigation line run under footer to outside, grease trap vents run up into building wall | TED | TED | | PB | P | 5936062 |
ROGERS PLUMBING, INC. | PB | P | 08/10/2018 | grease and sanitary dwv test and design ok, water main rolled into meter area | TED | TED | | PB | P | 5930270 |
R & R DITCHING, INC | XMS | P | 12/19/2018 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Splice if for A&M associated with refrigerant for walkins | JUSTINC | JUSTINC | | XMS | P | 6057395 |
HERRON ELECTRIC COMPANY | XES | T | 12/04/2018 | PAID (REC#1561042) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Added Panel E. | BERTHA | BERTHA | | XES | T | 6042586 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | XBS | T | 11/09/2018 | PAID (REC#1555650) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: IECC | MICHAELA | MICHAELA | | XBS | T | 6022175 |
R & R DITCHING, INC | XMS | T | 11/08/2018 | PAID (REC#1554993) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: delta 12 | DALEH | DALEH | | XMS | T | 6020517 |
HERRON ELECTRIC COMPANY | XES | T | 10/03/2018 | PAID (REC#1545661) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revised lighting plan | SHELBY | SHELBY | | XES | T | 5984798 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | XBS | T | 10/03/2018 | PAID (REC#1545658) PLAN SPLICE FEE: $50 by: DANM for Construction: Minor interior elevation revisions | DANM | DANM | | XBS | T | 5984030 |
R & R DITCHING, INC | XMS | T | 09/24/2018 | PAID (REC#1545666) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: added gih's and revised gas piping plan | DALEH | DALEH | | XMS | T | 5973741 |
HERRON ELECTRIC COMPANY | XES | T | 09/18/2018 | PAID (REC#1541737): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revise service/metering and one line | SHELBY | SHELBY | | XES | T | 5969091 |
R & R DITCHING, INC | XMS | P | 09/17/2018 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: see plan review comment section | DALEH | DALEH | | XMS | P | 5967001 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | XBS | T | 09/17/2018 | PAID (REC#1538200) PLAN SPLICE FEE: $50 by: DANM for Construction: Drive thru canopy added | DANM | DANM | | XBS | T | 5966987 |
HERRON ELECTRIC COMPANY | XES | T | 09/17/2018 | PAID (REC#1538202) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Add sheets for canopy | SHELBY | SHELBY | | XES | T | 5966942 |
R & R DITCHING, INC | XMS | P | 09/13/2018 | PLAN SPLICE FEE: $0 by: JUSTINC for Mechanical: Revised for new canopy with gas fired heaters | JUSTINC | JUSTINC | | XMS | P | 5963713 |
HERRON ELECTRIC COMPANY | XES | T | 09/13/2018 | PAID (REC#1538202) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: As builts | SHELBY | SHELBY | | XES | T | 5963692 |
CHRISTOFFERSON COMMERCIAL BUILDERS, INC. | XBS | T | 09/11/2018 | PAID (REC#1538200) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Drive thru canopy | SHELLEY | SHELLEY | | XBS | T | 5961643 |