COLARELLI CONSTRUCTION, INC. | B= | C | 08/27/2019 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 6315789 |
COLARELLI CONSTRUCTION, INC. | B= | P | 03/22/2019 | items corrected / final OK pending other finals. Additional Inspections Required (computer generated): LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is not Completed yet, RYBA ELECTRIC, INC. Electrical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 6140659 |
COLARELLI CONSTRUCTION, INC. | B= | P | 11/15/2018 | need to complete all MEP finals / still need to splice in change of alternate roll in shower to standard roll in shower / break room and standard roll in shower are OK pending other finals and splice -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is not Completed yet, RIAL HEATING & AIR COND, INC Mechanical Final Inspection is not Completed yet, RYBA ELECTRIC, INC. Electrical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 6026565 |
COLARELLI CONSTRUCTION, INC. | B= | P | 11/08/2018 | Need to installed breakroom cabinets and sink to check accessible elements -- Shower not ready for inspection, still need to splice in change from alternate roll in shower to standard roll in shower -- Rest of building final OK pending other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is not Completed yet, RIAL HEATING & AIR COND, INC Mechanical Final Inspection is not Completed yet, RYBA ELECTRIC, INC. Electrical Final Inspection is not Completed yet. | DAKOTAB | DAKOTAB | | B= | P | 6020011 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 11/06/2018 | light gauge framing at shower OK pending splice to change to standard roll in shower as plans show alternate roll in shower / met with superintendent to discussed roll in shower including seat valve and hand held head with 59" minimum hose and non-positive shutoff valve and the need for a threshold that complies with section 303 of the 2009 ANSI that allows for a 1/2" max rise at threshold if at 1:2 bevel - threshold currently has 1" to top of threshold | DANE | DANE | | BFR | P | 6016960 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 10/03/2018 | interior light gauge framing at break room and shower room OK pending other roughs / plans show shower as roll in shower but super stated that it is to be changed to transfer shower - need to splice in change / discussed accessible elements including transfer shower size and valve placement and and clear floor space and maximum and minimum depth and width | DANE | DANE | | BFR | P | 5984562 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 09/14/2018 | Interior light gauge framing OK pending other roughs -- reviewed accessible elements with site superintendent | DAKOTAB | DAKOTAB | | BFR | P | 5965430 |
RYBA ELECTRIC, INC. | E= | C | 08/27/2019 | | RANDY | RANDY | | E= | C | 6315788 |
RYBA ELECTRIC, INC. | ER | C | 11/05/2018 | shower walls and lid access to 3 boxes at final | BRET | BRET | | ER | C | 6015732 |
RYBA ELECTRIC, INC. | EP | C | 11/05/2018 | transformer and panel | BRET | BRET | | EP | C | 6015718 |
RYBA ELECTRIC, INC. | E= | P | 11/05/2018 | offices and corridors ok break room not ready panel schedule, revise plans , label panel and transformer, need access to 3 boxes in shower lid. need to verify breaker size feeding new transformer | BRET | BRET | | E= | P | 6015716 |
RYBA ELECTRIC, INC. | ER | P | 10/26/2018 | all ceilings except bathroom | RANDY | RANDY | | ER | P | 6007295 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 10/26/2018 | FIRE ALARM INSPECTION: red card signed | RANDY | RANDY | | E= | C | 6007291 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 10/26/2018 | FIRE ALARM INSPECTION: | RANDY | RANDY | | ER | C | 6007245 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 10/26/2018 | FIRE ALARM INSPECTION: | RANDY | RANDY | | E= | C | 6007246 |
RYBA ELECTRIC, INC. | ER | P | 10/03/2018 | in wall shower room and break room --- hard lid in shower room | CRAIGS | CRAIGS | | ER | P | 5984301 |
RYBA ELECTRIC, INC. | ER | P | 09/14/2018 | all walls except showers and break room | RANDY | RANDY | | ER | P | 5965415 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | C | 11/27/2018 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6034524 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 11/16/2018 | MECHANICAL FINAL OK PENDING TEST AND BALANCE REPORT. | DUSTINS | DUSTINS | | H= | P | 6028714 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 10/25/2018 | MINISPLIT OK. ROOF OK. FLEX AND DIFFUSERS OK EXCEPT MISSING SOME RETURN AIR GRILLES, MARKED ON GC'S PLAN. MISSING 6" SUPPLY AIR IN SHOWER AREA BY EF-2. MISSING THERMOSTAT FOR RTU-11. LABEL ALL THERMOSTATS. PROVIDE TEST AND BALANCE REPORT. | DUSTINS | DUSTINS | | H= | P | 6005816 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 09/27/2018 | NEW SUPPLY AIR DUCTS OK, OK TO WRAP. NO FLEX AND DIFFUSERS. STILL NEED TO SEE EXHAUST COMPLETED. NO ROOF TODAY. | DUSTINS | DUSTINS | | HD | P | 5979152 |
LANDMARK PLUMBING AND HEATING, INC. | P= | C | 06/28/2019 | Correction made. | DANR | DANR | | P= | C | 6247241 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 11/16/2018 | Need splice for standard roll in shower and un changed water heater, rest ok. | DANR | DANR | | P= | P | 6027878 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | C | 11/16/2018 | Ok. | DANR | DANR | | PTO | C | 6027876 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 11/05/2018 | Need plan splice for change on alternate roll in to standard roll in, cover at own risk. Note: check water heater at final, need plenum wrap on non rated piping in plenum by final. | DANR | DANR | | PTO | P | 6015753 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 10/03/2018 | In wall dwv and domestic water ok except bathroom plumbing (accessible shower consult). | DANR | DANR | | PTO | P | 5984471 |
LANDMARK PLUMBING AND HEATING, INC. | PB | C | 09/18/2018 | Ok. | DANR | DANR | | PB | C | 5968134 |
RYBA ELECTRIC, INC. | XES | P | 03/15/2019 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: REvise one line | SHELBY | SHELBY | | XES | P | 6133166 |
COLARELLI CONSTRUCTION, INC. | XBS | T | 03/11/2019 | PAID (REC#1583567) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Drawing revision at shower | MICHAELA | MICHAELA | | XBS | T | 6129729 |