ROCKY VIEW CONSTRUCTION LLC | B= | C | 01/31/2024 | Zoning final is now complete | DANE | DANE | | B= | C | 7982499 |
ROCKY VIEW CONSTRUCTION LLC | B= | T | 10/20/2023 | PAID (REC#2002368) Temp CO: Extension pending required finals ( Expires: 11/19/2023 12:00:00 AM) | MATTHEWM | MATTHEWM | | B= | T | 7895208 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 07/24/2023 | Temp CO: extension ( Expires: 8/23/2023 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 7805771 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 06/08/2023 | Temp CO: Pending zoning and building finals ( Expires: 7/8/2023 12:00:00 AM) | SYDNEYB | SYDNEYB | | B= | P | 7766438 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 04/17/2023 | Temp CO: extension ( Expires: 5/17/2023 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 7718141 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 03/08/2023 | Temp CO: Extension ( Expires: 4/7/2023 12:00:00 AM) | ASHLEYL | ASHLEYL | | B= | P | 7680979 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 02/03/2023 | Temp CO: Pending zoning and building finals ( Expires: 3/5/2023 12:00:00 AM) | RITA | RITA | | B= | P | 7653256 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 01/05/2023 | Temp CO: Pending zoning and building finals ( Expires: 2/4/2023 12:00:00 AM) | RITA | RITA | | B= | P | 7626908 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 12/07/2022 | Temp CO: TCO extension ( Expires: 1/6/2023 12:00:00 AM) | JANE | JANE | | B= | P | 7602913 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 11/10/2022 | Temp CO: Pending zoning and building finals ( Expires: 12/10/2022 12:00:00 AM) | RITA | RITA | | B= | P | 7578968 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 08/11/2022 | pending completion of zoning, building okay. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: 719-322-2028). | BOBF | BOBF | | B= | P | 7479312 |
ROCKY VIEW CONSTRUCTION LLC | B= | P | 08/02/2022 | still need stamped open hole and soils report / need ANSI compliant door hardware throughout / mirrors in both restrooms cannot be greater than 40" AFF to reflective surface / rear grab bars in both rest rooms to extend 12" to side wall from center of toilet, side grab bars in both rest rooms to start 12" from rear wall and extend to 54" from rear wall, need to complete zoning and fire finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: mgates@fountainfire.org), External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: 719-322-2028). | BOBF | BOBF | | B= | P | 7468056 |
ROCKY VIEW CONSTRUCTION LLC | BIN | P | 11/08/2021 | still need splice with truss details, IECC form showing all insulation requirements and soils report. Please note, no foundation insulation inspection has been performed / spray foam insulation installed on all exterior walls and roof, Need ES report for closed cell insulation | BOBF | BOBF | | BIN | P | 7169159 |
ROCKY VIEW CONSTRUCTION LLC | B= | R | 11/02/2021 | revised construction pages must be submitted to plan review for approval and spliced to plans, cannot upload revisions with an inspection request. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: mgates@fountainfire.org), External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: 719-322-2028), FOSTER ELECTRIC CORPORATION Electrical Final Inspection is not Completed yet, ASPEN VIEW MECHANICAL LLC Mechanical Final Inspection is not Completed yet, COOPER HEATING & COOLING, INC. Mechanical Final Inspection is not Completed yet, OSCAR PLUMBING LLC Mechanical Final Inspection is not Completed yet, SPARROW ENTERPRISES, INC. Mechanical Final Inspection is not Completed yet, OSCAR PLUMBING LLC Plumbing Final Inspection is not Completed yet, SPARROW ENTERPRISES, INC. Plumbing Final Inspection is not Completed yet. | BOBF | BOBF | | B= | R | 7161996 |
ROCKY VIEW CONSTRUCTION LLC | BFR | P | 09/16/2021 | Need to complete the following , splice sois report and truss details, splice plans showing deletion of front portico / need eng letter allowing full height non bearing walls to be non floating walls / need to splice com check to verify insulation requirements / need eng letter approving depth of light piers, pending completion of splices, other required inspections and receipt of eng letters rest of frame okay | BOBF | BOBF | | BFR | P | 7110085 |
ROCKY VIEW CONSTRUCTION LLC | BSP | R | 08/17/2021 | Call ahead completed at 11:11, no one on site at 11:42 -could not locate any details for exterior pole lights on plans, need to splice all requirements for pole lights as well as pier requirements to plans | BOBF | BOBF | | BSP | R | 7074842 |
ROCKY VIEW CONSTRUCTION LLC | B= | R | 08/12/2021 | uploads were for Mech , elec and plumb revisions that must submitted to plan review for approval and spliced into plans. Cannot be submitted to building inspector. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: mgates@fountainfire.org), External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: 719-322-2028), COOPER HEATING & COOLING, INC. Electrical Final Inspection is not Completed yet, COOPER HEATING & COOLING, INC. Mechanical Final Inspection is not Completed yet, FOSTER ELECTRIC CORP Electrical Final Inspection is not Completed yet, OSCAR PLUMBING LLC Mechanical Final Inspection is not Completed yet, OSCAR PLUMBING LLC Plumbing Final Inspection is not Completed yet, SPARROW ENTERPRISES, INC. Mechanical Final Inspection is not Completed yet, SPARROW ENTERPRISES, INC. Plumbing Final Inspection is not Completed yet. | BOBF | BOBF | | B= | R | 7069310 |
ROCKY VIEW CONSTRUCTION LLC | B= | R | 07/12/2021 | file uploaded is for mech splice, need to have plan spliced and approved by mech plan review. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: mgates@fountainfire.org), External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: 719-322-2028), COOPER HEATING & COOLING, INC. Electrical Final Inspection is not Completed yet, COOPER HEATING & COOLING, INC. Mechanical Final Inspection is not Completed yet, FOSTER ELECTRIC CORP Electrical Final Inspection is not Completed yet, OSCAR PLUMBING LLC Mechanical Final Inspection is not Completed yet, OSCAR PLUMBING LLC Plumbing Final Inspection is not Completed yet, SPARROW ENTERPRISES, INC. Mechanical Final Inspection is not Completed yet, SPARROW ENTERPRISES, INC. Plumbing Final Inspection is not Completed yet. | BOBF | BOBF | | B= | R | 7031507 |
ROCKY VIEW CONSTRUCTION LLC | BSP | P | 03/19/2021 | onsite meeting with contractor, reviewed splice and performed frame inspection based on splice, pending approval of splice - need to complete all other required inspections, laps on splices to intersect 3 trusses / need eng letter allowing non floating walls that continue to bottom of trusses / need splice deleting portico at front of building / still need soils report to complete footing | BOBF | BOBF | | BSP | P | 6904762 |
ROCKY VIEW CONSTRUCTION LLC | BFT | P | 03/16/2021 | letter for open hole footing and steel on file, still need to complete all structural splices | BOBF | BOBF | | BFT | P | 6899406 |
ROCKY VIEW CONSTRUCTION LLC | BFN | P | 03/10/2021 | Changed request from final to footing / eng letter for open hole, footing and steel for dock area on file, still need to complete all splices for all changes noted on previous inspections | BOBF | BOBF | | BFN | P | 6894271 |
ROCKY VIEW CONSTRUCTION LLC | BFR | R | 02/24/2021 | Provide all required foundation observation, revised foundation plan and soils paperwork, plan splice needed for as built conditions in building, addressing all changes for headers, beams and ledger substitutions,or omission of ledger for direct bearing. deleting firewall not constructed, full height walls at upstairs. | NATHAN | NATHAN | | BFR | R | 6879594 |
ROCKY VIEW CONSTRUCTION LLC | BFN | R | 12/07/2020 | Retaining wall retention pond outlet, reinforcement, clearance and forms per plan on kennel permit but a separate permit will be needed. | NATHAN | NATHAN | | BFN | R | 6798397 |
ROCKY VIEW CONSTRUCTION LLC | BFR | P | 12/03/2020 | inspection was for walls supporting mono trusses and monotrusses on both sides only pending completion of other required inspections - need trusses submitted and approved, plans show trusses pending but was scratched out, could not locate truss details on plans / ledger supporting mono trusses both sides to be secured with 5 lags 16" on center /laps at lateral bracing must intersect 3 trusses / please note plans show a fire wall that has not been framed in at this time and will need to go through roof and be independent of all structural elements when built | BOBF | BOBF | | BFR | P | 6795482 |
ROCKY VIEW CONSTRUCTION LLC | BFN | T | 11/18/2020 | PAID (REC#1733764) not ready, forms not started for rear loading dock | BOBF | BOBF | | BFN | T | 6780793 |
ROCKY VIEW CONSTRUCTION LLC | BFT | P | 11/17/2020 | changed request to footing from foundation, footing for loading dock okay, still need stamped open hole | BOBF | BOBF | | BFT | P | 6779011 |
ROCKY VIEW CONSTRUCTION LLC | BSP | P | 11/02/2020 | exterior shear okay | BOBF | BOBF | | BSP | P | 6761886 |
ROCKY VIEW CONSTRUCTION LLC | BSP | L | 10/29/2020 | not ready - shear inspection cancelled onsite per call with site superintendent / GC to reschedule when ready | BRIANB | BRIANB | | BSP | L | 6757737 |
ROCKY VIEW CONSTRUCTION LLC | BSP | R | 10/28/2020 | shear walls not per plan see sheet S4 for sheer wall locations and S5 for shear wall types shear not ready. | NATHAN | NATHAN | | BSP | R | 6757069 |
ROCKY VIEW CONSTRUCTION LLC | BFN | P | 04/24/2020 | main building walls okay, still need stamped open hole, still need dock area | BOBF | BOBF | | BFN | P | 6551639 |
ROCKY VIEW CONSTRUCTION LLC | BFT | P | 04/16/2020 | Field open hole and compaction on file, 2000 psf, main building footer only okay rear dock and interior thickened edge area remain for inspection. | NATHAN | NATHAN | | BFT | P | 6542567 |
ROCKY VIEW CONSTRUCTION LLC | BE | C | 04/15/2020 | | SAVANNAHT | SAVANNAHT | | BE | C | 6541632 |
FOSTER ELECTRIC CORPORATION | E= | C | 02/28/2022 | Complete per pics. / | LOGANP | LOGANP | | E= | C | 7283524 |
STILSON ELECTRIC SYSTEMS, INC. | E= | C | 02/24/2022 | FIRE ALARM INSPECTION: Monitored sprinkler system ok. / | LOGANP | LOGANP | | E= | C | 7281760 |
STILSON ELECTRIC SYSTEMS, INC. | ER | C | 02/24/2022 | FIRE ALARM INSPECTION: ER ok. / | LOGANP | LOGANP | | ER | C | 7281752 |
FOSTER ELECTRIC CORPORATION | E= | R | 02/22/2022 | Need to make corrections on SO cord ran through structure to exhaust fans --- Need to label service --- | LOGANP | LOGANP | | E= | R | 7279138 |
COOPER HEATING & COOLING, INC. | E= | C | 09/21/2021 | 50-amp mini-split ok. / | LOGANP | LOGANP | | E= | C | 7114381 |
COOPER HEATING & COOLING, INC. | ER | C | 09/21/2021 | | LOGANP | LOGANP | | ER | C | 7114372 |
FOSTER ELECTRIC CORPORATION | ER | R | 08/19/2021 | Can't run SO cord through structure to exhaust fans on east side of building --- | LOGANP | LOGANP | | ER | R | 7078609 |
COOPER HEATING & COOLING, INC. | ER | P | 08/19/2021 | Need to see MC connection to 4 fan coils and breaker labeled for final --- | LOGANP | LOGANP | | ER | P | 7078589 |
FOSTER ELECTRIC CORPORATION | EUG | P | 08/13/2021 | 3/4" pvc between 5 pole bases ok. / | LOGANP | LOGANP | | EUG | P | 7072242 |
COOPER HEATING & COOLING, INC. | ER | R | 07/22/2021 | need to strap mc cable on north side unit feed thats hanging below joist / need to use npt thread connector at transition from emt to flex at compressor / need flex strapped at compressor | TIMA | TIMA | | ER | R | 7045423 |
FOSTER ELECTRIC CORPORATION | ESL | P | 04/09/2021 | Ufer Ground Ok --- | LOGANP | LOGANP | | ESL | P | 6928498 |
FOSTER ELECTRIC CORPORATION | EP | P | 04/09/2021 | Need to splice plans to match service installation --- Panel A 250a 250 CU #4 CU GND --- Panel B 150a 1/0 CU #6 GND -- Panels C & D 60a --- | LOGANP | LOGANP | | EP | P | 6928491 |
FOSTER ELECTRIC CORPORATION | ES | P | 04/09/2021 | Commercial Service: 400-amp 4w 208v Ok to energize / Need to splice plans to show Parrallel 250 AL #4 GEC | LOGANP | LOGANP | | ES | P | 6928490 |
FOSTER ELECTRIC CORPORATION | ER | C | 04/07/2021 | panel walls ok / | MIGUEL | MIGUEL | | ER | C | 6924849 |
FOSTER ELECTRIC CORPORATION | ER | P | 02/04/2021 | lids and walls except where electrical panels will be installed, leave open until next inspection / exterior kennel areas to be surface mounted installation / | MIGUEL | MIGUEL | | ER | P | 6860053 |
FOSTER ELECTRIC CORPORATION | EUG | P | 12/02/2020 | service lateral ok | TIMA | TIMA | | EUG | P | 6794261 |
FOSTER ELECTRIC CORPORATION | EUG | P | 07/14/2020 | slab ok | TIMA | TIMA | | EUG | P | 6636489 |
DYNAMIC HEATING AND AIR LLC | H= | C | 08/01/2022 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES | BILLS | BILLS | | H= | C | 7465891 |
DYNAMIC HEATING AND AIR LLC | H= | P | 07/21/2022 | received photos of thermostats (SEE IMAGES) & Test and Balance Report (REJECTED/SEE IMAGES), TEST & BALANCE REPORT IS MISSING OUTSIDE FRESH AIR/EXHAUST FANS PER FRESH AIR TABLE (M1) AND OTHER EXHAUST FANS. | PAULO | PAULO | | H= | P | 7454370 |
DYNAMIC HEATING AND AIR LLC | HWP | C | 07/21/2022 | received photo of leak fixed (SEE IMAGES). | PAULO | PAULO | | HWP | C | 7454314 |
DYNAMIC HEATING AND AIR LLC | H= | P | 07/06/2022 | FINAL PENDING-- COMPLETION OF HWP INSPECTION, ALL THERMOSTATS (13) FOR ALL MS-1 UNITS (4) AND ZONES FOR IN FLOOR HEAT INSTALLED WITH CONTROLS ON THERMOSTATS TO BE NO MORE THAN 48" ( FROM FLOOR OR LOCK BOX INSTALLED) AND LABELED TO AREA SERVED, ALL SCOPE OF WORK (3 OPEN PERMITS) TO REFLECT 5 EXHAUST DUCTS, 2 DUCTS, 3 VENTS, 2 HRV's & 1 OTHER (HOT WATER PIPING), TEST AND BALANCE REPORT. | PAULO | PAULO | | H= | P | 7436119 |
DYNAMIC HEATING AND AIR LLC | HD | C | 07/06/2022 | Note / Dryer exhaust duct/bath fan exhaust duct x2 with terminations ok. | PAULO | PAULO | | HD | C | 7436058 |
DYNAMIC HEATING AND AIR LLC | HWP | P | 07/06/2022 | LEAK ON HOT WATER PIPING IN MECHANICAL ROOM/rest ok. | PAULO | PAULO | | HWP | P | 7436057 |
SPARROW ENTERPRISES, INC. | H= | C | 07/05/2022 | PLAN SPLICE ON FILE FOR CHANGE OF BOILER MANUFACTURE (E-PLAN PG.#93). GAS & BOILER CONTRACTOR COMPLETE. | PAULO | PAULO | | H= | C | 7434630 |
SPARROW ENTERPRISES, INC. | H= | P | 07/01/2022 | FINAL PENDING-- ENGINEER APPROVED SUBMITTAL FOR CHANGE OF BOILERS FROM (ALPINE COMMERCIAL TO INSTALLED NAVIEN/399K/Mod.#NFB-399C). | PAULO | PAULO | | H= | P | 7432609 |
SPARROW ENTERPRISES, INC. | HSP | P | 06/23/2022 | received Engineer letter for under slab insulation of (R-10) but is not needed and is not for this contractor (SEE IMAGES). FINAL PENDING-- ENGINEER APPROVED SUBMITTAL FOR CHANGE OF BOILERS FROM (ALPINE COMMERCIAL TO INSTALLED NAVIEN/399K/Mod.#NFB-399C), CONTRACTOR I.D.#24334 TO VOID PERMIT AS NO MECHANICAL WORK WAS DONE BY THIS CONTRACTOR. | PAULO | PAULO | | HSP | P | 7422109 |
SPARROW ENTERPRISES, INC. | H= | P | 06/16/2022 | received photos of medium pressure label (SEE IMAGES). FINAL PENDING-- ENGINEER APPROVED SUBMITTAL FOR CHANGE OF BOILERS FROM (ALPINE COMMERCIAL TO INSTALLED NAVIEN/399K/Mod.#NFB-399C), CONTRACTOR I.D.#24334 TO VOID PERMIT AS NO MECHANICAL WORK WAS DONE BY THIS CONTRACTOR. | PAULO | PAULO | | H= | P | 7413443 |
SPARROW ENTERPRISES, INC. | H= | P | 06/06/2022 | FINAL PENDING-- MEDIUM PRESSURE LABEL AT GAS METER (MAY ATTACH CLEAR PHOTO TO PERMIT AND RECALL FOR INSPECTION), ENGINEER APPROVED SUBMITTAL FOR CHANGE OF BOILERS FROM (ALPINE COMMERCIAL TO INSTALLED NAVIEN/399K/Mod.#NFB-399C). | PAULO | PAULO | | H= | P | 7400320 |
SPARROW ENTERPRISES, INC. | HWP | C | 05/19/2022 | INSPECTION NOTE TO ALERT STATE OF 2 BOILERS INSTALLED WITH 399K EACH. | PAULO | PAULO | | HWP | C | 7382444 |
SPARROW ENTERPRISES, INC. | H= | P | 05/19/2022 | CONTRACTOR TO ADDRESS THE FOLLOWING-- NEED INSTALLATION INSTRUCTIONS FOR BOILERS FOR PROPER INSPECTION, LABEL ALL EXPOSED GAS PIPING WITH MEDIUM PRESSURE LABELS EVERY 10' PER THE RBC PG.#76/RBC305.4.2, COMPLETE DRAINS FROM BACK FLOW PREVENTER X2 TO AN APPROVED LOCATION, SUPPORT VERTICAL GAS LINE TO WATER HEATER, ENGINEER APPROVED SUBMITTAL FOR CHANGE OF BOILERS FROM (ALPINE COMMERCIAL TO INSTALLED NAVIEN/399K/Mod.#NFB-399C). | PAULO | PAULO | | H= | P | 7382429 |
COOPER HEATING & COOLING, INC. | H= | C | 12/02/2021 | DRAINS COMPLETED PER LAST INSPECTOR NOTES. SEE IMAGES | JON | JON | | H= | C | 7195835 |
SPARROW ENTERPRISES, INC. | H= | P | 11/19/2021 | NOT READY, SEE PREVIOUS HI NOTES. | PAULO | PAULO | | H= | P | 7184533 |
SPARROW ENTERPRISES, INC. | HC | C | 11/18/2021 | OK TO SET 2# METER. | PAULO | PAULO | | HC | C | 7182533 |
SPARROW ENTERPRISES, INC. | HI | C | 11/18/2021 | NEEDED AT FINAL-- ALL MEDIUM PRESSURE STICKERS AT EXPOSED LOCATIONS EVERY 10', ALL REGULATORS INSTALLED TO APPLIANCES PER MANUFACTURES INSTRUCTIONS. Note / all gas piping installed per plans. | PAULO | PAULO | | HI | C | 7182530 |
COOPER HEATING & COOLING, INC. | H= | P | 11/18/2021 | FINAL PENDING-- COMPLETE ALL CONDENSATE DRAIN TERMINATIONS (NORTH WEST DRAIN HAS BEEN DAMAGED)(MAY ATTACH CLEAR PHOTOS TO PERMIT AND RECALL FOR INSPECTION). | PAULO | PAULO | | H= | P | 7182522 |
ASPEN VIEW MECHANICAL LLC | HWP | P | 10/07/2021 | INSPECTION FOR IN FLOOR HOT WATER PIPING AND INSULATION: HOT WATER PIPING AND INSULATION BOARD COVERED PRIOR TO INSPECTION AND NO PRESSURE TEST WAS DONE AS ALL HOT WATER PIPING IN MECHANICAL ROOM IS NOW COMPLETE (CONTRACTOR IS PROCEEDING AT OWN RISK) (PHOTOS OF HOT WATER PIPING AND INSULATION BOARD UNDER CONCRETE RECEIVED/SEE IMAGES). | PAULO | PAULO | | HWP | P | 7133782 |
ASPEN VIEW MECHANICAL LLC | HV | C | 10/07/2021 | Note / Water heater vent and air intake ok/Boiler vent and air intake x2 ok. | PAULO | PAULO | | HV | C | 7133752 |
ASPEN VIEW MECHANICAL LLC | HD | P | 10/01/2021 | CONTRACTOR TO ADDRESS THE FOLLOWING-- NEED LICENSED MECHANICAL CONTRACTOR TO CLAIM HOT WATER PIPING/WATER HEATER VENT AND DRYER EXHAUST, ENGINEER TO ADDRESS IN FLOOR HEAT INSULATION AS HOT WATER PIPING WAS COVERED (CONCRETE POURED) PRIOR TO INSPECTION, WATER HEATER VENT MATERIAL IS PROHIBITED PER MANUFACTURES INSTALLATIONS (MAY ATTACH CLEAR PHOTOS OF MATERIAL/SUPPORT AND ALL GLUE JOINTS TO PERMIT AND OR EMAIL PAULO@PPRBD.ORG WITH PERMIT # AND RECALL FOR INSPECTION), CORRECT SCOPE TO REFLECT 2 HRV's, 5 EXHAUST (EF-1 X2/EF-2 &3 (3), 1 DRYER AND 1 WATER HEATER VENT. | PAULO | PAULO | | HD | P | 7127157 |
COOPER HEATING & COOLING, INC. | HRP | C | 09/21/2021 | NEEDED AT FINAL-- ENGINEER APPROVED SUBMITTAL FOR MODEL CHANGE OF MS-1 TO INSTALLED MODEL. Note / all mini split heads and condenser installations and clearances ok. | PAULO | PAULO | | HRP | C | 7114534 |
ASPEN VIEW MECHANICAL LLC | HD | P | 09/17/2021 | CONTRACTOR TO ADDRESS THE FOLLOWING-- NEED LICENSED MECHANICAL CONTRACTOR TO CLAIM HOT WATER PIPING WITH INSPECTION/WATER HEATER VENT WITH INSPECTION AND DRYER EXHAUST WITH INSPECTION, ENGINEER TO ADDRESS IN FLOOR HEAT INSULATION AS HOT WATER PIPING WAS COVERED (CONCRETE POURED) PRIOR TO INSPECTION, VENT INSPECTION FOR WATER HEATER TO BE PRIOR TO CONCEALMENT(CONTRACTOR TO HAVE INSTALLATION MANUAL ON SITE FOR INSPECTION), MECHANICALLY FASTEN ALL BATH FAN EXHAUST DUCT JOINTS, NAIL PROTECTION FOR DRYER EXHAUST DUCT (MAY ATTACH CLEAR PHOTOS TO PERMIT AND RECALL FOR INSPECTION), CORRECT SCOPE TO REFLECT 2 HRV's, 5 EXHAUST (EF-1 X2/EF-2 &3 (3), 1 DRYER AND 1 WATER HEATER VENT. | PAULO | PAULO | | HD | P | 7111216 |
SPARROW ENTERPRISES, INC. | HV | P | 09/16/2021 | CONTRACTOR TO ADDRESS THE FOLLOWING-- ENGINEER TO ADDRESS GAS INSTALLATION NOT INSTALLED PER PLANS AND WILL NEED REVISED PLANS FOR GAS, 2# LETTER FROM GAS PURVEYOR, ENGINEER APPROVED SUBMITTAL FOR CHANGE OF BOILERS, STILL NEED LICENSED MECHANICAL CONTRACTOR TO CLAIM HOT WATER PIPING FOR BOILERS/WATER HEATER VENT WITH INSPECTIONS (HAD CONVERSATION WITH OWNER/DAN AND HE STATED THAT HE HAS PHOTOS OF INSULATION USED AND INSTALLED HOT WATER PIPING IN FLOOR AND WILL EMAIL PHOTOS WITH ENGINEER LETTER), NAIL PROTECTION FOR VENTS AND AIR INTAKES, SUPPORT VERTICAL VENTS AND AIR INTAKES IN ATTIC (TOP AND BOTTOM PLATES/MAY ATTACH CLEAR PHOTOS TO PERMIT AND RECALL FOR INSPECTION)/rest of vents and air intakes for boilers ok. | PAULO | PAULO | | HV | P | 7109577 |
ASPEN VIEW MECHANICAL LLC | HD | P | 09/15/2021 | --Still need water heater venting permitted by a mechanical contractor and inspected. --Need boiler vents inspected prior to drywall. --Need refrigeration contractor to have condensate piping inspected prior to drywall. --Contractor may still need to address permit scope and add commercial duct to permit. ABOVE CEILING DUCT - Will need dryer duct terminated to the outdoors. Will need condensate piping for HRV units completed. SUPPLY/RETURN/ EXHAUST ABOVE HARD LIDS OK TO COVER. EF-2, EF-3 & LOUVERS INSTALLED PER PLAN. | MARKB | MARKB | | HD | P | 7108026 |
ASPEN VIEW MECHANICAL LLC | HD | P | 09/10/2021 | CONTRACTOR TO ADDRESS THE FOLLOWING-- NEED LICENSED MECHANICAL CONTRACTOR TO CLAIM WATER HEATER VENT/DRYER EXHAUST DUCT/HOT WATER PIPING, CHANGE SCOPE OF WORK FROM 2 MAKE UP AIR UNITS TO 2 HRV UNITS AND 2 EXHAUST AND 2 BATH FANS (WHAT ARE THE 2 VENTS BEING CLAIMED FOR?), BATH FAN EXHAUST DUCTS TO BE TERMINATED TO THE EXTERIOR AND ALL JOINTS TO BE MECHANICALLY FASTENED WITH 3 SCREWS, NEED INSTALLATION MANUALS TO EF2 AND EF3 FOR INSPECTION. BY FINAL-- CONTRACTOR TO VERIFY WITH PHOTOS OF SCREENS TO AIR INTAKE HOODS AND DAMPERS ON EXHAUST HOODS, TEST AND BALANCE REPORT. Note / HRV x2 installation ok, all supply/return/intake and exhaust ducts ok. | PAULO | PAULO | | HD | P | 7103170 |
ASPEN VIEW MECHANICAL LLC | HSP | P | 09/09/2021 | BATH FAN EXHAUST DUCTS ARE INSTALLED AS 3" AND WILL ACCEPT AN RFI FOR SIZING. ENGINEER TO ADDRESS INSULATION FOR RADIANT IN FLOOR HEAT (CONCRETE WAS POURED PRIOR TO INSPECTION). ADDED NOTES ;9-10-21- 4" RIGID EXHAUST DUCT INSTALLED FOR BATH FANS. | PAULO | PAULO | | HSP | P | 7100941 |
ASPEN VIEW MECHANICAL LLC | HD | P | 09/03/2021 | CONTRACTOR TO ADDRESS THE FOLLOWING-- NEED LICENSED MECHANICAL CONTRACTOR TO CLAIM WATER HEATER VENT/DRYER EXHAUST DUCT/HOT WATER PIPING, EF-2 AND EF-3 AND 2- BATH (EF-1) FANS WITH INSPECTIONS, SUPPLY AND RETURN TO OFFICE NEEDS SUPPORT (CANNOT USE WIRING AS SUPPORT), RETURN TO BATHING ROOM NEEDS SUPPORT (CANNOT USE WIRING FOR SUPPORT) (MAY ATTACH CLEAR PHOTOS TO PERMIT AND RECALL FOR INSPECTION). BY FINAL-- CONTRACTOR TO VERIFY WITH PHOTOS OF SCREENS TO AIR INTAKE HOODS AND DAMPERS ON EXHAUST HOODS, TEST AND BALANCE REPORT. Note / HRV x2 installation ok, all supply/return/intake and exhaust ducts ok. | PAULO | PAULO | | HD | P | 7097007 |
COOPER HEATING & COOLING, INC. | HRP | P | 08/19/2021 | CONTRACTOR TO ADDRESS THE FOLLOWING-- LICENSED CONTRACTOR TO CLAIM VENT FOR WATER HEATER/FURNACE/FURNACE VENT/DUCTING/DRYER EXHAUST DUCT, BATH FAN EXHAUST DUCTS, EF-2 X3, HRV-1 X2 AND HOT WATER PIPE FOR BOILERS, WILL NEED A TEST FOR ALL HOT WATER PIPING, ENGINEER TO ADDRESS THE REMOVAL OF FORCED AIR HEATING AND REPLACING WITH RADIANT HEAT, WILL NEED ENGINEER APPROVED SUBMITTAL FOR MODEL CHANGE OF MS-1 TO INSTALLED MODEL, INSTALLATION MANUAL TO MS-1 UNITS AND CU-1 UNIT FOR INSPECTION, NEED HRP TEST FOR LINE SET FROM MS-1 IN CHECK IN ROOM. Mini Split System-- Inspection-- all pvc condensate drains ok. | PAULO | PAULO | | HRP | P | 7078627 |
COOPER HEATING & COOLING, INC. | HSP | P | 07/22/2021 | CONTRACTOR TO ADDRESS THE FOLLOWING-- LICENSED CONTRACTOR TO CLAIM VENT FOR WATER HEATER/FURNACE/FURNACE VENT/DUCTING/DRYER EXHAUST DUCT, BATH FAN EXHAUST DUCTS, EF-2 X3, APPROVED PLANS ADDRESSING DUCT LESS MINI SPLIT SYSTEM, WILL NEED TO VERIFY APPROVED MECHANICAL SPLICE FOR ALL NOTES LISTED. Mini Split System-- PROCEED AT OWN RISK....- NEED TO COMPLETE CONDENSATE DRAIN FOR ENTRY HEAD, NAIL PROTECTION FOR LINE SETS TO ENTRY HEAD AND STORAGE ROOM (UPPER LEVEL), INSTALLATION MANUALS TO ALL HEADS AND CONDENSERS FOR INSPECTION. Inspection-- all pvc condensate drains/line sets and heads installed. | PAULO | PAULO | | HSP | P | 7045948 |
COOPER HEATING & COOLING, INC. | HSP | P | 06/17/2021 | (NO INSPECTION TODAY!) CHANGED HRR INSPECTION TO AN HSP AND WILL NEED ALL FUTURE INSPECTIONS CALLED WITH COMMERCIAL INSPECTION CODES, CALLED MIKE FROM COOPER HEATING AND DISCUSSED THE ABSENCE OF UPDATED APPROVED PLANS (SPLICE) FOR MINI SPLITS INSTALLED AND EQUIPMENT SCHEDULE FOR MECHANICAL AND ELECTRICAL, CONTRACTOR TO REVIEW ALL PREVIOUS NOTES AND ADDRESS, CALLED ORVI FROM ROCKY VIEW CONSTRUCTION ABOUT NO APPROVED SPLICES TO CHANGES. | PAULO | PAULO | | HSP | P | 7005920 |
SPARROW ENTERPRISES, INC. | HI | P | 05/03/2021 | NEED THE FOLLOWING - REVISED PLAN BEFORE METER RELEASE TO MATCH INSTALLED - MEDIUM PRESSURE LABELS - REGULATORS AND VENTS - NEED MECHANICAL CONTRACTOR ATTACHED FOR ALL HVAC WORK - CORRECT PERMIT WORK SCOPE ((((( CONTRACTOR PROCEEDING AT OWN RISK)))) NOTES: PRESSURE TEST OK | JERRYF | JERRYF | | HI | P | 6954757 |
OSCAR PLUMBING LLC | HI | R | 03/02/2021 | NOTE ADDED 3/3/21: SPOKE WITH SENIOR MECHANICAL INSPECTOR JON B. HE CALLED LICENSEE FOR BUILDING CONTRACTOR AND LEFT MESSAGE WITH HIS PHONE NUMBER - NEED FULL MECHANICAL SCOPE COVERED UNDER PERMIT ATTACHMENTS TO INCLUDE, MECHANICAL EQUIPMENT, DUCTS, VENTS AND EXHAUST. INFLOOR HEAT TUBING WAS INSTALLED AND COVERED WITH CONCRETE WITHOUT PROPER INSPECTIONS. THERE IS MECHANICAL EQUIPMENT INSTALLED IN BUILDING NOT SHOWN ON PLANS. NEED ENGINEER TO ADDRESS DAMPER COMMENTS ON PLAN. NEED MEDIUM PRESSURE LETTER FROM GAS PROVIDER. NEED PROPER PRESSURE TEST ON GAS PIPING AND GAS PIPING NEEDS TO MATCH APPROVED PLANS. WILL NEED APPROVED PLANS TO MATCH WHAT IS BEING INSTALLED, ALL CONTRACTORS ATTACHED TO PERMIT AND ALL INSPECTIONS CALLED IN A TIMELY MANOR. Further research on approved plans - Will enter notes at later time. | MARKB | MARKB | | HI | R | 6885230 |
SPARROW ENTERPRISES, INC. | P= | C | 06/22/2022 | See images. | DANR | DANR | | P= | C | 7420209 |
SPARROW ENTERPRISES, INC. | P= | P | 06/22/2022 | Pending vacuum breakers installed in dog kennel room for hot and cold outlets / engineers letter is uploaded to images. | DANR | DANR | | P= | P | 7420046 |
SPARROW ENTERPRISES, INC. | P= | P | 06/21/2022 | pending approval of engineers letter and vacuum breakers installed in dog kennel room for hot and cold outlets | JOEL | JOEL | | P= | P | 7419003 |
SPARROW ENTERPRISES, INC. | P= | P | 06/16/2022 | Break sink needs piped to code with trap and vent - cannot indirect waste break sink waters need piped to code / need pipe protection under sink / need side wall vent termination installed per code / need all engineers letters / | DANR | DANR | | P= | P | 7414379 |
SPARROW ENTERPRISES, INC. | P= | P | 06/03/2022 | Need to complete kitchen fixtures, side wall vent termination per code, grooming area fixtures, hose bibs inside, need engineers letters / rest ok. | DANR | DANR | | P= | P | 7399588 |
SPARROW ENTERPRISES, INC. | P= | P | 05/02/2022 | Need splice for moving water heater to loft / need engineers approval letter for installing free stand utility sink / What is going on at dishwasher drain? / break sink not installed / sink by dishwasher not installed per code and not on drawings / / need hammer arrestor dishwasher and separate isolation valve / re-inspect all kitchen break area / need tempering at lavs / missing trap guards at floor drains / missing AAV's and engineers letter for AAV's / hot and cold flipped on utility sink / water heater T&P drain m.i.p. rated for cold water only and need air gap at pan / where does water heater pan drain terminate? / leak by dishwasher supply lines / both boiler back flows need vent drain rain to floor drain with air gap / leak water entry / need inspect hose bibs / need PTO completed / side vent termination needs to per code / grooming area not completed / partial list may be more items. | DANR | DANR | | P= | P | 7359986 |
SPARROW ENTERPRISES, INC. | P= | R | 03/11/2022 | no hot water / contractor need to walk job site before next inspection / all fixtures not installed / need to complete PTO / re-inspect all note: Training with Dan | ANTHONYT | ANTHONYT | | P= | R | 7299256 |
SPARROW ENTERPRISES, INC. | PTO | P | 05/03/2021 | Need plans splice for moving water heater to loft area ( will need drain from pan ) / need engineers letter for AAV's at trench drains, break sink, washer vent side wall termination, and for changing from mop sink to utility sink / if using single drinking fountain with bottle filler will need Alternate Means and Methods with plans review / need hose bibs/ fix scope of work and remove 15 water softners and add hose bibs / toilet flanges and floor drains ok / Note: at final check water heater, water entry, backflow protection boiler make up water, side wall vent termination bird and rodent protection / discussed accessible elements. | DANR | DANR | | PTO | P | 6954939 |
SPARROW ENTERPRISES, INC. | PTO | L | 04/30/2021 | Cancelled by contractor. | DANR | DANR | | PTO | L | 6953384 |
OSCAR PLUMBING LLC | PTO | P | 04/23/2021 | Need plans splice for moving water heater to loft area ( will need drain from pan ) / need engineers letter for AAV's at trench drains, break sink, washer vent side wall termination, and for changing from mop sink to utility sink / if using single drinking fountain with bottle filler will need Alternate Means and Methods with plans review / need toilet flanges, hose bibs, and all floor drains installed / need insulation all hot water lines / test ok. Note: at final check water heater, water entry, backflow protection boiler make up water, side wall vent termination bird and rodent protection / | DANR | DANR | | PTO | P | 6945489 |
D & D PLUMBING | PB | C | 07/02/2020 | VERIFY PROPER HDPE TRANSITIONS @ APPLICABLE AREAS | JOHNS | JOHNS | | PB | C | 6625234 |
D & D PLUMBING | PB | P | 06/26/2020 | Water piping does not match plan sizing / re-inspect all on water. | DANR | DANR | | PB | P | 6619719 |
D & D PLUMBING | PB | P | 06/22/2020 | STILL need to see incoming water and looped underground waters, rest ok | JOHNS | JOHNS | | PB | P | 6612135 |
D & D PLUMBING | PB | P | 06/17/2020 | NEED contractor on site w/ plans, inspector cant get plans to download
several areas of flat 4" and 3", cant have horizontal dry vents through out (there is enough room for them not to be horizontal dry vents), need to use 3" p-traps @ areas where 90's were used to make traps, contractor to verify all stand pipes do not exceede 24" tall, need water stubbed in, rest ok pending inspector to review plans | JOHNS | JOHNS | | PB | P | 6608087 |
ROCKY VIEW CONSTRUCTION LLC | XBS | T | 06/17/2022 | PAID (REC#1875741) PLAN SPLICE FEE: $50 by: CGIECK for Construction: Truss and shop drawings ok | CGIECK | CGIECK | | XBS | T | 7415070 |
COOPER HEATING & COOLING, INC. | XMS | P | 05/03/2022 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Mechanical: see clouded areas | TCRIPPEN | TCRIPPEN | | XMS | P | 7360924 |
COOPER HEATING & COOLING, INC. | XMS | T | 11/16/2021 | PAID (REC#1823577): PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: revise gas and mini splits | TCRIPPEN | TCRIPPEN | | XMS | T | 7178892 |
ROCKY VIEW CONSTRUCTION LLC | XBS | P | 11/03/2021 | PLAN SPLICE: (No Fee) by: GITA for Construction/ remove covered entryway | GITA | GITA | | XBS | P | 7163927 |
OSCAR PLUMBING LLC | XMS | T | 11/03/2021 | PAID (REC#1820293) PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: Approved new splice revised gas line. | TCRIPPEN | TCRIPPEN | | XMS | T | 7163852 |
FOSTER ELECTRIC CORPORATION | XES | T | 08/12/2021 | PAID (REC#1798290) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Added Panel C and Panel D to scope. | BERTHA | BERTHA | | XES | T | 7069455 |
COOPER HEATING & COOLING, INC. | XMS | T | 07/29/2021 | PAID (REC#1794361): PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: new splice removed floor sinks | TCRIPPEN | TCRIPPEN | | XMS | T | 7053901 |