GOODWIN KNIGHT, LLC | B= | C | 09/01/2020 | final OK pending other finals per previous inspection. | DANE | DANE | | B= | C | 6693103 |
GOODWIN KNIGHT, LLC | B= | P | 08/20/2020 | pending completion of other required inspections, building okay -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): TEAM PLUMBING, INC. Mechanical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 6679585 |
GOODWIN KNIGHT, LLC | B= | P | 08/19/2020 | inspection was for south tower only, missing CO detectors in units 106 and 207 rest of south tower okay -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): TEAM PLUMBING, INC. Mechanical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 6677986 |
GOODWIN KNIGHT, LLC | BSP | P | 07/27/2020 | drywall install in 3rd floor corridor ceilings and 3rd floor mech room ceilings per P 522 okay / final layer drywall install in 1st and 2nd floor mech room ceilings per spliced detail okay | BOBF | BOBF | | BSP | P | 6650816 |
GOODWIN KNIGHT, LLC | BSP | P | 07/21/2020 | drywall install at 3rd floor corridors and mech rooms not ready / drywall install at 1st and 2nd floor corridors and mech rooms okay | BOBF | BOBF | | BSP | P | 6644503 |
GOODWIN KNIGHT, LLC | BSP | P | 07/09/2020 | ist layer drywall install south corridor ceilings 1st and 2nd floor okay | BOBF | BOBF | | BSP | P | 6631803 |
GOODWIN KNIGHT, LLC | BFR | P | 07/09/2020 | framing for rated drop ceilings in mech rooms 1st and 2nd floors of both towers okay | BOBF | BOBF | | BFR | P | 6631786 |
GOODWIN KNIGHT, LLC | BSP | R | 07/08/2020 | request was for 1st layer drywall install at corridors ceilings of 1st and 2nd floors , drywall has too large gaps on south tower 1st and 2nd floor, 1st and 2nd floor of north tower okay | BOBF | BOBF | | BSP | R | 6630461 |
GOODWIN KNIGHT, LLC | BSP | P | 07/08/2020 | rc channel install at 3rd floor corridor okay | BOBF | BOBF | | BSP | P | 6630444 |
GOODWIN KNIGHT, LLC | BSP | P | 07/06/2020 | rc channel on north tower 3rd floor corridor okay | BOBF | BOBF | | BSP | P | 6627027 |
GOODWIN KNIGHT, LLC | BSP | R | 07/06/2020 | need feed fire damper drops installed before framing is installed in rated drop ceilings | BOBF | BOBF | | BSP | R | 6627016 |
GOODWIN KNIGHT, LLC | BSP | P | 06/29/2020 | drywall install at rated walls and ceilings in all live units of north tower okay | BOBF | BOBF | | BSP | P | 6620568 |
GOODWIN KNIGHT, LLC | BIN | P | 06/29/2020 | rc channel and insulation all garages and riser rooms okay | BOBF | BOBF | | BIN | P | 6620564 |
GOODWIN KNIGHT, LLC | BSP | P | 06/26/2020 | drywall install at rated walls and ceilings all live units in south tower okay | BOBF | BOBF | | BSP | P | 6618922 |
GOODWIN KNIGHT, LLC | BIN | P | 06/11/2020 | Insulation and RC OK throughout units // Still need to see garages and riser rooms | JEREMYA | JEREMYA | | BIN | P | 6601872 |
GOODWIN KNIGHT, LLC | BFR | P | 06/03/2020 | All frame corrections complete pending all other required inspections | ADAML | ADAML | | BFR | P | 6592121 |
GOODWIN KNIGHT, LLC | BFR | P | 06/02/2020 | South tower Unit 105- 1) Still need to complete fire caulking at tub trap above tub / Unit 206- Need to protect opening in ceiling above laundry room / North tower Unit 101- 1) penetration protection in laundry room not completed / Roof vents have been installed but still need to remove tar paper from underneath all vents / All other frame corrections complete | ADAML | ADAML | | BFR | P | 6589999 |
GOODWIN KNIGHT, LLC | BSP | P | 05/27/2020 | training with Adam L - reviewed framing for Type 5B construction - reviewed penetration and membrane protection at rated walls talked about accessibility requirements in apartments with stairs only and with elevators | BOBF | BOBF | | BSP | P | 6584419 |
GOODWIN KNIGHT, LLC | BFR | P | 05/27/2020 | Pending all other required inspections / Inspected North tower livable units and boiler room only / Unit 101- 1) Cannot split drywall for penetration protection in laundry room / Riser room- 1) Top plates damaged at vent and missing fire protection / Unit 203- 1) Strap top plate break at vent in bathroom on both sides / Truss repair letter for bottom chord of truss accepted on site and repair verified / Unit 302- 1) Fire caulk dryer vent / Training with Bob F / Reviewed opening and penetration protection / Reviewed differences between 5A and 5B construction | ADAML | ADAML | | BFR | P | 6584363 |
GOODWIN KNIGHT, LLC | BFR | P | 05/26/2020 | Pending all other required inspections / Inspected South tower livable units and boiler room only / Unit 104 - 1) Missing fire protection in lid of concealed space next to tub 2) Fire caulk tub trap above ceiling 3) Complete fire protection on tub trap above laundry room / Unit 106 - 1) Shim trimmers on window header in front room 2) Missing fire caulk on vent pipe in laundry room / Riser room - 1) Top plates damaged at 4" pvc and missing fire protection / Unit 205 - 1) Missing fire protection at openings in bottom plate in laundry room / Unit 206 - 1) Missing fire protection at tub trap above ceiling / Unit 207 - 1) Pex penetration through top flange of open web truss above tub / Unit 306 - 1) Need to remove tar paper and install roof vents throughout 2) Missing fire protection at bottom plate in laundry room 3) Strap top plate break at beam in main room / Unit 308 - 1) Need nail protection plate in bathroom HVAC vent on both sides / Training with Bob F / Reviewed rated floor/ceiling assemblies / Reviewed opening and penetration protection / Reviewed general framing for type 5B construction / Reviewed drywall protection at tub traps and rated collars with 4" pvc pipes | ADAML | ADAML | | BFR | P | 6582814 |
GOODWIN KNIGHT, LLC | BSP | P | 05/26/2020 | training with Adam L. - reviewed elements of frame inspection of type 5B construction including penetration protection , protection at concealed spaces, rated wall and ceiling assemblies / requirements for draftstop at unsprinkled areas within floor ceiling and roof ceiling assemblies | BOBF | BOBF | | BSP | P | 6582800 |
GOODWIN KNIGHT, LLC | BFR | P | 04/27/2020 | truss repairs per eng letters okay truss repair letters received | BOBF | BOBF | | BFR | P | 6552240 |
GOODWIN KNIGHT, LLC | BLA | C | 04/22/2020 | | BOBF | BOBF | | BLA | C | 6548408 |
GOODWIN KNIGHT, LLC | BLA | P | 04/10/2020 | north tower okay / entire west side and south side okay / still need to complete east side of south tower | BOBF | BOBF | | BLA | P | 6537320 |
GOODWIN KNIGHT, LLC | BFR | P | 04/07/2020 | inspection for trusses only , truss hardware throughout okay / truss repairs throughout not done per details, will need to inspect damaged trusses throughout | BOBF | BOBF | | BFR | P | 6533979 |
GOODWIN KNIGHT, LLC | BFR | P | 04/01/2020 | deck framing all units okay | BOBF | BOBF | | BFR | P | 6528034 |
GOODWIN KNIGHT, LLC | BFR | R | 03/13/2020 | request was for truss inspection, inspection stopped, missing hardware in 1st 3 units , not ready | BOBF | BOBF | | BFR | R | 6510212 |
GOODWIN KNIGHT, LLC | BSP | P | 03/12/2020 | drywall install at rated corridor walls, both towers, 1st, 2nd and 3rd floors per WP 8105 okay | BOBF | BOBF | | BSP | P | 6508862 |
GOODWIN KNIGHT, LLC | BFR | P | 03/04/2020 | framing at revised riser room okay | BOBF | BOBF | | BFR | P | 6499586 |
GOODWIN KNIGHT, LLC | BFR | R | 02/26/2020 | Beam to beam connection at all interior decks call for HUCQ 210- SDS hangars each end, SDS screws not installed per simpson handbook | BOBF | BOBF | | BFR | R | 6493787 |
GOODWIN KNIGHT, LLC | BFR | R | 02/13/2020 | need to splice plans showing expanded size of riser room, also need to show added floor joists, ledger attachment and approval of non floating-wall sitting directly on existing garage floor, | BOBF | BOBF | | BFR | R | 6481435 |
GOODWIN KNIGHT, LLC | BFR | P | 01/07/2020 | shear wall nailing at breezeways north and south towers okay | BOBF | BOBF | | BFR | P | 6445149 |
GOODWIN KNIGHT, LLC | BFR | R | 01/06/2020 | nailing at breezeway sheer not ready | NATHAN | NATHAN | | BFR | R | 6443773 |
GOODWIN KNIGHT, LLC | BFR | P | 10/24/2019 | exterior shear wall nailing okay | BOBF | BOBF | | BFR | P | 6379298 |
GOODWIN KNIGHT, LLC | BSP | P | 09/05/2019 | osb install on interior north-south wall separating units on 2nd floor okay | BOBF | BOBF | | BSP | P | 6324758 |
GOODWIN KNIGHT, LLC | BSP | P | 08/07/2019 | type 1 shear wall running north - south at north tower 1st floor okay | BOBF | BOBF | | BSP | P | 6291620 |
GOODWIN KNIGHT, LLC | BSP | P | 08/07/2019 | training with inspector Bob F / walked shear wall inspection for north slab first level | LONNYS | LONNYS | | BSP | P | 6291605 |
GOODWIN KNIGHT, LLC | BSP | P | 08/05/2019 | 1st floor interior shear wall separating units on south side okay / 1st floor shear wall running east to west in middle of building okay | BOBF | BOBF | | BSP | P | 6288075 |
GOODWIN KNIGHT, LLC | BFN | P | 09/26/2018 | Authorized Third Party Observations - Stamped Letters to Follow | JEREMYA | JEREMYA | | BFN | P | 5977824 |
GOODWIN KNIGHT, LLC | BFT | P | 09/26/2018 | Authorized Third Party Observations - Stamped Letters to Follow | JEREMYA | JEREMYA | | BFT | P | 5977823 |
COLORADO SECURITY, LLC | E= | C | 08/14/2020 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | E= | C | 6673793 |
DIE HARD, INC | E= | C | 08/13/2020 | 301--302--303--304---ok with ac units | BRIAN | BRIAN | | E= | C | 6672139 |
DIE HARD, INC | E= | P | 08/12/2020 | 201--202--203--204---ok / | BRIAN | BRIAN | | E= | P | 6670294 |
DIE HARD, INC | E= | P | 08/11/2020 | ac units ---units 101--102--104---ok / | BRIAN | BRIAN | | E= | P | 6669092 |
DIE HARD, INC | E= | P | 08/10/2020 | 105--106--107---ok / no garages they are full of supplies / | BRIAN | BRIAN | | E= | P | 6667149 |
DIE HARD, INC | E= | P | 08/07/2020 | 205--206--207--208----ok | BRIAN | BRIAN | | E= | P | 6665035 |
DIE HARD, INC | E= | P | 08/06/2020 | 305--306--307--308---ok / | BRIAN | BRIAN | | E= | P | 6663777 |
COLORADO SECURITY, LLC | ER | P | 05/21/2020 | all units ok-- need riser room / | BRIAN | BRIAN | | ER | P | 6579497 |
DIE HARD, INC | ER | C | 05/21/2020 | | BRIAN | BRIAN | | ER | C | 6579495 |
DIE HARD, INC | ER | R | 05/13/2020 | need fire alarm permit pulled / | BRIAN | BRIAN | | ER | R | 6570906 |
DIE HARD, INC | ER | P | 04/28/2020 | rework of bathrooms--ok | BRIAN | BRIAN | | ER | P | 6554573 |
DIE HARD, INC | ER | P | 04/24/2020 | all units--ok / need riser room complete | BRIAN | BRIAN | | ER | P | 6551672 |
DIE HARD, INC | ER | R | 02/26/2020 | Electrical rough in complete - still need fire alarm to complete | CHIPO | CHIPO | | ER | R | 6492703 |
DIE HARD, INC | ER | R | 02/21/2020 | do not wrap the ground around the ground screw 3 times / need the ac whips stubbed out / need fire alarm complete | BRIAN | BRIAN | | ER | R | 6489350 |
DIE HARD, INC | ER | R | 02/20/2020 | units on 2nd and 3rd floor plus corridors ok pending fire alarm / Electrical rough ok, FA not complete,-------- do not close walls-------------- / | MIGUEL | MIGUEL | | ER | R | 6486958 |
DIE HARD, INC | ES | C | 01/10/2020 | Commercial Service: 1600 amp 3-w / ---ok to set meters in units / 101--102--104--105--106---107-201--202--203--204--205--206--207--208--301--302--303--304--305--306--307--308----house panel 1850 ---- | BRIAN | BRIAN | | ES | C | 6450052 |
TEAM PLUMBING, INC. | H= | C | 09/01/2020 | GAS FINAL OK, METER VERIFICATION LETTER RECEIVED FROM C.S.U. | BENH | BENH | | H= | C | 6692169 |
STEELE BROS. HEATING, INC | H= | C | 08/18/2020 | BUILDING 5: HVAC FINAL OK, NEED GAS CONTRACTOR TO CALL FOR FINAL AND BUILDING WILL BE CLOSED OUT FOR MECHANICAL | BENH | BENH | | H= | C | 6676337 |
STEELE BROS. HEATING, INC | H= | P | 08/17/2020 | INSPECTION WAS FOR SOUTH TOWER UNITS, ALL OK, STILL NEED TO SEE NORTH TOWER AND ALL CONDENSERS | BENH | BENH | | H= | P | 6674460 |
STEELE BROS. HEATING, INC | HD | C | 07/29/2020 | BUILDING 5: INSPECTION WAS FOR ANNULAR SPACE TO REGISTER AND SHEETROCK, NORTH AND SOUTH TOWERS OK TO INSTALL REGISTERS , ALSO LOOKED AT UNIT 101 AND 106 DUCT BELOW PRE ROCK, OK TO COVER PER MECHANICAL | BENH | BENH | | HD | C | 6653783 |
STEELE BROS. HEATING, INC | HD | P | 07/08/2020 | INSPECTION WAS FOR NORTH TOWER MECHANICAL ROOMS CEILING RADIATION DAMPERS ABOVE CEILING, STILL NEED TO SEE 3RD FLOOR MECHANICAL ROOM CEILING RADIATION DAMPERS ON NORTH AND SOUTH TOWERS | BENH | BENH | | HD | P | 6629980 |
STEELE BROS. HEATING, INC | HD | P | 07/06/2020 | INSPECTION WAS FOR MECHANICAL ROOM CEILING RADIATION DAMPERS ON 1ST AND 2ND FLOOR SOUTH TOWER, OK TO COVER STILL NEED TO SEE 3RD FLOOR SOUTH TOWER MECHANICAL ROOMS AND ALL FLOORS ON NORTH TOWER | BENH | BENH | | HD | P | 6626741 |
STEELE BROS. HEATING, INC | HD | P | 05/27/2020 | BUILDING 5: INSPECTION WAS FOR 3 RD FLOOR MECHANICAL ROOMS CEILING RADIATION DAMPERS ON NORTH AND SOUTH TOWERS,ABOVE CEILING OK, STILL NEED TO SEE 1ST AND SECOND FLOOR MECHANICAL ROOMS ON NORTH AND SOUTH TOWERS | BENH | BENH | | HD | P | 6583833 |
STEELE BROS. HEATING, INC | HRP | C | 05/12/2020 | 22- 350 LB TEST OK FOR NORTH AND SOUTH TOWERS | BENH | BENH | | HRP | C | 6568226 |
STEELE BROS. HEATING, INC | HD | P | 04/30/2020 | BUILDING 5: SOUTH TOWER SUPPLY AND EXHAUST ABOVE PRE ROCK OK, STILL NEED DUCT INSPECTION BELOW PRE ROCK ON NORTH AND SOUTH TOWERS AND HRP INSPECTION FOR LINE SETS ON NORTH AND SOUTH TOWERS | BENH | BENH | | HD | P | 6556613 |
STEELE BROS. HEATING, INC | HV | P | 04/28/2020 | INSPECTION WAS FOR NORTH TOWER FURNACE VENTS, ALL VENTS ABOVE PRE ROCK OK, EXCEPT UNIT 102, IT IS INCOMPLETE ABOVE CEILING | BENH | BENH | | HV | P | 6553646 |
STEELE BROS. HEATING, INC | HD | P | 04/28/2020 | NORTH TOWER SUPPLYS AND EXHAUST ABOVE PRE ROCK OK, WILL NEED HRP INSPECTION FOR ALL BRAZED LINE SET IN CONCEALED WALLS, STILL NEED TO SEE ALL DUCT ABOVE PRE ROCK ON SOUTH TOWER, AND ALL DUCT BELOW PRE ROCK WHEN INSTALLED ON NORTH AND SOUTH TOWERS | BENH | BENH | | HD | P | 6553645 |
STEELE BROS. HEATING, INC | HSP | P | 04/28/2020 | LETTER FROM ENGINEER ADDRESSING NO NEED FOR FURNACE SHUTDOWNS, SEE IMAGES | BENH | BENH | | HSP | P | 6553230 |
TEAM PLUMBING, INC. | HC | C | 02/19/2020 | RELEASE 22 METERS FOR THIS BUILDING THANKS | BENH | BENH | | HC | C | 6485578 |
TEAM PLUMBING, INC. | HI | C | 02/19/2020 | NEED MECHANICAL CONTRACTOR INSTALLING DUCT WORK TO ATTACH TO PERMIT AND CALL FOR INSPECTION WHEN READY | BENH | BENH | | HI | C | 6485570 |
TEAM PLUMBING, INC. | HI | P | 02/18/2020 | MECHANICAL CONTRACTOR MUST ATTACH TO PERMIT AND CALL FOR INSPECTION WHEN READY. SECURE GAS LINE TERMINATIONS ON SECOND FLOOR. ELEVEN 10 LB TESTS OK. INSTALLED AS PER PLAN ON SPLICE (BDA 287). | NANCY | NANCY | | HI | P | 6484453 |
TEAM PLUMBING, INC. | HI | P | 02/06/2020 | 2/18/20: Changed from complete to partial, still need to inspect north tower. NS. SOUTH TOWER ALL 11 GAS LINES INSTALLED PER SPLICE ON PAGE 287 IN BDA, STILL NEED TO SEE NORTH TOWER BEFORE I CAN RELEASE METER FOR BUILDING | BENH | BENH | | HI | P | 6475268 |
TEAM PLUMBING, INC. | HI | P | 02/05/2020 | SUPPORT 3/4" GAS LINE EVERY 8 FEET REFER TABLE 415.1 IN 2015 IFGC, GAS LINE INSTALLED PER SPLICE DATED 3/26/2019 IN BDA PAGE 287 11- 10 LB TEST OK | BENH | BENH | | HI | P | 6474204 |
TEAM PLUMBING, INC. | PB | C | 08/18/2020 | water stubbed into water entry | JOHNS | JOHNS | | PB | C | 6676259 |
TEAM PLUMBING, INC. | PTO | C | 08/18/2020 | 1st floor floor drains @ kitchen pantry has been deleted per engineer | JOHNS | JOHNS | | PTO | C | 6676257 |
TEAM PLUMBING, INC. | P= | C | 08/18/2020 | this completes all plbg phases | JOHNS | JOHNS | | P= | C | 6676252 |
TEAM PLUMBING, INC. | P= | P | 08/17/2020 | Unit 102 need toilet set rest ok this unit. Ok for the following units: 101 - 104 - 201 - 202 - 203 - 204 - 301 - 302 - 303 - 304. | DANR | DANR | | P= | P | 6674590 |
TEAM PLUMBING, INC. | PTO | P | 04/30/2020 | still need engineers approval for floor drains in kitchen pantry in lieu of laundry room
rest ok for all PTO | JOHNS | JOHNS | | PTO | P | 6557168 |
TEAM PLUMBING, INC. | PTO | P | 04/28/2020 | ok for tubs and accessible measurements MINUS @ 301 leak @ tub shoe, 302 & 304 s-trap @ tub drain, and 204 strap tub drain
STILL NEED engineers appeoval for floor drains in kitchen pantry in lieu of laundry rooms | JOHNS | JOHNS | | PTO | P | 6553781 |
TEAM PLUMBING, INC. | PTO | P | 02/26/2020 | Ok for Freeze protection North Breezway. Ok for tub drain repair unit 305 in 205 ceiling. | DANR | DANR | | PTO | P | 6493777 |
TEAM PLUMBING, INC. | PTO | P | 02/24/2020 | need to rfi engineer about floor drains in kitchen pantry and not in laundry room (is it ok to cap and delete floor drain or does it need to be relocated to laundry room---has post tension cables inside slab)
ok for south tower freeze protection, dwv, and unit waters only MINUS @ 205 s-trap @ upr tub, need all tubs set and tested, and all 1st floor accessible measurements. NOTE: vtr, check water htrs and water entry @ final, @ 106 aav - waasher box (right side wall), aav- water entry, @ 105 aav- washer box ( right side), @ 107 aav - washer box (right side), and @ 206 aav- washer box (left side) | JOHNS | JOHNS | | PTO | P | 6490316 |
TEAM PLUMBING, INC. | PTO | P | 02/18/2020 | DWV and domestic water the following units / all units need tubs set and tested / all 1st floor units need toilet flange inspection after tubs are set: 101 nail protection storage room side by garage, rest ok this unit - AAV laundry and mechanical storage room side.room side. 102 ok - AAV laundry / 104 ok - AAV laundry. 201 nail protection laundry, rest ok this unit - AAV laundry / 202 - 203 - 204 ok. 301-302-303-304 ok.
| DANR | DANR | | PTO | P | 6485188 |
TEAM PLUMBING, INC. | PTO | P | 02/12/2020 | Domestic water main and risers only: Need freeze protection breezeways, rest bof corrections ok. Note: need isolation valves at units at final / check water entry at final / need hose bib isolation valve access unit 102 above washer (2) and mechanical room ceiling unit 101 (1), | DANR | DANR | | PTO | P | 6480659 |
TEAM PLUMBING, INC. | PTO | P | 02/11/2020 | Domestic water main and risers only: Need pipe support / nail protection / freeze protection breezeways / test ok. Note: need isolation valves at units at final / check water entry at final / need hose bib isolation valve access unit 102 above washer (2) and mechanical room ceiling unit 101 (1),. | DANR | DANR | | PTO | P | 6479633 |
TEAM PLUMBING, INC. | PB | P | 01/23/2019 | Need water stubbed, rest ok | DANR | DANR | | PB | P | 6086267 |
TEAM PLUMBING, INC. | PB | P | 01/18/2019 | Need proper bedding around piping, tub stand pipes over 24" North and South side, re-inspect all. | DANR | DANR | | PB | P | 6083282 |
TEAM PLUMBING, INC. | PB | P | 10/26/2018 | ok for bldg 5 type 3 deep base risers. NOTE: 6" trunk line | JOHNS | JOHNS | | PB | P | 6006924 |
TEAM PLUMBING, INC. | PB | L | 10/24/2018 | all access roads blocked off @ time of inspection, possible dry fill dirt needed, re inspect all | JOHNS | JOHNS | | PB | L | 6004348 |
GOODWIN KNIGHT, LLC | XBS | T | 05/27/2020 | PAID (REC#1683199): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Trusses | MICHAELA | MICHAELA | | XBS | T | 6583502 |
GOODWIN KNIGHT, LLC | XBS | T | 02/26/2020 | PAID (REC#1665561): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Relocate water entry room | MICHAELA | MICHAELA | | XBS | T | 6493281 |
GOODWIN KNIGHT, LLC | XBS | T | 11/25/2019 | PAID (REC#1653556): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Clarify penetrations at Mech. closet | MICHAELA | MICHAELA | | XBS | T | 6410046 |
GOODWIN KNIGHT, LLC | XES | T | 11/01/2019 | PAID (REC#1653557): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revise service lateral | SHELBY | SHELBY | | XES | T | 6385616 |
GOODWIN KNIGHT, LLC | XBS | T | 06/05/2019 | PAID (REC#1620297): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Clarify rated assemblies | MICHAELA | MICHAELA | | XBS | T | 6220612 |
GOODWIN KNIGHT, LLC | XES | P | 04/09/2019 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: Revise hallway lighting | SHELBY | SHELBY | | XES | P | 6160652 |
GOODWIN KNIGHT, LLC | XES | T | 04/09/2019 | PAID (REC#1588917) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised lighting. | BERTHA | BERTHA | | XES | T | 6160019 |