BALANCED BUILDERS, INC. | B= | C | 12/19/2019 | Building final OK - No A/C, No deck, slab on grade. | CHUCK | CHUCK | | B= | C | 6432549 |
BALANCED BUILDERS, INC. | BSP | P | 12/19/2019 | UES report for spray foam on file - will need to verify thermal barrier requirements met at final inspection. | CHUCK | CHUCK | | BSP | P | 6431831 |
BALANCED BUILDERS, INC. | BIN | C | 12/19/2019 | 3rd party air leakage report on file. | CHUCK | CHUCK | | BIN | C | 6431824 |
BALANCED BUILDERS, INC. | BIN | P | 12/13/2019 | Need to verify spray foam is covered by prescriptive thermal barrier at final. | CHUCK | CHUCK | | BIN | P | 6426674 |
BALANCED BUILDERS, INC. | BLA | C | 11/20/2019 | | CHUCK | CHUCK | | BLA | C | 6406024 |
BALANCED BUILDERS, INC. | BIN | P | 11/18/2019 | installers cert for spray foam on file / states R28 installed | DANE | DANE | | BIN | P | 6401814 |
BALANCED BUILDERS, INC. | BIN | P | 10/14/2019 | Spray foam insulation installed - all behind a thermal barrier according to contractor - will need insulation cert prior to final inspection. | CHUCK | CHUCK | | BIN | P | 6367261 |
BALANCED BUILDERS, INC. | BIN | R | 10/11/2019 | Insulation not complete at time of inspection - no certificate found on site. | CHUCK | CHUCK | | BIN | R | 6365553 |
BALANCED BUILDERS, INC. | BFR | C | 10/08/2019 | corrections complete | SCOTTS | SCOTTS | | BFR | C | 6361594 |
BALANCED BUILDERS, INC. | BFR | P | 10/07/2019 | Fire blocking not started - rest of frame OK. Slab on grade construction. | CHUCK | CHUCK | | BFR | P | 6359913 |
BALANCED BUILDERS, INC. | BSP | P | 08/19/2019 | R10 insulation observed at entire slab of interior floors | JUSTINL | JUSTINL | | BSP | P | 6305674 |
BALANCED BUILDERS, INC. | BSP | P | 07/30/2019 | Inspection request for flat roof over entry - CS16 straps at top side of rafters OK - Still need to inspect remaining framing / 8x8 post base at 3 interior locations and 3 exterior locations OK / Ice and water shield at entire roof deck / Address open wrecking permit for address/After further review on 8-15-19 by Bert W Demo permit is not Balanced Builders responsibility | JUSTINL | JUSTINL | | BSP | P | 6281899 |
BALANCED BUILDERS, INC. | BFN | C | 07/30/2019 | Foundation design on file (Bearing Capacity Verified) / | JUSTINL | JUSTINL | | BFN | C | 6281870 |
BALANCED BUILDERS, INC. | BFT | C | 07/30/2019 | Foundation design on file | JUSTINL | JUSTINL | | BFT | C | 6281850 |
BALANCED BUILDERS, INC. | BSP | P | 05/16/2019 | Still need to complete wrecking permit ( I85685 ) | JUSTINL | JUSTINL | | BSP | P | 6201018 |
BALANCED BUILDERS, INC. | BFI | C | 05/15/2019 | R10 installed | JUSTINL | JUSTINL | | BFI | C | 6200657 |
BALANCED BUILDERS, INC. | BFD | C | 05/15/2019 | Drain entire to daylight at east side of foundation / Damp proof OK | JUSTINL | JUSTINL | | BFD | C | 6200649 |
BALANCED BUILDERS, INC. | BFN | P | 05/15/2019 | Engineer letter for foundation on file -- Eufer noted / Request stamped foundation design | JUSTINL | JUSTINL | | BFN | P | 6200646 |
BALANCED BUILDERS, INC. | BFT | P | 05/15/2019 | Engineer letter for footing on file -- Open hole on file - 4000 PSF / No drain required per open hole / 5% / Request stamped foundation design | JUSTINL | JUSTINL | | BFT | P | 6200643 |
MDH ELECTRIC, LLC | E= | C | 12/12/2019 | E= OK ------NO A/C ------- | GREGM | GREGM | | E= | C | 6425683 |
MDH ELECTRIC, LLC | ES | C | 10/02/2019 | Residential Underground: 200-amp 3-wire service upgrade, no action required by utility. / | TOMC | TOMC | | ES | C | 6355545 |
MDH ELECTRIC, LLC | ER | C | 10/02/2019 | 1 - 1/0 , 1 - #6 , 2 - #10 , 1 - 20 amp mcc , no central vac , slab on grade , uffer is not irreversible | TOMC | TOMC | | ER | C | 6355534 |
MDH ELECTRIC, LLC | EUG | C | 08/07/2019 | EUG OK ----4/O URD X# 2------ | GREGM | GREGM | | EUG | C | 6292148 |
MDH ELECTRIC, LLC | ESL | C | 08/01/2019 | 3 - 2" , 1 - 1/2" | TOMC | TOMC | | ESL | C | 6285351 |
GENE'S HEATING AND AIR LLC | H= | C | 12/18/2019 | | KYLEW | KYLEW | | H= | C | 6430735 |
GENE'S HEATING AND AIR LLC | H= | P | 12/17/2019 | Need to label all medium pressure gas piping in garage and at meter. You can attach pictures to the permit when re scheduling for a final. | MARK | MARK | | H= | P | 6430370 |
GENE'S HEATING AND AIR LLC | H= | P | 12/12/2019 | Still need letter from mfg regarding cross lines in slab. See notes from HWP inspection on 16 Aug. Need access to gas regulators for fireplace and gas cook top. (Both are located in the kitchen island) Need to label all medium pressure gas piping. Need to label the whole house ventilation switch located in the laundry room. Need to raise the sauna guard per mfg instructions pg 2.Boiler verified meets equipment schedule. Note: 2# letter received, Boiler is direct vented, side arm, no water heater. | MARK | MARK | | H= | P | 6425860 |
WESTERN FIREPLACE SUPPLY, INC. | HC | C | 10/04/2019 | RELEASE METER | KYLEW | KYLEW | | HC | C | 6358819 |
WESTERN FIREPLACE SUPPLY, INC. | HV | C | 10/04/2019 | fireplace vent and framing ok. | KYLEW | KYLEW | | HV | C | 6358800 |
GENE'S HEATING AND AIR LLC | HRR | C | 10/04/2019 | at final verify boiler installation. whole house ventilation will be provided by 110 cfm laundry fan running continuous and the switch location is to be determined. ----- notes: in floor radiant heat. | KYLEW | KYLEW | | HRR | C | 6358794 |
COLORADO GAS SYSTEMS | HI | C | 09/25/2019 | 10 LB TEST OK. 1" MAIN 1 BOILER, 1 RANGE, 1 FIREPLACE, 1 BBQ. ALL STENCILING AND REGULATORS ARE IN PLACE. BY FINAL WILL NEED 2 LB LETTER ON FILE. | KYLEW | KYLEW | | HI | C | 6347363 |
JOEAGLE PLUMBING & HEATING, INC. | HWP | C | 08/16/2019 | WILL NEED LETTER FROM MANUFACTURER STATING IT IS OK TO CROSS LINES UNDER SLAB BY FINAL. CONTRACTOR CONTACTED THEM BY PHONE DURING INSPECTION AND THEY STATED IT WAS OK. 100 LB TEST OK. R10 INSULATION IN PLACE. | KYLEW | KYLEW | | HWP | C | 6303509 |
JOEAGLE PLUMBING & HEATING, INC. | P= | C | 12/19/2019 | Potable Water Certificate Received | MALYNDA | MALYNDA | | P= | C | 6431892 |
JOEAGLE PLUMBING & HEATING, INC. | P= | P | 12/18/2019 | Need potable water certificate, rest ok Note: pvb installed on East side of house for irrigation on the East side only | MALYNDA | MALYNDA | | P= | P | 6430888 |
JOEAGLE PLUMBING & HEATING, INC. | PTO | C | 09/26/2019 | Note: Check water service connections at final, boiler to be installed by final, check for whirlpool pump access by final, tempering in master toilet, aav at left master lav and in mech room. | MALYNDA | MALYNDA | | PTO | C | 6349512 |
HOMEOWNER | PWO | C | 06/04/2019 | check water service connection in pit by final, note: need certificate of potable water, backflow is installed in pit for yard hydrants. | TAYLOR | TAYLOR | | PWO | C | 6219331 |
JOEAGLE PLUMBING & HEATING, INC. | PB | C | 05/20/2019 | H2O looped underground, no water service at this time. | TAYLOR | TAYLOR | | PB | C | 6204352 |
BALANCED BUILDERS, INC. | XBS | T | 10/07/2019 | PAID (REC#1635382) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Modify structure | MICHAELA | MICHAELA | | XBS | T | 6359404 |