CLINT DARNELL, INC. | B= | C | 07/08/2019 | All other required Final inspections are complete. (This is a computer generated result) | JEREMYA | JEREMYA | | B= | C | 6256362 |
CLINT DARNELL, INC. | B= | P | 06/27/2019 | Rear grab bar may be reduced to 24" when adjacent fixture is recessed per 2003 ANSI 604.5.2, Exception 1. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: 719-322-2028), MICK HEATING & SHEET METAL Mechanical Final Inspection is not Completed yet, WSM MECHANICAL Mechanical Final Inspection is not Completed yet. | JEREMYA | JEREMYA | | B= | P | 6246198 |
CLINT DARNELL, INC. | BSP | P | 06/27/2019 | received certified welding inspection report for welding,bolting, and column grout | LONNYS | LONNYS | | BSP | P | 6245700 |
CLINT DARNELL, INC. | B= | P | 06/26/2019 | Temp CO: pending finals ( Expires: 7/26/2019 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 6245280 |
CLINT DARNELL, INC. | B= | P | 06/26/2019 | need to complete mech and fire finals / grab bar behind mens toilet to extend 24" to right side of toilet -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: mgates@fountainfire.org), External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: 719-322-2028), MICK HEATING & SHEET METAL Mechanical Final Inspection is not Completed yet, WSM MECHANICAL Mechanical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 6244984 |
CLINT DARNELL, INC. | BFR | C | 06/26/2019 | letter for welds and bolting of structural steel components on file | BOBF | BOBF | | BFR | C | 6244983 |
CLINT DARNELL, INC. | BSP | P | 06/26/2019 | open hole on file 1500#, bearing pressure verified | BOBF | BOBF | | BSP | P | 6244197 |
WSM MECHANICAL | BSP | T | 06/24/2019 | PAID (REC#1673540): ADDITIONAL PLAN REVIEW TIME: $50 From: TCRIPPEN new splice | TCRIPPEN | TCRIPPEN | | BSP | T | 6240944 |
CLINT DARNELL, INC. | BIN | P | 06/18/2019 | acrchitects letter for spray foam at box headers on file | BOBF | BOBF | | BIN | P | 6234475 |
CLINT DARNELL, INC. | BLA | C | 03/15/2019 | BLA inspection OK, perimeter of structure. | CHUCK | CHUCK | | BLA | C | 6133505 |
CLINT DARNELL, INC. | BIN | P | 02/15/2019 | Insulation at all exterior wall cavities inspected - R19 installed (at convenience store and tenant finish ) | JUSTINL | JUSTINL | | BIN | P | 6109463 |
CLINT DARNELL, INC. | BFR | P | 02/15/2019 | Framing for steel studs at interior non load bearing walls OK per splice on file - Sheet A100 / Request weld observation documentation noted in BSP 11-09-18 / Reviewed accessible elements with site representative ( Peter ) / Pending other rough inspections // Training with Chuck L | JUSTINL | JUSTINL | | BFR | P | 6109461 |
CLINT DARNELL, INC. | BSP | R | 02/13/2019 | BSP / Inspection not needed for parking lot light pole bases. | CHUCK | CHUCK | | BSP | R | 6105507 |
CLINT DARNELL, INC. | BSP | P | 02/05/2019 | BSP inspection - exterior continuous mounted rigid R7.5 Foamular insulation, entire perimeter of building OK as per IECC cert. on file. | CHUCK | CHUCK | | BSP | P | 6098076 |
CLINT DARNELL, INC. | BIN | P | 01/18/2019 | BIN inspection / Installation of R19 (R13 specified on IECC cert. on file) insulation in exterior wall at cooler areas only OK. (Cooler areas in convenience store (1) and in tenant finish (1)) | CHUCK | CHUCK | | BIN | P | 6082516 |
CLINT DARNELL, INC. | BIN | P | 01/08/2019 | BIN inspection / Box headers, blind corner framing and dead spaces only insulated with spray foam. Need an installer's certificate of compliance with product details and R-value for thickness sprayed. / Need welding observation documentation. | CHUCK | CHUCK | | BIN | P | 6071491 |
CLINT DARNELL, INC. | BFR | P | 12/13/2018 | BFR inspection / Exterior perimeter stud wall metal framing and 4' o.c. bracing OK per approved plan / Note: no insulation installed in box headers, window/door jambs and corner framing cavities at time of inspection. Discussed with contractor on site. / Need stamped documentation/observation of heavy steel frame welding. | CHUCK | CHUCK | | BFR | P | 6052230 |
CLINT DARNELL, INC. | BSP | P | 11/09/2018 | BSP inspection - bolting of steel frame for retail building / All HSS4x4x1/4 columns bolted at bottom to foundation per approved plans. All corner column posts have been bolted and welded to beams at top. Line E and F, HSS diagonal bracing and W18x35 beam connection points have been field welded to top and sides of interior and exterior columns. Diagonal bracing on lines A and 2 have also been field welded to columns. Bar joists and roof decking welded to beams. Viewed contractor's copy of weld observation documentation on site. Awaiting submittal for RBD records. Layout and material of steel frame matches Sht. S1.1 of the approved plans. | CHUCK | CHUCK | | BSP | P | 6021331 |
CLINT DARNELL, INC. | BFN | C | 09/17/2018 | Perimeter foundation and grade beam reinforcement inspection OK per S0.1/S1.0 of approved plans. | CHUCK | CHUCK | | BFN | C | 5967251 |
CLINT DARNELL, INC. | BFT | C | 09/06/2018 | Pad at A,2 line corrected footer okay | NATHAN | NATHAN | | BFT | C | 5956321 |
CLINT DARNELL, INC. | BFT | P | 09/05/2018 | Peter is POC. 1500 psf, need 2nd rebar mat at pad on A,2 grid corner remaining okay | NATHAN | NATHAN | | BFT | P | 5956176 |
PHOENIX FIRE AND SECURITY, LLC | E= | C | 06/25/2019 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | E= | C | 6243380 |
PHOENIX FIRE AND SECURITY, LLC | ER | C | 06/25/2019 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | ER | C | 6243373 |
PHOENIX FIRE AND SECURITY, LLC | E= | C | 06/25/2019 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | E= | C | 6243374 |
LIBERTY ELECTRIC COMPANY, INC. | E= | C | 06/18/2019 | | BRIAN | BRIAN | | E= | C | 6234992 |
LIBERTY ELECTRIC COMPANY, INC. | E= | R | 06/17/2019 | For MAU1 20 amp breaker exceedes MOCP of 15 amps (disconnects are un fused). Rest is OK | SHELBY | SHELBY | | E= | R | 6234236 |
LIBERTY ELECTRIC COMPANY, INC. | ER | P | 06/11/2019 | drop ceilings ok | TIMA | TIMA | | ER | P | 6227661 |
LIBERTY ELECTRIC COMPANY, INC. | EP | C | 06/07/2019 | breaker retainer installed on house panel main | TIMA | TIMA | | EP | C | 6224296 |
LIBERTY ELECTRIC COMPANY, INC. | ER | R | 06/07/2019 | cant run conduit and mc cable and boxes in roof decking need 1-1/2'" spacing from deck---seal offs ok | TIMA | TIMA | | ER | R | 6224149 |
LIBERTY ELECTRIC COMPANY, INC. | EUG | C | 03/01/2019 | rest of the pole lights--ok | BRIAN | BRIAN | | EUG | C | 6121857 |
LIBERTY ELECTRIC COMPANY, INC. | EP | R | 02/20/2019 | need retainer screw in house panel back fed breaker---- | BRIAN | BRIAN | | EP | R | 6112314 |
LIBERTY ELECTRIC COMPANY, INC. | ES | C | 02/20/2019 | Commercial Service: 400 amp 4-w --ok to set meter | BRIAN | BRIAN | | ES | C | 6112308 |
LIBERTY ELECTRIC COMPANY, INC. | ER | P | 02/08/2019 | walls only ok | CRAIG | CRAIG | | ER | P | 6101710 |
LIBERTY ELECTRIC COMPANY, INC. | EUG | P | 12/14/2018 | slab ok | TIMA | TIMA | | EUG | P | 6053538 |
LIBERTY ELECTRIC COMPANY, INC. | EUG | P | 10/16/2018 | service lateral up to building ok----SERVICE LATERAL TO CAR WASH TO MIDDLE OF PARKING LOT OK BUT NEED TO CALL THIS IN UNDER CAR WASH PERMIT---- | TIMA | TIMA | | EUG | P | 5996137 |
LIBERTY ELECTRIC COMPANY, INC. | EUG | P | 09/18/2018 | service lateral from transformer across street to edge of property line ok------INFORMED CONTRACTOR TO AVOID 20' RADIUS OF FUEL CANOPY WITH CONDUITS OR WOULD NEED SEAL OFFS--- | TIMA | TIMA | | EUG | P | 5968562 |
WSM MECHANICAL | H= | C | 07/05/2019 | | BILLS | BILLS | | H= | C | 6253809 |
MICK HEATING & SHEET METAL CO. | H= | C | 07/05/2019 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES | BILLS | BILLS | | H= | C | 6253797 |
MICK HEATING & SHEET METAL CO. | H= | P | 06/26/2019 | Final pending test and balance report | MARKB | MARKB | | H= | P | 6245265 |
MICK HEATING & SHEET METAL CO. | H= | R | 06/24/2019 | NOT READY - Hood interlocks not functional, exhaust fans on roof need to be mechanically fastened to curbs, bathroom exhaust volume dampers lack access, still need water heater splice. | MARKB | MARKB | | H= | R | 6241686 |
WSM MECHANICAL | H= | P | 06/21/2019 | FINAL PENDING - Splice for water heaters, cannot see in system at this time. | MARKB | MARKB | | H= | P | 6239604 |
ALNOR INC. | H= | C | 06/21/2019 | | MARKB | MARKB | | H= | C | 6239594 |
WSM MECHANICAL | H= | P | 06/19/2019 | FINAL PENDING - Plan splice for water heaters | MARKB | MARKB | | H= | P | 6237194 |
MICK HEATING & SHEET METAL CO. | HV | R | 06/18/2019 | WATER HEATER VENTS - PLAN SPLICE REQUIRED Water heater schedule calls for 1 Navion NPE-240 to be installed but contractor installed 2 NPE-210A heaters. Note #1 on water heater schedule calls for direct vent application and water heaters are pulling combustion air from kitchen. | MARKB | MARKB | | HV | R | 6235222 |
WSM MECHANICAL | H= | R | 06/17/2019 | NOT READY - Need water heater vent added to permit scope and inspected. Maxitrol regulator using a vent limiter need to be installed in the horizontal-upright position per manufacturer instructions for car wash. Need medium pressure stickers installed on gas piping. Need meters tagged with address. OTHER CORRECTIONS MADE | MARKB | MARKB | | H= | R | 6233396 |
ALNOR INC. | H= | P | 06/14/2019 | Need to complete condensate lines. Rest OK. | MARKB | MARKB | | H= | P | 6231519 |
WSM MECHANICAL | H= | R | 06/14/2019 | NOT READY - Need water heater vent added to permit scope and inspected. All Maxitrol regulators using a vent limiter need to be installed in the horizontal-upright position per manufacturer instructions(including car wash). Vent openings on roof need to be pointed down with bug screens installed. Need medium pressure stickers installed on gas piping. Need meters tagged with address. | MARKB | MARKB | | H= | R | 6231509 |
MICK HEATING & SHEET METAL CO. | HD | P | 04/26/2019 | 2 layers of grease warp and bands complete. | MARKB | MARKB | | HD | P | 6179660 |
MICK HEATING & SHEET METAL CO. | HD | P | 04/24/2019 | GREASE DUCT LIGHT TEST - LIGHT TEST ON HOOD CONNECTION COMPLETE AND INSIDE OF HOOD COLLAR GROUND SMOOTH. AT FINAL. OK TO FINISH GREASE WRAP- See that ANSUL screws are correct and not just zip screws. | MARKB | MARKB | | HD | P | 6176383 |
MICK HEATING & SHEET METAL CO. | HD | L | 04/23/2019 | Site cancelled by contractor | MARKB | MARKB | | HD | L | 6174659 |
MICK HEATING & SHEET METAL CO. | HD | P | 04/22/2019 | GREASE DUCT LIGHT TEST - Light test for last butt joint and hood connection found holes under corners and back/right side of butt joint. Found holes at hood connection at hood joint back and right sides. Need to grind down lip inside hood connection. Re inspect butt and hood connection once fixed. | MARKB | MARKB | | HD | P | 6173525 |
MICK HEATING & SHEET METAL CO. | HD | P | 04/08/2019 | GREASE DUCT WRAP - 91" OF DROP WITH 2 LAYERS OF WRAP AND BANDS PER INSTALL INSTRUCTION INSPECTED ON GROUND. | MARKB | MARKB | | HD | P | 6158699 |
MICK HEATING & SHEET METAL CO. | HD | P | 04/02/2019 | GREASE DUCT LIGHT TEST - DROP COMPLETE, OK TO WRAP WITH 2 LAYERS BEFORE DROPPING THROUGH CURB. Still need to light test connection to hood. ABOVE CEILING DUCT - SUPPLY/RETURN MAINS/BRANCHES/DIFFUSERS INSTALLED PER PLAN EXCEPT still need diffusers and access to volume dampers for bathrooms. | MARKB | MARKB | | HD | P | 6152231 |
MICK HEATING & SHEET METAL CO. | HD | P | 04/01/2019 | ----ADD TYPE1 HOOD TO PERMIT SCOPE---- GREASE DUCT LIGHT TEST - Curb drop (total 3 sections) has 2 holes in top butt joint. | MARKB | MARKB | | HD | P | 6150770 |
ALNOR INC. | HRP | C | 03/27/2019 | COOLER - 120 PSI PRESSURE TEST (HOOKED UP TO EQUIPMENT), NO REFRIGERATION ALARMS REQUIRED PER ENGINEER CALC'S. FREEZER - 120 PSI PRESSURE TEST (HOOKED UP TO EQUIPMENT), NO REFRIGERATION ALARMS REQUIRED PER ENGINEER CALC'S. No condensate lines or roof this inspection. | MARKB | MARKB | | HRP | C | 6145978 |
WSM MECHANICAL | HI | C | 03/15/2019 | 10 PSI PRESSURE TEST OK AND PIPING PER PLAN SPLICE EXCEPT SPLICE SHOWS GAS PIPING INSIDE AND T IS INSTALLED ON ROOF. | MARKB | MARKB | | HI | C | 6133276 |
WSM MECHANICAL | HC | C | 03/13/2019 | OK TO RELEASE 2 PSI METER | MARKB | MARKB | | HC | C | 6132623 |
WSM MECHANICAL | HI | P | 03/12/2019 | NEED CAR WASH GAS LINE TO BE INSTALLED TO GAS LINE PER SPLICE (WILL NEED A RETEST WITH GAS LINE TO CAR WASH). NEED SPLICE FOR GAS LINE RAN ON ROOF TOP AND NOT PER PLANS. STILL NEED-- 2# LETTER FROM BLACK HILLS, MEDIUM PRESSURE STICKERS AT ALL APPLICABLE LOCATIONS. | PAULO | PAULO | | HI | P | 6131753 |
MICK HEATING & SHEET METAL CO. | HD | P | 02/25/2019 | ABOVE CEILING DUCT - VOLUME DAMPERS HAVE BEEN INSTALL ABOVE BATHROOMS, at final will need access above bathrooms. | MARKB | MARKB | | HD | P | 6116031 |
MICK HEATING & SHEET METAL CO. | HD | P | 02/06/2019 | HOOD WALL - HOOD WALL HAS ZERO COMBUSTIBLES ABOVE CEILING DUCT - SUPPLY MAINS/BRANCHES EXPOSED/ABOVE HARD LIDS INSTALLED PER PLAN OK TO WRAP OR CONCEAL. | MARKB | MARKB | | HD | P | 6099790 |
ALL AROUND PLUMBING | P= | C | 06/24/2019 | Correction made. | DANR | DANR | | P= | C | 6242129 |
ALL AROUND PLUMBING | P= | P | 06/21/2019 | Hand sinks need to be direct connect, t&p drain lines need to be rated for BTU load, rest ok. | DANR | DANR | | P= | P | 6240338 |
ALL AROUND PLUMBING | P= | P | 06/13/2019 | LH bathroom lav to high off ground, will need to conduct more research into hand sinks indirect draining, no hot water at bathroom lavs, need to see soda backflow, never completed PRD, will update in morning
update: hand sinks show direct connect on plans | JOSEPHD | JOSEPHD | | P= | P | 6230970 |
ALL AROUND PLUMBING | PTO | C | 02/15/2019 | Corrections made. Note: By final need roof drain splice, check water heater - sub meter - overhead domestic insulation - need accessible side clearance both toilets - check outside hose bib S.W. corner - vtr clearance air intake, check overhead domestic pipe insulation, need accessible clearance at both toilets off finish wall. | DANR | DANR | | PTO | C | 6108271 |
ALL AROUND PLUMBING | PTO | P | 02/14/2019 | Toilet side clearance men's and women's (18-1/2" off drywall), nail protection, domestic water insulation, install outside hose bib with isolation valve, need PRD complete rest ok. Note: By final need roof drain splice, check water heater - sub meter - vtr clearance air intake. | DANR | DANR | | PTO | P | 6107913 |
ALL AROUND PLUMBING | PRD | P | 01/18/2019 | Need plan splice for 5 - 4" roof drains - plumbing drawings show 3, A200 roof plans shows 5, rest ok. | DANR | DANR | | PRD | P | 6082942 |
ALL AROUND PLUMBING | PB | C | 12/12/2018 | NEED LETTER FROM ENGINEER ALLOWING PEX UNDERGROUND IN LIEU OF COPPER, COVER @ OWN RISK, rest ok for test and design @ g.w. and s.s, waters looped under ground | JOHNS | JOHNS | | PB | C | 6050863 |
ALL AROUND PLUMBING | PB | L | 11/20/2018 | called in by accident | JOHNS | JOHNS | | PB | L | 6031140 |
ALL AROUND PLUMBING | PGI | L | 11/08/2018 | local waste water purveyor to inspect outside structure interceptor / grease traps, rbd responsible for inside structure inspections | JOHNS | JOHNS | | PGI | L | 6020296 |
MICK HEATING & SHEET METAL CO. | XMS | P | 06/21/2019 | PLAN SPLICE FEE: $0 by: TCRIPPEN for Mechanical: new splice page revised gas piping added second water heater | TCRIPPEN | TCRIPPEN | | XMS | P | 6239159 |
ALL AROUND PLUMBING | XPS | T | 06/20/2019 | PAID (REC#1608298): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Plumbing splice 6/20/19: Delta 5 revision adjusted water heater schedule, delta 6 revision changed to two tankless water heaters | SHANEN | SHANEN | | XPS | T | 6238610 |
ALL AROUND PLUMBING | XPS | T | 06/04/2019 | PAID (REC#1606085): PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: new splice re routed ducts, added note remove co sensor | TCRIPPEN | TCRIPPEN | | XPS | T | 6219838 |
MICK HEATING & SHEET METAL CO. | XMS | P | 03/15/2019 | PLAN SPLICE FEE: $0 by: JUSTINC for Mechanical: Revised gas | JUSTINC | JUSTINC | | XMS | P | 6133351 |
ALL AROUND PLUMBING | XPS | T | 03/15/2019 | PAID (REC#1582502) PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Plumbing splice 3/15/19: Delta 4 revisions - Tankless water heater schedule,changed to tankless water heater, relocated mop sink and hand sink. | SHANEN | SHANEN | | XPS | T | 6133293 |
MICK HEATING & SHEET METAL CO. | XMS | T | 02/19/2019 | PAID (REC#1578348) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised gas | JUSTINC | JUSTINC | | XMS | T | 6110995 |
CLINT DARNELL, INC. | XBS | T | 10/02/2018 | PAID (REC#1555110) PLAN SPLICE FEE: $50 by: DANM for Construction: Reconfigured kitchen and moved MAU on roof | DANM | DANM | | XBS | T | 5982484 |
CLINT DARNELL, INC. | XPS | P | 09/17/2018 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Plumbing: plumbing splice 9-17-18 | TCRIPPEN | TCRIPPEN | | XPS | P | 5967450 |