BLUE RIDGE CONTRACTORS, INC. | B= | C | 11/06/2019 | Sign off | JEREMYA | JEREMYA | | B= | C | 6390591 |
BLUE RIDGE CONTRACTORS, INC. | B= | P | 10/31/2019 | Temp CO: Pending mechanical final ( Expires: 11/30/2019 12:00:00 AM) | RITA | RITA | | B= | P | 6384673 |
BLUE RIDGE CONTRACTORS, INC. | B= | P | 10/18/2019 | Building final OK pending other finals. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, ALPHALETE MECHANICAL LLC Mechanical Final Inspection is not Completed yet, ALPHALETE MECHANICAL LLC Plumbing Final Inspection is not Completed yet, PEAK HEATING & AIR COND, INC. Mechanical Final Inspection is not Completed yet. | DAKOTAB | DAKOTAB | | B= | P | 6373897 |
BLUE RIDGE CONTRACTORS, INC. | BFR | P | 04/23/2019 | attach plumbing and mechanical permits/complete roughs -- frame ok -- Reviewed Accessible Elements / | SCOTTS | SCOTTS | | BFR | P | 6175246 |
ROCKY MOUNTAIN ELECTRICAL SERVICES INC | E= | C | 10/09/2019 | Hot checked entire restaurant, also inspected all electrical rough for above ceiling. | JOSEPH | JOSEPH | | E= | C | 6363049 |
ROCKY MOUNTAIN ELECTRICAL SERVICES INC | ER | P | 04/18/2019 | front counter,sales and office walls | RANDY | RANDY | | ER | P | 6170885 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 11/01/2019 | HEAT FINAL OK. | LIDO | LIDO | | H= | C | 6385868 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 11/01/2019 | RECEIVED TEST AND BALANCE REPORT ( SEE IMAGES ) | LIDO | LIDO | | H= | P | 6385289 |
ALPHALETE MECHANICAL LLC | H= | C | 10/28/2019 | HEAT FINAL OK. | LIDO | LIDO | | H= | C | 6382288 |
ALPHALETE MECHANICAL LLC | H= | P | 10/24/2019 | PARTIAL PENDING -NEED INSTALL INSTRUCTION FOR INSPECTION OF CONCENTRIC VENT TERMINATION ON ROOF. WATER HEATER VENT INSIDE WAS INSPECTED AT AN EARLIER DATE AND ROOF WAS NOT ACCESSIBLE AT THAT TIME. | LIDO | LIDO | | H= | P | 6379873 |
ALPHALETE MECHANICAL LLC | HV | P | 10/24/2019 | NEED INSTALL INSTRUCTION FOR INSPECTION OF WATER HEATER CONCENTRIC VENT TERMINATION ON ROOF. WATER HEATER VENT INSIDE WAS INSPECTED AT AN EARLIER DATE AND ROOF WAS NOT ACCESSIBLE AT THAT TIME. | LIDO | LIDO | | HV | P | 6379872 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 10/24/2019 | PARTIAL PENDING : ELECTRICAL SEAL TIGHT FOR KITCHEN EXHAUST FAN IS INSTALLED IN A MANNER THAT IS PREVENTING THE EXHAUST FAN FROM OPENING FOR SERVICE. INSTALL FIRE RATED GASKET ON CURB BELOW KITCHEN EXHAUST FAN. LABEL MAKE-UP AIR UNIT AND EXHAUST FAN FOR ADDRESS THEY SERVE. TEST AND BALANCE REPORT FOR SCOPE OF WORK ASSOCIATED WITH THIS PERMIT. | LIDO | LIDO | | H= | P | 6379870 |
ALPHALETE MECHANICAL LLC | H= | P | 10/11/2019 | CONTRACTOR THAT INSTALLED WATER HEATER DIRECT ( CONCENTRIC) VENT MUST ATTACH TO THE PERMIT AND CALL FOR INSPECTION / INSPECTED WATER HEATER VENT AND INTAKE INSIDE BUILDING INSTALL OK / NO ACCESS TO ROOF, STILL NEED TERMINATION INSPECTED , INSTALL MEDIUM PRESSURE LABELS ON GAS PIPE BEFORE REGULATORS. GAS PIPE INSTALLED PER PLAN, COOK-LINE AND WATER HEATER FINAL GAS CONNECTIONS AND REGULATORS OK. ANSUL VALVE IN PLACE. | LIDO | LIDO | | H= | P | 6366327 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 09/23/2019 | GREASE DUCT FIRE WRAP INSPECTION ONLY: ACCESS DOOR AND WRAP FOR ACCESS DOOR ARE NOT INSTALLED PER MANUFACTURE INSTALLATION INSTRUCTIONS. WENT OVER INSTALL WITH MECHANICAL CONTRACTOR. | LIDO | LIDO | | HD | P | 6344518 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 08/16/2019 | FIRST LAYER OF GREASE DUCT WRAP OK / OK TO INSTALL SECOND LAYER . GREASE DUCT IS ( CAPTIVE AIR ) PRE MANUFACTURED SINGLE WALL / ACCESS DOOR WILL NEED TO BE PER THE MANUFACTURE REQUIREMENTS. | LIDO | LIDO | | HD | P | 6304673 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 08/15/2019 | NEED TO REVIEW GREASE DUCT WRAP INSTALLATION INSTRUCTION .WILL ADD TO NOTES IN THE MORNING. | LIDO | LIDO | | HD | P | 6302553 |
ALPHALETE MECHANICAL LLC | HI | P | 08/13/2019 | (( BRASS VENT LIMITERS ON GAS REGULATORS ARE NOT RATED FOR OUTSIDE USE)) PLANS SHOW 1-1/4 GAS PIPE FOR COOK-LINE / 1" WAS INSTALLED / INSTALL PER PLAN OR REVISED AND APPROVED PLANS ARE REQUIRED. PLAN DOES NOT SHOW THE GAS OUTLET SIZE FOR THE 406 K BTU RANGE, NEED REVISED / APPROVED PLANS TO SHOW OUTLET SIZE. 10 lb TEST OK , GAS ON ROOF AND GAS PIPING TO WATER HEATER OK . | LIDO | LIDO | | HI | P | 6299192 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 08/06/2019 | NEED THE FOLLOWING CONTRACTORS ATTACHED TO PERMIT- REFRIGERATION , GAS AND CONTRACTOR INSTALLING WATER HEATER VENT.(( GREASE DUCT OK / OK FOR 1ST LAYER OF WRAP INSTALLED PER THE MANUFACTURES REQUIREMENTS.)) MAKE UP AIR DUCT AND TIE- IN TO PLENUM FOR HOOD OK / OK TO WRAP. TYPE -1 HOOD INSTALL OK / 18" METAL INSTALLED ALL DIRECTIONS OK. | LIDO | LIDO | | HD | P | 6290302 |
PEAK HEATING & AIR CONDITIONING, INC. | HSP | P | 08/06/2019 | HAD PHONE CONVERSATION WITH MECHANICAL CONTRACTOR IN REFERENCE TO SINGLE WALL GREASE DUCT, GREASE DUCT WILL NEED TO FIRE WARED PER THE MANUFACTURE REQUIREMENT'S. | LIDO | LIDO | | HSP | P | 6289540 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 08/02/2019 | PRE MANUFACTURED GREASE DUCT INSPECTION : GREASE DUCT DOES NOT PASS - SINGLE WALL GREASE DUCT INSTALLED / COMBUSTIBLES ARE LESS THEN 18" AWAY. REFER TO DWG# 2 ON THE PLANS ( BDA11) FOR GREASE DUCT MANUFACTURE REQUIREMENTS WHEN COMBUSTIBLES ARE WITHIN 18". | LIDO | LIDO | | HD | P | 6286515 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 08/02/2019 | ADDITIONAL NOTES FOR INSPECTION -((NEED TO RESEARCH GREASE DUCT CLEAN OUT / WILL ADD TO NOTES AFTER )) GREASE DUCT INSPECTION : GREASE DUCT DOES NOT PASS. 16 " ( CAPTIVE AIR )PRE MANUFACTURED SINGLE WALL GREASE DUCT INSTALLED WITHIN 18" OF COMBUSTIBLES, IN ADDITION PLANS SHOWS 18" GREASE DUCT TO BE INSTALLED / PLANS WILL NEED TO BE REVISED AND APPROVED. | LIDO | LIDO | | HD | P | 6287545 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 07/12/2019 | KITCHEN HOOD WALL OK. | LIDO | LIDO | | HD | P | 6262250 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 07/11/2019 | KITCHEN HOOD WALL IS SHEET ROCKED . NEED TO INSPECT OPEN WALL IN NEXT DOOR TENANT SPACE, SPACE IS LOCKED / NO ACCESS.(( NEED CONTRACTOR INSTALLING WATER HEATER VENT AND CONTRACTOR DOING THE REFRIGERATION ATTACHED TO PERMIT.) | LIDO | LIDO | | HD | P | 6260882 |
ALPHALETE MECHANICAL LLC | P= | C | 10/24/2019 | Corrections made. | SAMH | SAMH | | P= | C | 6378986 |
ALPHALETE MECHANICAL LLC | P= | P | 10/23/2019 | Lacking 5' clearance at Men's restroom sink. Rest OK. | SAMH | SAMH | | P= | P | 6377531 |
ALPHALETE MECHANICAL LLC | P= | L | 10/11/2019 | sent call ahead 12:50, door locked, no lock box code | TED | TED | | P= | L | 6366025 |
ALPHALETE MECHANICAL LLC | PTO | C | 08/08/2019 | Checked Dwv and Water behind hood wall. CI waste and Copper water lines ok. Note: Verify insulation at water above mop sink, Water heater, and VTR at final. | SAMH | SAMH | | PTO | C | 6294043 |
ALPHALETE MECHANICAL LLC | PTO | P | 05/01/2019 | need water piping insulation, rest ok, test and design good | TED | TED | | PTO | P | 6184060 |
ALPHALETE MECHANICAL LLC | XPS | T | 10/21/2019 | PAID (REC#1639468) PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: 10/21/19: Delta 2 revisions revised waste piping plan | SHANEN | SHANEN | | XPS | T | 6374709 |