FALCON BUILDERS, LLC | B= | C | 02/20/2019 | All other required Final inspections are complete. (This is a computer generated result) | CHUCK | CHUCK | | B= | C | 6111817 |
FALCON BUILDERS, LLC | B= | P | 01/08/2019 | Bldg final inspection - interior remodel OK per amended and approved plans. / Partial pending completion of electrical final inspection. Additional Inspections Required (computer generated): TRUSTED ELECTRIC Electrical Final Inspection is not Completed yet. | CHUCK | CHUCK | | B= | P | 6072413 |
FALCON BUILDERS, LLC | BFR | R | 11/01/2018 | BFR inspection cancelled by Stan Lewis by phone. Working to correct plan and will recall inspection for a later date. | CHUCK | CHUCK | | BFR | R | 6013331 |
FALCON BUILDERS, LLC | BFR | R | 10/23/2018 | BFR re-inspection / GA WP1052 and WP1072 still do not meet the listing requirements as built on site. Contractor to check with architect for a compliance alternative for the walls that separate the S and B/M occupancies. | CHUCK | CHUCK | | BFR | R | 6003286 |
FALCON BUILDERS, LLC | BFR | R | 10/22/2018 | BFR re-inspection / Architect spliced a GA WP1070 and 1052 - 1 hr. fire resistance rated wall assembly since UL U415 did not accommodate what was constructed on site. However, both GA listings also do not reflect the assemblies as partially constructed due to orientation and thickness of drywall material installed (WP1070), spacing of metal studs (both assemblies) and cavity fill requirements (WP1070). Contractor may have architect look into prescriptive/calculated fire resistance out of the IBC (Section 720/721) or use another assembly that suits the walls as constructed. | CHUCK | CHUCK | | BFR | R | 6002287 |
FALCON BUILDERS, LLC | BFR | P | 10/11/2018 | BFR inspection / Non-bearing 1 hr. fire-resistance rated metal frame wall OK per Sht. A1 of the approved plans. Contractor to discuss change of listed assembly wall with architect to sync with existing conditions and materials in place. UL U415 assembly called out on plans. American Gypsum product used on site does not meet listing requirements and existing assembly has 2 layers of gyp on 1 side. | CHUCK | CHUCK | | BFR | P | 5992057 |
TRUSTED ELECTRIC | E= | C | 02/20/2019 | | CRAIG | CRAIG | | E= | C | 6111816 |
TRUSTED ELECTRIC | E= | P | 02/19/2019 | need splice for lighting | CRAIG | CRAIG | | E= | P | 6110300 |
TRUSTED ELECTRIC | E= | P | 12/10/2018 | front lobby and back storage area --------- splice lighting to show number of lights in tint area | CRAIG | CRAIG | | E= | P | 6047667 |
TRUSTED ELECTRIC | ER | P | 12/10/2018 | above ceiling in front lobby and tint area and sales floor. ok
| CRAIG | CRAIG | | ER | P | 6047662 |
TRUSTED ELECTRIC | ER | P | 10/08/2018 | walls see plans---ok | BRIAN | BRIAN | | ER | P | 5988732 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | H= | C | 11/29/2018 | TEST AND BALANCE REPORT RECEIVED | MARKB | MARKB | | H= | C | 6037344 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | H= | P | 11/28/2018 | FINAL PENDING - Test And Balance Report | MARKB | MARKB | | H= | P | 6036248 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | H= | P | 11/20/2018 | Get all screws installed in damper angles, install supply diffuser in back hallway and provide Test And Balance report. | MARKB | MARKB | | H= | P | 6030874 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | HD | C | 11/20/2018 | FLEX AND DIFFUSERS INSTALLED EXCEPT SUPPLY IN HALL | MARKB | MARKB | | HD | C | 6030860 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | HD | P | 11/19/2018 | DAMPER FRAMING OVER DOUBLE DOORS PER ENGINEER DRAWING - SEE IMAGES | MARKB | MARKB | | HD | P | 6029209 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | HD | P | 11/12/2018 | Framing for damper over double doors not yet completed. Still need engineer to address damper support over double doors. | MARKB | MARKB | | HD | P | 6022695 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | HD | P | 11/08/2018 | ----Will Need engineer to address damper support over double doors and how support meets the intent of the manufacturer instructions (discussed with Stan Lewis on site)---- Still need to see framing for return air damper over double door. DAMPER INSTALL - 14" ROUND FIRE DAMPERS FRAMED AND INSTALLED PER MANUFACTURER INSTRUCTIONS - Still need access doors installed in duct. ABOVE CEILING DUCT - SUPPLY MAINS INSTALLED PER PLAN OK TO WRAP. DUCT TO WAREHOUSE FOR 7.5 TON RTU CAPPED OFF INSIDE PER NOTE #14 M1 SPLICE. No Flex or diffusers this inspection. | MARKB | MARKB | | HD | P | 6020587 |
TRUSTED ELECTRIC | XES | T | 02/19/2019 | PAID (REC#1577230) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Splice to address inspector's comments - added lighting. | BERTHA | BERTHA | | XES | T | 6110973 |
FALCON BUILDERS, LLC | XBS | T | 11/01/2018 | PAID (REC#1552963) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Note walls not rated per IBC | MICHAELA | MICHAELA | | XBS | T | 6012923 |
FALCON BUILDERS, LLC | XBS | T | 11/01/2018 | PAID (REC#1552831) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Non-structural walls | MICHAELA | MICHAELA | | XBS | T | 6012581 |
TRUSTED ELECTRIC | XES | T | 10/25/2018 | PAID (REC#1550954) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Removed service upgrade portion - Revised one-line, site and floor plans to indicate existing Panel A. | BERTHA | BERTHA | | XES | T | 6006272 |
FALCON BUILDERS, LLC | XBS | T | 10/23/2018 | PAID (REC#1549935) PLAN SPLICE FEE: $50 by: DANM for Construction: Fire rated walls revised listed assemblies | DANM | DANM | | XBS | T | 6002694 |
FALCON BUILDERS, LLC | XMS | P | 10/19/2018 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Revised duct layout | JUSTINC | JUSTINC | | XMS | P | 6000692 |
FALCON BUILDERS, LLC | XBS | T | 10/18/2018 | PAID (REC#1548859) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Add assemblies and new wall with openings | MICHAELA | MICHAELA | | XBS | T | 5999254 |