GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 08/04/2022 | All other required Final inspections are complete. (This is a computer generated result) | BRIANB | BRIANB | | B= | C | 7470868 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 07/26/2022 | courtesy inspection / met with GE Johnson superintendents and Greg with PPRBD | BRIANB | BRIANB | | BSP | P | 7460665 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 07/14/2022 | pending other final inspections. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, U.S.ENGINEERING CONSTRUCTION, LLC Mechanical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 7446449 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 07/08/2022 | pending re-inspection for gyp penetrations in fire barrier at stair pressurization rooms on 4th floor / observed other corrections / pending other final inspections -- Schedule a new Building Final when above items are complete. | BRIANB | BRIANB | | B= | P | 7439790 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | C | 07/08/2022 | sign off | BRIANB | BRIANB | | BFR | C | 7439787 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 06/09/2022 | pending re-inspection of 1hr smoke barrier doors at 5th and 6th floor and pending other final inspections -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, U.S.ENGINEERING CONSTRUCTION, LLC Mechanical Final Inspection is not Completed yet, ELEVATOR: OTIS ELEVATOR CO - TAX DEPT Mechanical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 7405600 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | R | 06/07/2022 | PARTIAL / 5TH - 6TH FLR / observed final inspection for 5th and 6th floor - still need to complete final inspection for remainder of addition at roof and stair towers / need to complete other final inspections. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection FHZ= by FIREDEPT is not Completed yet, External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, U.S.ENGINEERING CONSTRUCTION, LLC Mechanical Final Inspection is not Completed yet, ELEVATOR: OTIS ELEVATOR CO - TAX DEPT Mechanical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | R | 7402622 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | R | 05/25/2022 | PARTIAL / 6th floor - on call sleeping units area (6565 - 6568) / observed final inspection elements for 6th floor areas noted / still need to complete final inspection for remainder of addition / discussed accessible elements and final inspection processes with superintendent / need to complete other final inspections. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection FHZ= by FIREDEPT is not Completed yet, External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, U.S.ENGINEERING CONSTRUCTION, LLC Mechanical Final Inspection is not Completed yet, ELEVATOR: OTIS ELEVATOR CO - TAX DEPT Mechanical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Plumbing Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | R | 7388789 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | R | 05/24/2022 | PARTIAL / 6th floor - north half from 1hr smoke barrier / observed final inspection elements for 6th floor north of 1hr smoke barrier / still need to complete final inspection for remainder of addition / discussed accessible elements and final inspection processes with superintendent / need to complete other final inspections. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection FHZ= by FIREDEPT is not Completed yet, External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, U.S.ENGINEERING CONSTRUCTION, LLC Mechanical Final Inspection is not Completed yet, ELEVATOR: OTIS ELEVATOR CO - TAX DEPT Mechanical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Plumbing Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | R | 7387145 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/17/2022 | ABOVE GRID - GYP PENETRATIONS / 5TH FLR / need to re-inspect gyp penetration in fire barrier in LVR 5586 / observed other gyp penetration corrections 5th floor | BRIANB | BRIANB | | BSP | P | 7378860 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/04/2022 | ABOVE GRID - GYP PENETRATIONS / 5TH FLR / still missing multiple penetrations in 1hr fire smoke barrier / penetrations in fire barrier in rooms LVR 5586 - MEDS 5571 | JEREMYA | JEREMYA | | BSP | P | 7363333 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 04/26/2022 | ABOVE GRID - GYP PENETRATIONS / 5TH FLR / multiple penetrations in 1hr fire smoke barrier / penetrations in fire barrier in rooms LVR 5586 - MEDS 5571 --------------
WALL FRAME / 5TH FLR - STR 5566 / observed wall framing at storage room noted - see splice dated 25APR22 / pending other rough inspections
| BRIANB | BRIANB | | BSP | P | 7352871 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 04/26/2022 | summary letter for construction observations and materials - structural steel - spray applied fire proofing - structural concrete on file | BRIANB | BRIANB | | BSP | P | 7352028 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 04/21/2022 | ABOVE GRID / GYP PENETRATIONS - 5TH FLR / need re-inspection for multiple conduit penetrations in fire rated assembles / observed above grid gyp penetrations areas north of smoke barrier on 5th floor | BRIANB | BRIANB | | BSP | P | 7347982 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 04/14/2022 | FRAME - 1" GYP INSPECTION / 5TH - 6TH - 7TH FLR - O2 ROOMS / observed wall framing and 1" American gyp panels for O2 rooms / V489 - V455 assemblies / pending other rough inspections --------------
FRAME - SOFFITS - WALLS / 5TH - 6TH - 7TH STR TOWER #7 VESTIBULE / observed wall and soffit framing at areas noted / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7339157 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 03/17/2022 | 5th floor -- Tub drain protection at above hard lid OK pending other roughs
6th floor -- Above lid through out whole floor OK pending other roughs | DAKOTAB | DAKOTAB | | BFR | P | 7305890 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 02/28/2022 | PARTIAL / HARD LID FRAME - ABOVE GRID GYP PENETRATIONS / ELEVATORS 10-11 5TH &6TH FLR / ELEVATORS 12-13 ROOF VESTIBULE / observed hard lid framing and above grid penetrations at areas noted / pending other rough inspections ----
PARTIAL / HARD LID FRAME - ABOVE GRID GYP PENETRATIONS AT SMOKE PARTITIONS / 5TH FLR / observed hard lid framing and above grid gyp penetrations at areas noted only / pending other rough inspections-----
GYP PENETRATIONS - ABOVE GRID / 6TH FLR NURSES STATION / observed above grid gyp penetrations at 1hr fire barrier in nurses station 6th floor / reviewed accessible elements and final inspection processes with superintendent --- | BRIANB | BRIANB | | BFR | P | 7284778 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 02/09/2022 | GYP INSPECTION / 5TH - 6TH FLR - ELEVATOR 10&11 / V455 - observed (2) layers 5/8" gyp at in-fill for elevators 10 & 11 ------
1" GYP & MTL FRAMING - V455 / 6TH FLR & ROOF VESTIBULE - ELEVATOR 12-13 / observed mtl framing and 1" American gyp panels at in-fill for elevator 12 & 13 ---------
WALL FRAME - ROOF VESTIBULE - STAIR TOWER 8 / observed non-rated light gauge wall framing at areas noted / pending other rough inspections
| BRIANB | BRIANB | | BFR | P | 7264631 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/27/2022 | FRAME / 5TH FLR - 5512 - 5568 / observed wall framing and in wall penetrations at 5th floor rooms 5512 - 5568 / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7252285 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/26/2022 | GYP INSPECTION / 5TH FLR / AREA 8 - RMS 5576 - 5570 LVR 5586 - 5587 - 5588 / observed gyp - gyp fastening for areas noted on 5th floor | BRIANB | BRIANB | | BFR | P | 7250848 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 01/25/2022 | observation letter for SFRM on file | BRIANB | BRIANB | | BSP | P | 7248851 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/21/2022 | Screw inspection on level 5, area 7 in all rooms, to exclude corridors, OK | JEREMYA | JEREMYA | | BFR | P | 7246161 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/18/2022 | 5TH FLOOR -- AREA 8 -- Light gauge wall frame at rooms 5575 through 5569A OK pending other roughs | DAKOTAB | DAKOTAB | | BFR | P | 7241573 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/14/2022 | 5TH FLOOR -- AREA 1 - Light gauge frame at rooms 5534 through 5595 OK pending other roughs -- AREA 7 - Light guage frame at rooms 5579 through 5594 OK pending other roughs | DAKOTAB | DAKOTAB | | BFR | P | 7240408 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/12/2022 | Gypsum attachment at face layer of shaft 2 on 5th floor OK -- Gypsum attachment at smoke barrier in rooms 5550 and 5552 OK | DAKOTAB | DAKOTAB | | BFR | P | 7237515 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 01/12/2022 | Gypsum attachment at face layer of shaft 2 on 5th floor OK -- Gypsum attachment at smoke barrier in rooms 5550 and 5552 OK | DAKOTAB | DAKOTAB | | BSP | P | 7237516 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/05/2022 | FRAME - IN-WALL PENETRATIONS / 5TH FLR / CC60 - 44 / observed wall framing and in wall penetrations at rooms noted / pending other rough inspections / discussed details for fire rated assemblies with site reps -------
GYP INSPECTION / 5TH FLR / SHAFT 2 / observed face layer 5/8" gyp all sides for shaft 2 -----
GYP INSPECTION / 5TH FLR / SHAFT 1 / observed base layer 5/8" gyp all side sides for shaft 1 ------
| BRIANB | BRIANB | | BFR | P | 7229353 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/03/2022 | GYP INSPECTION / 5TH FLR / SHAFT 2 - ELEC 5593 / observed base layer 5/8" gyp at 2hr fire barrier at shaft 2 and exterior side of electrical room 5593 --
GYP INSPECTION / 5TH FLR / CC 22 - 24 & ADJ CORRIDOR - 1HR SMOKE BARRIER / observed 5/8" gyp for 1hr smoke barrier at rooms - corridor noted -- | BRIANB | BRIANB | | BFR | P | 7226718 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 12/22/2021 | Interior light gauge frame at 5th floor area 3 and 6, room 5514 through 5532 OK pending other roughs -- Infill at elevator 10 and 11 steel frame and 1" gypsum panel OK per UL V455 | DAKOTAB | DAKOTAB | | BFR | P | 7219117 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 12/16/2021 | GYP INSPECTION / 6TH FLR / ON CALL AREA / observed 5/8" American gyp at on call area 6th floor | BRIANB | BRIANB | | BFR | P | 7211327 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 12/14/2021 | 1" GYP & MTL FRAME / 2HR FIRE BARRIER - V455 / IN-FILL 5TH - 6TH FLR ELEV 10 - 11 / 5TH FLR MULTI PURPOSE 5568 / observed 1" gyp and mtl frame at 2hr fire barrier at areas noted / discussed details for fire rated assemblies at elevators in approved design and applied to onsite conditions with site reps / reviewed inspection history with site superintendent / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7208705 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 12/13/2021 | Courtesy inspection requested / reviewed ANSI 608.2.3 Alternate Roll-in-type shower compartments with site superintendent and applied to onsite conditions | BRIANB | BRIANB | | BSP | P | 7206550 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 12/09/2021 | WALL - SOFFIT FRAME / 6TH FLR - STAIR 8 LOBBY/ CORRIDORS / observed wall and soffit framing at areas noted / pending other rough inspections and above lid gyp penetration inspection /
GYP INSPECTION / 6TH FLR / SHAFT 1 - REMAINING SIDES / MED 6571 - CLEAN 6572 - CORRIDOR SIDE OF 1HR SMOKE BARRIER AND MULTI PURPOSE 6501 / observed gyp at areas noted / | BRIANB | BRIANB | | BFR | P | 7203829 |
U.S. ENGINEERING CONSTRUCTION, LLC | BSP | T | 12/08/2021 | PAID (REC#1828303): ADDITIONAL PLAN REVIEW TIME: $50 From: DALEH clouds | DALEH | DALEH | | BSP | T | 7201045 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | C | 12/01/2021 | remaining west elevation | BRIANB | BRIANB | | BLA | C | 7193985 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/30/2021 | FRAME / 6TH FLR / MED 6571 - SHAFT 1 - NURSE STATION 6569 - IMC 02-12 - MULTI PURPOSE 6501 - EVS 6593 - ON CALL AREA 6565 - 6568 / observed in wall penetrations and wall framing at areas at 6th floor - discussed accessible elements with site reps / pending other rough inspections /
SHAFT WALL MTL FRAME & 1" GYP - ELEV 10 / observed mtl framing and 1" American gyp panels behind elevator 10 / pending other rough inspections /
GYP INSPECTION / 6TH FLR / OFFICE 6580 - STAFF TOILET 6578 - STAFF LOUNGE 6576 - SOILED 6573 - CORRIDOR 6513 - CLEAN 6572 - CORRIDOR ALONG GRID LINE XB & AC FROM 5 T0 10 / observed gyp and gyp fastening at areas noted at 6th floor / discussed details for fire rated assemblies with site reps and needing fire stop details for penetrations in fire rated assemblies | BRIANB | BRIANB | | BFR | P | 7192337 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/23/2021 | GYP INSPECTION / 6TH FLR / 1HR FIRE - SMOKE BARRIER / STORAGE 6588 - NURSE 6591 - 89 - CLEAN SUPPLY 6587 - OFFICE 6585 / INSIDE SOILED STORAGE 6579 & EQ ALCOVE 6581 / observed gyp and fastening for fire rated assemblies at rooms noted on 6th floor | BRIANB | BRIANB | | BFR | P | 7187442 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/19/2021 | FRAME INSPECTION / 6TH FLR AREAS 7 & 8 / ROOMS 6591 - 6572 / observed mtl framing and in wall penetrations at areas noted / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7184261 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/17/2021 | FRAME / 6TH FLR / IMC 22 - IMC 14 / observed mtl framing and in wall penetrations at rooms noted / pending other rough inspections / discussed accessible elements with site reps /
GYP INSPECTION / 5TH FLR / SHAFT 1 / observed 2nd layer 5/8" gyp at top of wall (4) sides and entire west elevation (V455) / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7180957 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | R | 11/16/2021 | inspection cancelled onsite by superintendent | BRIANB | BRIANB | | BFR | R | 7178861 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/15/2021 | 6TH FLOOR -- 1st layer of 5/8" gypsum at SHAFT 1 including electrical room OK -- Gypsum attachment at smoke barrier at rooms 6552 and 6554 OK -- 5TH FLOOR -- SHAFT 2 - Gypsum attachment at whole wall on west elevation OK -- Gypsum attachment at above lid around entire shaft OK | DAKOTAB | DAKOTAB | | BFR | P | 7177626 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/10/2021 | PARTIAL / EXTERIOR WALL FRAME - WEST ELEVATION / EXTERIOR WALLS - GRID LINE XA - 10 TO 16 / observed exterior wall framing at areas noted - pending other rough inspection /
GYP INSPECTION / 5TH FLR - ELEC RM 5593 - 2HR FIRE BARRER - V489 / observed (2) layers American 5/8" gyp inside electrical rm 5593
GYP INSPECTION / 6TH FLR - ELEC 6593 - 2HR FIRE BARRIER - V489 / observed base layer American 5/8" gyp exterior side of electrical room 6593
GYP INSPECTION / 6TH FLR - SHAFT 2 - 2HR FIRE BARRIER - V455 / observed base layer American 5/8" gyp | BRIANB | BRIANB | | BFR | P | 7172339 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/08/2021 | 1" GYP AND MTL FRAME / SHAFT 1 - 5TH FLR / 2HR FIRE BARRIER - V455 / observed mtl framing and 1" American gyp panels at (4) sides of shaft 1 / reviewed construction progress and permit history with site superintendent | BRIANB | BRIANB | | BFR | P | 7169054 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/04/2021 | PARTIAL FRAME -- 5th and 6th floor -- 5th FLOOR -- Light gauge frame at above lid of 1hr fire barrier in CLEAN 5572 OK per V489 -- Light gauge frame at above lid for MEDS 5571 OK -- 6th FLOOR -- Interior light gauge frame at IMC rooms 6534 through 6562 and EVS 6592 OK pending other roughs -- Steel stud framing and 1" gypsum panel at SHAFT 2 OK per UL V455 -- Light guage frame at ELECTRICAL 6593 OK | DAKOTAB | DAKOTAB | | BFR | P | 7166442 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 11/03/2021 | Exterior Thermal Insulation Inspection report on file | BRIANB | BRIANB | | BSP | P | 7163393 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/02/2021 | PARTIAL / TOP OF WALL - 5TH FLR / CC 14 (5514-5516) / observed top of wall framing at corridor common wall at areas noted / pending other rough inspection
1" GYP AND MTL FRAME / SHAFT 2 - 5TH FLR / observed 1" gyp panels and mtl frame for 2hr fire barrier at shaft 2 / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7162507 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/28/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / CRITICAL CARE 5534 - 5542 - STAFF 5596 - OFFICE 5595 - MEDS 5594 / observed top of wall framing at areas noted / WALL FRAME ELEC 5593 - observed wall framing for 2hr fire barrier V489 assembly in electrical 5593 / pending other rough inspections
FRAME - IN-WALL PENETRATIONS / 6TH FLR / IMC 6534 - 6542 - STAFF 6595 - IMC 6532 - 6524 / observed wall framing and in-wall penetrations at rooms noted on 6th floor / NOTE - missing revised enlarged plan - typical accessible room sheet A422 (per ASI-039) in permitted design in IMC 32 - discussed accessible elements with site rep / NOTE - observation letter for structural steel & SFRM to follow / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7158888 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/26/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / CORRIDOR COMMON WALLS (SMOKE PARTITIONS) CRITICAL CARE 5534 - 5542 & NON RATED COMMON WALL CC 5512 - 5502 -observed top of wall framing at areas noted /
5TH FLR / TLT 5567 1HR SMOKE BARRIER V489 - GYP AND WALL FRAME - observed wall framing and one side of 5/8"x gyp inside tlt 5567 /
5TH FLR / 1" GYP AND MTL FRAME - V455 2HR FIRE BARRIER FOR SHAFT IN ELEC 5593 / observed 1" American gyp panels and mtl framing inside elec room 5593 for 2hr shaft / discussed smoke barrier - fire barrier continuity with site reps / pending all other rough inspections
COURTESY FRAME WALK 6TH FLR w/ site reps - discussed fire rated assemblies and needing firestop details for all penetrations in fire rated assemblies | BRIANB | BRIANB | | BFR | P | 7155244 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/20/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / CORRIDOR COMMON WALL CC 5502 - 5512 / observed top of smoke partition wall framing at areas noted / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7148970 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/18/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / TLT 5575 / observed top of wall framing at room noted / pending other rough inspections
GYP INSPECTION / ONE SIDE - LVR 5586 / 1 HR FIREBARRER - V489 / observed 5/8" x gyp at inside of LVR room only | BRIANB | BRIANB | | BFR | P | 7145476 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/13/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / STORAGE 5588 - CLEAN 5587 - OFFICE 5585 - TLT 5584 - OFFICE 5581 - 5580 - STORAGE 5578 - LOCKER 5576 - SOILS 5573 - OFFICE 5574 / SMOKE BARRIER V489 & V496 - FIRE BARRIER V489 / observed top of wall framing at walls - areas noted / pending other rough inspections / reviewed details for fire rated assemblies - head wall and penetrations | BRIANB | BRIANB | | BFR | P | 7140733 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 10/12/2021 | SOUTH ELEVATION / observed lath along south elevation | BRIANB | BRIANB | | BLA | P | 7139300 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/11/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / CRITICAL CARE 44 - 60 at COMMON WALLS / SMOKE BARRIER V496 / observed top of wall framing at common walls - areas noted / pending other rough inspections
WALL FRAME / 5TH FLR - EVS 5592 / 1HR FIREBARRIER - V489 / observed wall framing at EVS 5592 only / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7137412 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 10/06/2021 | PARTIAL / observed lath along west elevation from north corner to critical care 16 / inspection added onsite per request from GC | BRIANB | BRIANB | | BLA | P | 7132498 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/05/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / CORRIDOR COMMON WALLS - CRITICAL CARE 44 - 56 & MEDS 5571 - EQUIP. 5588 / observed top of wall framing at corridor common walls -1hr fire barrier - 1hr smoke barriers - smoke partitions at areas noted / V489 & V496 / discussed smoke barrier continuity with site reps / WALL FRAME - LVR 5586 / observed wall frame at LVR 5586 (1hr fire barriers) / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7130872 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/30/2021 | PARTIAL / WALL FRAME - PENETRATIONS - ONE SIDE GYP INSIDE MECH 7101 - VESTIBULE 7100 / FIRE BARRIER V489 / observed penetration in floor in wall and 5/8" gyp one side in mech closet / discussed details for 1hr fire barrer V489 with site reps / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7126210 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/29/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / CRITICAL CARE 18 - 32 at COMMON WALLS / SMOKE BARRIER V496 / observed top of wall framing at common walls - areas noted / pending other rough inspections / reviewed construction progress and inspection scheduling with site super /
CURTAIN WALL - FLR INTERSECTION / FIRE-RESISTANT JOINT SYS - HILTI Design No. HI/BP - 120-05 - perimeter firebarrier sys on file | BRIANB | BRIANB | | BFR | P | 7124549 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 09/24/2021 | PARTIAL / Observed lath installed at window well to existing stucco | JUSTINL | JUSTINL | | BLA | P | 7119428 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/22/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 5TH FLR / SMOKE PARTITIONS CRITICAL CARE 20 - 32 at CORRIDOR WALL / observed top of wall framing at corridor walls common walls - areas noted / pending other rough inspections / reviewed construction progress and inspection scheduling with site superintendent | BRIANB | BRIANB | | BFR | P | 7116637 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 09/16/2021 | EXTERIOR WALL - FLR INTERSECTION / ROOF - TRAUMA VEST / FIRE-RESISTANT JOINT SYS - HILTI Design No. CEJ 421p - perimeter firebarrier sys / observed mineral wool and firestop joint spray at exterior wall - floor intersection / also met with GE Johnson construction management staff and design professional for project - reviewed details for Hilti Design No. CEJ 421p at curtain wall - floor slab intersection and applied to onsite conditions | BRIANB | BRIANB | | BSP | P | 7109879 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/15/2021 | Balance of wall top out framing OK | JEREMYA | JEREMYA | | BFR | P | 7107886 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/09/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR / NON - RATED COMMON WALLS - IMC 02 - 12 / 1HR FIRE PARTITIONS - ON CALL 6567 - 6568 - 6565 - 6566 / observed top of wall framing at non rated common walls and 1hr fire partitions (V489) at areas noted / discussed fire partition continuity and head wall with site reps / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7101809 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/07/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR / CORRIDOR COMMON WALLS - IMC 02 - 12 / STAFF LOUNGE 6576 - STAFF TLT 6578 - 6577 - TLT 6575 - 6574 - SOILED 6573 - CORRIDOR 6513 - CLEAN 6572 / observed top of wall framing at non rated common walls and 1hr fire barrier - 1hr smoke barriers at areas noted / discussed smoke barrier continuity with site reps / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7098789 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 09/07/2021 | PARTIAL / observed lath along east elevation from trauma to window well area | BRIANB | BRIANB | | BLA | P | 7098771 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/30/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - NON-RATED COMMON WALLS - IMC 14 - 22 / STORAGE 6588 - 6587 observed top of wall framing at non rated common walls and 1hr fire barrier - areas noted / discussed smoke barrier continuity with site reps / pending other rough inspections --
GYP INSPECTION / 6TH FLR / ONE SIDE - INSIDE LVR ROOM 6586 / V489 / observed 5/8" x gyp at inside LVR room | BRIANB | BRIANB | | BFR | P | 7090536 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/26/2021 | SHAFT 1 - 6TH FLR / 2HR FIRE-BARRIER V455 - WEST CORRIDOR SIDE / observed (2) layers 5/8" x" GYP / pending other rough inspections --
PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - RMS 6588 - 6589 NURSE - 6587 CLEAN - 6586 LVR - 6585 OFFICE - 6579 SOILED - 6580 OFFICE / WEST CORRIDOR COMMON WALL AT RMS 6576 - 6575 - 6572 / observed top of wall framing at rooms and corridor common walls - smoke partitions and fire barrier (V489) at areas noted / discussed fire barrier continuity with site reps / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7087260 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/24/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR / SMOKE PARTITIONS IMC 14 - 22 / observed top of wall framing at east corridor walls - areas noted / DOOR 6513B - 1HR SMOKE BARRIER / observed top of wall framing at door 6513b / STORAGE 6588 - NURSE STATION COMMON WALL - 1HR FIRE BARRER V489 / observed top of wall framing at areas noted / LVL 6586 - CORRIDOR 6533 COMMON WALL - 1HR FIRE BARRIER V489 / observed top of wall at area note / pending other rough inspections --
PARTIAL / 6th flr - Head Wall (V489) / EVS 6592 - IMC 46 COMMON WALL / observed mineral wool and fire spray at head of wall in concealed space / NOTE - inspected as a MF3U wall type - this wall type is not identified in the approved design - pending approved plan splice for wall type clarification --
PARTIAL / 6TH FLR / GYP - TOP OF WALL - 1HR FIRE BARRIER & 1HR SMOKE BARRIER (V489) / CORRIDOR COMMON WALL AT AREAS - STORAGE - 6588 - CLEAN 6587 - SOILED 6579 - SOILED HOLD 6573 / DOOR 6513B / observed top of wall gyp (American 5/8" AGX-1) at common wall between the areas noted / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7083762 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 08/24/2021 | NORTH ELEVATION / observed lath north elevation | BRIANB | BRIANB | | BLA | P | 7083702 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/19/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - DOOR 6513A -1HR SMOKE BARRIER V489 / observed top of wall framing at 1hr smoke barrier - areas noted / pending other rough inspections -- | BRIANB | BRIANB | | BFR | P | 7078497 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/18/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - NON-RATED COMMON WALLS - IMC 14 - 32 / IMC 52-54 1HR SMOKE BARRIER V496 / observed top of wall framing at non rated common walls and 1hr smoke barrier - areas noted / discussed smoke barrier continuity with site reps / pending other rough inspections --
SHAFT 1 - 6TH FLR / 2HR FIRE-BARRIER V455 - (4) SIDES / MTL FRAME - 1" GYP / observed mtl frame and 1" American gyp panels at shaft 1 6th floor / pending other rough inspections --
PARTIAL / 6th flr / GYP 1-SIDE - 1HR FIRE BARRIER (V489) / EVS 6563 - / observed 5/8" American gyp at IMC 62 side of 1hr fire barrier in EVS 6563 / NOTE - inspected as a MF3U wall type - this wall type is not identified in the approved design - pending approved plan splice for wall type clarification --
PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - CORRIDOR COMMON WALL AT ROOMS 6588 - 6771 / observed top of wall framing at corridor common walls including 1hr smoke barrier (V496) - smoke partitions and fire barrier (V489) at areas noted / discussed smoke barrier and fire barrier continuity with site reps / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7077339 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/16/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - SMOKE PARTITIONS IMC 46 - 62 / observed top of wall framing at east corridor walls - areas noted / pending other rough inspections --
SHAFT 2 - 6TH FLR / 2HR FIRE-BARRIER V455 - (2) SIDES / observed (2) layers 5/8" x gyp at north and west sides of upper - top of shaft 2 / pending other rough inspections --
PARTIAL / 6th flr WALL FRAME - 1HR FIRE BARRIER (V489) / EVS 6563 - IMC 62 COMMON WALL / observed wall frame at common wall between the areas noted / NOTE - inspected as a MF3U wall type - this wall type is not identified in the approved design - pending approved plan splice for wall type clarification --
PARTIAL / WALL FRAME - 1HR FIRE BARRIER (V489) & ONE SIDE GYP / EVS 6592 - IMC 46 COMMON WALL / observed wall frame and one side gyp (American 5/8" AGX-1) at common wall between the areas noted / NOTE - inspected as a MF3U wall type - this wall type is not identified in the approved design - pending approved plan splice for wall type clarification and wall layout modifications / pending other rough inspections
| BRIANB | BRIANB | | BFR | P | 7073740 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/12/2021 | SHAFT 2 - 6TH FLR / 2HR FIRE-BARRIER V455 - (3) SIDES / observed mtl framing and 1" American gyp panels at (3) sides of shaft 2 / observed penetrations at 1" gyp - see Hilti fire-stop detail W-L 5029 onsite / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7070676 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/10/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - NON-RATED COMMON WALLS IN IMC RMS 24 - 42 / observed top of wall framing at rooms noted / reviewed details for Hilti sys no w-l 5257 and fire-stop details for through penetrations at 2hr fire barrier with site reps | BRIANB | BRIANB | | BFR | P | 7067183 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/09/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - NON-RATED COMMON WALLS IN IMC RMS 24 - 42 / observed top of wall framing at rooms noted | BRIANB | BRIANB | | BFR | P | 7065453 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/05/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - 1hr FIRE BARRIER (V489) - LVR 6586 - CLEAN SUPPLY 6587 - STR-EQUIP 6558 / SMOKE PARTITION - MEDS 6594 / observed top of wall framing at west corridor wall at rooms noted / discussed details for 1hr fire rated assembly V489 and applied to onsite conditions with site superintendent and framing rep / discussed needing fire-stop details for all penetrations and inspected / pending other rough inspection | BRIANB | BRIANB | | BFR | P | 7062416 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/04/2021 | PARTIAL / FRAME - TOP OF WALL ONLY / 6TH FLR - SMOKE PARTITIONS IMC 24 - 42 / SMOKE BARRIER - IMC 24 / observed top of wall framing at areas noted / discussed details for 1hr fire rated assembly V496 smoke barrier and applied to onsite conditions with site superintendent and framing rep / discussed needing fire-stop details for all penetrations and inspected / pending other rough inspection
PARTIAL / WALL FRAME - MECH 7101 - VESTIBULE 7100 / FIRE BARRIER V489 / observed wall framing at areas noted / discussed details for 1hr fire barrer V489 with site reps / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7060801 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 08/02/2021 | PARTIAL / observed lath at Vestibule 7100 - roof deck | BRIANB | BRIANB | | BLA | P | 7057277 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 07/19/2021 | GYP INSPECTION - ROOM 4507 / 2HR FIRE BARRIER - V489 / observed 2nd layer 5/8" x gyp at exterior side of room 4507 for 2hr fire barrier / pending other rough inspections / reviewed continuity for 2hr fire barrier at ELEC RM 6593 with site reps | BRIANB | BRIANB | | BSP | P | 7041030 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 07/13/2021 | GYP INSPECTION - ROOM 4507 / 2HR FIRE BARRIER - V489 / observed 2nd layer 5/8" x gyp at interior side and base layer 5/8" x gyp at outside of room 4507 for 2hr fire barrier / pending other rough inspections | BRIANB | BRIANB | | BSP | P | 7034129 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 07/07/2021 | PARTIAL / WALL FRAME - ROOM 4507 / 2HR FIRE BARRIER - V489 / observed mtl wall framing and 5/8" x gyp at interior side of 2hr fire barrier / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7027490 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/29/2021 | PARTIAL / EXTERIOR WALL FRAME / observed remaining exterior wall framing along east - south east elevation / this completes inspections for exterior wall framing minus the loading area along the west elevation by the stair tower / pending other rough inspections / reviewed inspection history and construction progress for permit with site superintendent | BRIANB | BRIANB | | BFR | P | 7019334 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/22/2021 | PARTIAL / EXTERIOR FURRING AT ELEV. 12 - 13 / observed c studs at exterior wall framing along east elevation at area noted - this completes frame inspection at this area
ELEC. RM 6593 / 2HR FIRE BARRIER V 489 / discussed details for fire rated assembly and continuity requirements for 2hr fire barrier with site superintendent | BRIANB | BRIANB | | BFR | P | 7011666 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/15/2021 | PARTIAL / EXTERIOR FURRING AT ELEV. 12 - 13 / observed c studs at exterior wall framing at 6th flr at area noted
PARTIAL / CURTAIN WALL - FLR INTERSECTION / FIRE-RESISTANT JOINT SYS - HILTI Design No. CEJ 421p - perimeter firebarrier sys / 6TH FLR - HORSESHOE - TRIANGLE / observed mineral wool and firestop joint spray at curtain wall - floor intersection | BRIANB | BRIANB | | BFR | P | 7003335 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/10/2021 | EXTERIOR WALL FRAME / observed exterior wall framing at north elevation of trauma core and at parapet at triangle / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 6998396 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/09/2021 | PARTIAL / EXTERIOR FURRING AT ELEV. 12 - 13 / observed c studs at exterior wall framing along east elevation at area noted
GYP INSPECTION - ELEC. RM 6593 / 2HR FIRE BARRIER V 489 / observed face layer American 5/8" gyp / also discussed continuity requirements for 2hr fire barrier with site superintendent | BRIANB | BRIANB | | BFR | P | 6996463 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/08/2021 | south and west wall framing at elevators 12& 13 OK at roof top / Level 6 electric room, drywall screws on inside OK | JEREMYA | JEREMYA | | BFR | P | 6994329 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/03/2021 | PARTIAL / EXTERIOR WALL FRAME - NORTH - NORTH EAST ELEVATION at HORSE SHOE AREA / 5TH FLR TO PARAPET / observed exterior wall framing at areas noted / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 6990237 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 06/03/2021 | PARTIAL / CURTAIN WALL - FLR INTERSECTION / FIRE-RESISTANT JOINT SYS - HILTI Design No. CEJ 421p - perimeter firebarrier sys / 6TH FLR - SOUTH ELEVATION / observed mineral wool and firestop joint spray at curtain wall - floor intersection | BRIANB | BRIANB | | BSP | P | 6990227 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/27/2021 | Training with PPRBD inspector Jason / discussed plan sticker - type of construction 1A (IBC table 601)- occupancy I-2 condition 2 / discussed exterior curtain wall framing / reviewed 715.4 - curtain wall - floor intersection | BRIANB | BRIANB | | BSP | P | 6984167 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/27/2021 | Training with BrianB / reviewed type of construction 1-A, table 601 / Reviewed 715.4 exterior curtain wall, floor intersection / discussed exterior curtain wall framing / Reviewed plan sticker | JASONL | JASONL | | BSP | P | 6984158 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/27/2021 | ES report for spray applied wall insulation on file / Hilti detail for floor - curtain wall on file | BRIANB | BRIANB | | BSP | P | 6982667 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/26/2021 | PARTIAL / CURTAIN WALL - FLR INTERSECTION / FIRE-RESISTANT JOINT SYS - HILTI Design No. CEJ 421p - perimeter firebarrier sys / Grid line XD - 13 to X6 - Grid line X6 - XA to XD - Grid line XA - X7 to 13 / OUTSIDE CORNER at grid line XE & 13 / observed mineral wool and firestop joint spray at curtain wall - floor intersection | BRIANB | BRIANB | | BSP | P | 6982238 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 05/25/2021 | PARTIAL / EXTERIOR WALL FRAME - VESTIBULE 7100 / EXTERIOR WALLS - SOUTH DOGHOUSE / observed exterior wall framing at areas noted - pending other rough inspections / reviewed approved design - 2hr fire barrier assembly for shaft 2 and SFRM for stl columns - beams AND discussed IBC 715.4 exterior curtain wall/floor intersection with site superintendent | BRIANB | BRIANB | | BFR | P | 6980370 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 05/20/2021 | PARTIAL / EXTERIOR WALL FRAME - SOUTH ELEVATION / EXTERIOR WALLS - DOGHOUSE / observed exterior wall framing at areas noted - pending other rough inspections / reviewed approved design - 2hr fire barrier assembly for shaft 2 and SFRM for stl columns and beams with site superintendent | BRIANB | BRIANB | | BFR | P | 6975999 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/18/2021 | letter for deflection clips on file | BRIANB | BRIANB | | BSP | P | 6971590 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | R | 05/17/2021 | WALL FRAME - ELEC. RM 6593 / 2HR FIRE BARRIER V 489 / wall framing stops at steel beam(s) and do not extend to deck above to meet continuity requirements for 2hr fire barrier / proposed Hilti EJs on site for inspection - need to splice in proposed design modifications for approval / note - still need to inspect wall framing at steel column in electrical room
WALL FRAME - SHAFT 2 / EAST WALL / MTL FRAME & 1" GYP / 2HR FIRE BARRIER V455 / observed mtl framing and 1" American gyp panels at east - one side of 2hr shaft / reviewed details for UL V455 assembly with site superintendent
PARTIAL / EXTERIOR WALL FRAME - NORTH - NORTH EAST ELEVATION - GRID LINE 13 - XD.5 TO B AND LINE B 13 TO 16 / 5TH FLR TO PARAPET / observed exterior wall framing at areas noted | BRIANB | BRIANB | | BFR | R | 6971346 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 05/07/2021 | PARTIAL / EXTERIOR WALL FRAME - EAST ELEVATION - GRID LINE XD - 13 TO X7 / 5TH FLR TO PARAPET / observed exterior wall framing at areas noted | BRIANB | BRIANB | | BFR | P | 6961710 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 04/30/2021 | PARTIAL / EXTERIOR WALL FRAME - WEST ELEVATION - X7 TO 10.5 / 5TH FLR TO PARAPET / observed exterior wall framing at areas noted / reviewed approved design and discussed inspection scheduling with site superintendent | BRIANB | BRIANB | | BFR | P | 6953351 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 04/27/2021 | PARTIAL / EXTERIOR WALL FRAME - NORTH ELEVATION - EAST ELEVATION X6 TO TRAUMA CORE / 5TH FLR TO PARAPET / observed exterior wall framing at areas noted / reviewed approved design and discussed 3rd party observation letters (KUMAR) for structural steel and SFRM (1A construction) - also discussed IBC 715.4 exterior curtain wall/floor intersection with site superintendent | BRIANB | BRIANB | | BFR | P | 6949026 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 04/08/2021 | GYP INSPECTION / V489 2HR FIRE BARRIER / RM 4058 / observed face layer American 5/8" x gyp (V489) / observed mineral wool at head of wall 2hr fire barrier RM4058 - UL-HW-D-0042 / reviewed construction progress and inspection scheduling with site superintendent | BRIANB | BRIANB | | BSP | P | 6926929 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 03/30/2021 | GYP INSPECTION / U419 2HR FIRE BARRIER / RM 4058 / base layer American 5/8" x gyp okay - see approved plan splice dated 27JAN21 / reviewed construction progress and inspection scheduling with site superintendent | BRIANB | BRIANB | | BSP | P | 6915859 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | R | 03/22/2021 | GYP INSPECTION / U419 2HR FIRE BARRIER / RM 4058 / observed American 5/8" x gyp (fastening at 12o.c in field and 8" o.c at edges) where the approved fire rated assembly U419 requires USG | BRIANB | BRIANB | | BSP | R | 6906379 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 03/08/2021 | PARTIAL / WALL FRAMING - RM 4508 ONLY / 2HR FIRE-BARRIER / U419 / observed mtl wall framing at area noted only / pending other rough inspections / reviewed details for 2hr fire barrier assembly U419 with site superintendent | BRIANB | BRIANB | | BFR | P | 6892150 |
ENCORE ELECTRIC, INC. | E= | C | 07/20/2022 | FIRE ALARM INSPECTION: | AARONR | AARONR | | E= | C | 7454032 |
ENCORE ELECTRIC, INC. | E= | C | 07/20/2022 | FIRE ALARM INSPECTION: | AARONR | AARONR | | E= | C | 7454028 |
ENCORE ELECTRIC, INC. | E= | C | 07/12/2022 | Hall ways on 5th and 6th floor will need to be checked for TR once receptacles come in. | AARONR | AARONR | | E= | C | 7443645 |
ENCORE ELECTRIC, INC. | E= | P | 07/11/2022 | Receptacles requiring GFCI protection on 5th floor OK. | AARONR | AARONR | | E= | P | 7441981 |
ENCORE ELECTRIC, INC. | E= | P | 06/21/2022 | Patient and corridors on south area finals OK. | AARONR | AARONR | | E= | P | 7419898 |
ENCORE ELECTRIC, INC. | E= | P | 06/20/2022 | Rooms and corridors OK for finals on north side. | AARONR | AARONR | | E= | P | 7418103 |
ENCORE ELECTRIC, INC. | E= | P | 06/15/2022 | South patient rooms and corridors OK. | AARONR | AARONR | | E= | P | 7412929 |
ENCORE ELECTRIC, INC. | ER | P | 05/27/2022 | FIRE ALARM INSPECTION: Ceiling rough OK on 5th floor in front of elevator. | AARONR | AARONR | | ER | P | 7393131 |
ENCORE ELECTRIC, INC. | ER | P | 05/27/2022 | Ceiling rough OK on 5th floor in front of elevator. | AARONR | AARONR | | ER | P | 7393079 |
ENCORE ELECTRIC, INC. | E= | R | 05/26/2022 | North patient room and corridor finals OK. | AARONR | AARONR | | E= | R | 7390568 |
ENCORE ELECTRIC, INC. | ER | P | 05/26/2022 | FIRE ALARM INSPECTION: Not ready. | AARONR | AARONR | | ER | P | 7390567 |
ENCORE ELECTRIC, INC. | ER | P | 05/26/2022 | Not ready. | AARONR | AARONR | | ER | P | 7390553 |
ENCORE ELECTRIC, INC. | E= | P | 05/24/2022 | Above ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | E= | P | 7387892 |
ENCORE ELECTRIC, INC. | ER | P | 05/24/2022 | FIRE ALARM INSPECTION: Above ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7387883 |
ENCORE ELECTRIC, INC. | ER | P | 05/24/2022 | Above ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7387879 |
ENCORE ELECTRIC, INC. | ER | R | 05/23/2022 | FIRE ALARM INSPECTION: See electrical notes. | AARONR | AARONR | | ER | R | 7386185 |
ENCORE ELECTRIC, INC. | ER | R | 05/23/2022 | Need to install one strap on light fixture. --- Need to use listed fittings on HCF cable with dimming cable on 3 light fixtures. | AARONR | AARONR | | ER | R | 7386176 |
ENCORE ELECTRIC, INC. | ER | P | 05/18/2022 | FIRE ALARM INSPECTION: FA inspected 5-17-22 with electric | RANDY | RANDY | | ER | P | 7380365 |
ENCORE ELECTRIC, INC. | ER | P | 05/17/2022 | FIRE ALARM INSPECTION: Above ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7384770 |
ENCORE ELECTRIC, INC. | ER | P | 05/17/2022 | Above ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7379690 |
ENCORE ELECTRIC, INC. | ER | P | 05/13/2022 | FIRE ALARM INSPECTION: Above ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7376283 |
ENCORE ELECTRIC, INC. | ER | P | 05/13/2022 | Above ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7376277 |
ENCORE ELECTRIC, INC. | ER | P | 05/12/2022 | FIRE ALARM INSPECTION: Rough above ceiling OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7374488 |
ENCORE ELECTRIC, INC. | ER | P | 05/12/2022 | Rough above ceiling OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7374482 |
ENCORE ELECTRIC, INC. | ER | P | 05/11/2022 | FIRE ALARM INSPECTION: Above ceiling rough OK. ---- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7372697 |
ENCORE ELECTRIC, INC. | ER | P | 05/11/2022 | Above ceiling rough OK. ---- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7372619 |
ENCORE ELECTRIC, INC. | ER | P | 04/27/2022 | FIRE ALARM INSPECTION: Ceilings marked on drawings 4/27 Area 8 | BRETC | BRETC | | ER | P | 7355038 |
ENCORE ELECTRIC, INC. | ER | P | 04/27/2022 | Ceilings marked on drawings 4/27 Area 8 / Critical and Normal circuits - ok | BRETC | BRETC | | ER | P | 7355031 |
ENCORE ELECTRIC, INC. | ER | P | 04/26/2022 | FIRE ALARM INSPECTION: Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7353173 |
ENCORE ELECTRIC, INC. | ER | P | 04/26/2022 | Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7353159 |
ENCORE ELECTRIC, INC. | ER | P | 04/25/2022 | FIRE ALARM INSPECTION: Above ceiling OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7351600 |
ENCORE ELECTRIC, INC. | ER | P | 04/25/2022 | Above ceiling OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7351537 |
ENCORE ELECTRIC, INC. | ER | P | 04/21/2022 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 7347915 |
ENCORE ELECTRIC, INC. | ER | P | 04/21/2022 | patient room ceilings marked on plans | RANDY | RANDY | | ER | P | 7347913 |
ENCORE ELECTRIC, INC. | ER | P | 04/20/2022 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 7345056 |
ENCORE ELECTRIC, INC. | ER | P | 04/20/2022 | 5th floor N/E patient room ceilings marked on plans | RANDY | RANDY | | ER | P | 7345048 |
ENCORE ELECTRIC, INC. | ER | P | 04/19/2022 | Above ceiling OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7343793 |
ENCORE ELECTRIC, INC. | ER | P | 04/19/2022 | FIRE ALARM INSPECTION: Above ceiling OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7343789 |
ENCORE ELECTRIC, INC. | ER | P | 04/14/2022 | FIRE ALARM INSPECTION: Wall rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7339385 |
ENCORE ELECTRIC, INC. | ER | P | 04/14/2022 | Wall rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7339378 |
ENCORE ELECTRIC, INC. | ER | P | 04/13/2022 | FIRE ALARM INSPECTION: Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7337824 |
ENCORE ELECTRIC, INC. | ER | P | 04/13/2022 | FIRE ALARM INSPECTION: Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7337735 |
ENCORE ELECTRIC, INC. | ER | P | 04/12/2022 | Check prints for areas inspected | JIMMY | JIMMY | | ER | P | 7336023 |
ENCORE ELECTRIC, INC. | ER | P | 04/12/2022 | FIRE ALARM INSPECTION: Check prints for areas inspected | JIMMY | JIMMY | | ER | P | 7336022 |
ENCORE ELECTRIC, INC. | ER | P | 04/06/2022 | FIRE ALARM INSPECTION: Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7328593 |
ENCORE ELECTRIC, INC. | ER | P | 04/06/2022 | Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7328569 |
ENCORE ELECTRIC, INC. | ER | P | 03/31/2022 | FIRE ALARM INSPECTION: Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7322186 |
ENCORE ELECTRIC, INC. | ER | P | 03/31/2022 | Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7322178 |
ENCORE ELECTRIC, INC. | ER | P | 03/22/2022 | FIRE ALARM INSPECTION: Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7310834 |
ENCORE ELECTRIC, INC. | ER | P | 03/22/2022 | Ceiling rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7310825 |
ENCORE ELECTRIC, INC. | ER | P | 03/14/2022 | FIRE ALARM INSPECTION: Rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7300864 |
ENCORE ELECTRIC, INC. | ER | P | 03/14/2022 | Rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7300858 |
ENCORE ELECTRIC, INC. | ER | P | 03/08/2022 | FIRE ALARM INSPECTION: Ceiling inspection OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7294612 |
ENCORE ELECTRIC, INC. | ER | P | 03/08/2022 | Ceiling inspection OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7294611 |
ENCORE ELECTRIC, INC. | ER | P | 03/02/2022 | FIRE ALARM INSPECTION: Above ceiling OK. --- See prints fro area inspected. | AARONR | AARONR | | ER | P | 7288274 |
ENCORE ELECTRIC, INC. | ER | P | 03/02/2022 | Above ceiling OK. --- See prints fro area inspected. | AARONR | AARONR | | ER | P | 7288272 |
ENCORE ELECTRIC, INC. | ER | P | 02/22/2022 | FIRE ALARM INSPECTION: See prints for areas inspected. | AARONR | AARONR | | ER | P | 7278612 |
ENCORE ELECTRIC, INC. | ER | P | 02/22/2022 | See prints for areas inspected. | AARONR | AARONR | | ER | P | 7278606 |
ENCORE ELECTRIC, INC. | ER | P | 02/16/2022 | FIRE ALARM INSPECTION: See prints for areas inspected | AARONR | AARONR | | ER | P | 7273578 |
ENCORE ELECTRIC, INC. | ER | P | 02/16/2022 | See prints for areas inspected. | AARONR | AARONR | | ER | P | 7273458 |
ENCORE ELECTRIC, INC. | ER | P | 01/05/2022 | Soffit rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7230001 |
ENCORE ELECTRIC, INC. | ER | P | 12/29/2021 | FIRE ALARM INSPECTION: Wall and soffit rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7224342 |
ENCORE ELECTRIC, INC. | ER | P | 12/29/2021 | Wall and soffit rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7224335 |
ENCORE ELECTRIC, INC. | ER | P | 12/22/2021 | Soffit rough and wall rough OK. --- See prints fro areas inspected. | AARONR | AARONR | | ER | P | 7219292 |
ENCORE ELECTRIC, INC. | ER | P | 12/21/2021 | Rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7216476 |
ENCORE ELECTRIC, INC. | ER | P | 12/14/2021 | Soffits on the 6th floor north sided of the building OK. | AARONR | AARONR | | ER | P | 7209104 |
ENCORE ELECTRIC, INC. | ER | P | 12/13/2021 | FIRE ALARM INSPECTION: Wall rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7207459 |
ENCORE ELECTRIC, INC. | ER | P | 12/13/2021 | Wall rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7207458 |
ENCORE ELECTRIC, INC. | ER | P | 12/06/2021 | FIRE ALARM INSPECTION: Wall rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7199251 |
ENCORE ELECTRIC, INC. | ER | P | 12/06/2021 | Wall rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7199246 |
ENCORE ELECTRIC, INC. | ER | P | 11/30/2021 | Wall rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7192663 |
ENCORE ELECTRIC, INC. | ER | P | 11/22/2021 | FIRE ALARM INSPECTION: Wall rough OK. See prints for areas inspected. | AARONR | AARONR | | ER | P | 7184951 |
ENCORE ELECTRIC, INC. | ER | P | 11/22/2021 | Wall rough OK. See prints for areas inspected. | AARONR | AARONR | | ER | P | 7184946 |
ENCORE ELECTRIC, INC. | ER | P | 11/08/2021 | Hard lids rough OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7168494 |
ENCORE ELECTRIC, INC. | ER | P | 11/01/2021 | FIRE ALARM INSPECTION: See prints for areas inspected. | AARONR | AARONR | | ER | P | 7161959 |
ENCORE ELECTRIC, INC. | ER | P | 11/01/2021 | See prints for areas inspected. | AARONR | AARONR | | ER | P | 7161868 |
ENCORE ELECTRIC, INC. | ER | P | 10/26/2021 | Soffit rough marked on prints. | AARONR | AARONR | | ER | P | 7155531 |
ENCORE ELECTRIC, INC. | ER | P | 10/25/2021 | ER OK --- SOFFIT -- 6516 - 6518 - 6520 - 6522 - 6524 - 6526 - 6528 - 6530 - 6532 - 6534 - 6536 - 6538 - 6540 - 6542 ------ | GREGM | GREGM | | ER | P | 7153036 |
ENCORE ELECTRIC, INC. | ER | P | 10/21/2021 | Wall rough OK --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7151002 |
ENCORE ELECTRIC, INC. | ER | P | 10/21/2021 | FIRE ALARM INSPECTION: Wall rough OK --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7150815 |
ENCORE ELECTRIC, INC. | ER | P | 10/15/2021 | FIRE ALARM INSPECTION: Wall rough OK......See prints for area inspected. | AARONR | AARONR | | ER | P | 7143968 |
ENCORE ELECTRIC, INC. | ER | P | 10/15/2021 | Wall rough OK......See prints for area inspected. | AARONR | AARONR | | ER | P | 7143962 |
ENCORE ELECTRIC, INC. | ER | P | 10/11/2021 | FIRE ALARM INSPECTION: FA rough in walls OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7137381 |
ENCORE ELECTRIC, INC. | ER | P | 10/11/2021 | Electrical rough in walls OK. --- See prints for areas inspected. | AARONR | AARONR | | ER | P | 7137379 |
ENCORE ELECTRIC, INC. | ER | P | 10/07/2021 | EF on roof top and VFD's. --- See prints fro area inspected. | AARONR | AARONR | | ER | P | 7134441 |
ENCORE ELECTRIC, INC. | EP | P | 10/06/2021 | Panels and X-FMR --- See prints for equipment inspected. | AARONR | AARONR | | EP | P | 7131812 |
ENCORE ELECTRIC, INC. | ER | P | 10/04/2021 | consultation only | RANDY | RANDY | | ER | P | 7128188 |
ENCORE ELECTRIC, INC. | ER | P | 10/04/2021 | FIRE ALARM INSPECTION: FA marked with electric | RANDY | RANDY | | ER | P | 7128185 |
ENCORE ELECTRIC, INC. | E= | R | 10/04/2021 | consultation only | RANDY | RANDY | | E= | R | 7128184 |
ENCORE ELECTRIC, INC. | ER | P | 09/30/2021 | rooms marked on plans | RANDY | RANDY | | ER | P | 7126305 |
ENCORE ELECTRIC, INC. | ER | P | 09/23/2021 | FIRE ALARM INSPECTION: FA in corridor marked with electric | RANDY | RANDY | | ER | P | 7118472 |
ENCORE ELECTRIC, INC. | E= | R | 09/23/2021 | no final | RANDY | RANDY | | E= | R | 7118470 |
ENCORE ELECTRIC, INC. | ER | P | 09/23/2021 | ISO rooms area 2 walls and corridor marked on plans | RANDY | RANDY | | ER | P | 7118469 |
ENCORE ELECTRIC, INC. | ER | P | 09/02/2021 | 6th floor north shaft wall and med room marked on plans | RANDY | RANDY | | ER | P | 7095839 |
ENCORE ELECTRIC, INC. | ER | P | 08/30/2021 | walls on roof marked on plans | RANDY | RANDY | | ER | P | 7090865 |
ENCORE ELECTRIC, INC. | ER | P | 07/29/2021 | exterior walls marked on plans | RANDY | RANDY | | ER | P | 7054687 |
ENCORE ELECTRIC, INC. | ER | P | 06/30/2021 | electric room wall rough marked on plans | RANDY | RANDY | | ER | P | 7021334 |
ENCORE ELECTRIC, INC. | ER | P | 06/23/2021 | consultation of helipad on roof------walls marked on plans | RANDY | RANDY | | ER | P | 7013429 |
ENCORE ELECTRIC, INC. | ER | P | 05/26/2021 | roof outlets marked on plans | RANDY | RANDY | | ER | P | 6982498 |
ENCORE ELECTRIC, INC. | E= | P | 04/21/2021 | wrong permit will add notes to correct one | RANDY | RANDY | | E= | P | 6942361 |
ENCORE ELECTRIC, INC. | ER | P | 03/09/2021 | 4th fl room 4508---consultation as well | RANDY | RANDY | | ER | P | 6894097 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | C | 08/04/2022 | STAMPED ENGINEER LETTER FROM ENGINEER OF RECORD APPROVING THE TEST AND BALANCE REPORT RECEIVED. SEE IMAGES / MECHANICAL CONTRACTOR FINAL OK / | LIDO | LIDO | | H= | C | 7470867 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 07/28/2022 | TEST AND BALANCE REPORT REVIEW / 2ND FLOOR PLAN SPLICE MH121 / MH123 DATED 5/2/22 : MISSING STAIRWELL SUPPLY AND RETURN READINGS / 4TH FLOOR PLAN PAGE MH141 / MH142 : MISSING STAIRWELL EXHAUST READINGS / ROOF PLAN PAGE MH172 : MISSING FCU-7-1 SUPPLY AND RETURN AIR READING FOR ELEVATOR LOBBY / AHU-14 AND AHU-15 - OUTSIDE AIR IS OUTSIDE THE10% +/- ALLOWED / 5TH FLOOR PLAN PAGE MH-151(BDA 626) -VAV-14-523 ROOM 5573 SUPPLY GRILL #1 AND #2 ARE OUTSIDE THE10% +/- ALLOWED. FOLLOWING RETURN AIR GRILLS ARE OUTSIDE THE 10% +/- ALLOWED : ROOM 5572 R#1, ROOM 5571 R#14, ROOM 5574 R#22, CORR R#30/ 5TH FLOOR PLAN PAGE MH-152 (BDA 627) - VAV-14-515 ROOM 5579 SUPPLY GRILL #1 IS OUTSIDE THE10% +/- ALLOWED / 5TH FLOOR PLAN PAGE MH-152 (BDA627) - FOLLOWING RETURN AIR GRILLS ARE OUTSIDE THE10% +/- ALLOWED : ROOM #5586 R#24, ROOM 5587 R#25, ROOM 5588 R#26, CORR R#35, ROOM 5594 R#30, ROOM 5595 R#31, ROOM 5596 R#32, ROOM 5585 R#33 / THE FOLLOWING EXHAUST AIR GRILLS ARE NOT PER THE CFM DESIGN AND ARE OUTSIDE THE 10% +/- ALLOWED : ROOM 5592 E#1, ROOM 5550 E#21, ROOM 5548 E#24./ THE FOLLOWING RETURN AIR GRILLS ARE MISSING THE READINGS : ROOM 5533 R#27 AND CORR R#29 / 6TH FLOOR PLAN PAGE MH-161 (BDA 628) - VAV-15-642 SUPPLY AIR WAS NOT DONE PER THE DESIGNED CFM'S (see p;lan splice dated 6/13/22) / FOLLOWING RETURN AIR GRILLS ARE OUTSIDE THE10% +/- ALLOWED : RM 6568 R#7, ROOM 6567 R#8, ROOM 6567 R#9, RM 6565 R#10, ROOM 6501 R#11, ROOM 6512 R#12, ROOM 6508 R#15, ROOM RM 6506 R#16, ROOM 6504 R#17, ROOM 6562 R#20, ROOM 6560 R#21, ROOM 6571 R#22, ROOM 6572 R#23, ROOM 6522 R#24, ROOM 6520 R#25, ROOM 6518 R#26, ROOM 6514 R#27, ROOM 6558 R#30, ROOM 6556 R#31, ROOM 6554 R#32, CORR R#40 / 6TH FLOOR PLAN PAGE MH-162 (BDA 629) - THE FOLLOWING RETURN GRILLS ARE OUTSIDE THE 10% +/- ALLOWED : ROOM 6596 R#1, ROOM 6595 E#2, ROOM 6589 R#4, ROOM 6586 R#33, ROOM 6585 R#35, ROOM 6593 R#36, ROOM 6587 R#37, ROOM 6588 R#38, CORR R#39./ ROOM 6533 R#3 AND ROOM 6500 R#5 ARE MISSING THE FINAL RETURN AIR READINGS / ROOM 6580 R#34 RETURN AIR READINGS ARE NOTE PER THE DESIGNED CFM'S / NEED REVISED TEST AND BALANCE REPORT OR ENGINEER TO APPROVE THE READINGS / | LIDO | LIDO | | H= | P | 7463402 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 07/18/2022 | TEST AND BALANCE REPORT IS BEING REVIEWED / | LIDO | LIDO | | H= | P | 7449210 |
OTIS ELEVATOR COMPANY | HE= | C | 07/12/2022 | ELEVATORS #10, #11, #12 AND #13 ALTERATION ITEMS ARE COMPLETE. | ROBERTV | ROBERTV | | HE= | C | 7443584 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 07/07/2022 | ALL SCOPE OF WORK COMPLETE / FINAL PENDING : NEED TEST AND BALANCE REPORT / | LIDO | LIDO | | H= | P | 7438796 |
U.S. ENGINEERING CONSTRUCTION, LLC | HSP | P | 07/07/2022 | PICTURES RECEIVED OF 3 ADDED SMOKE DAMPERS AND 3 REMOTE SMOKE INDICATORS. SEE IMAGES / | LIDO | LIDO | | HSP | P | 7438791 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 06/29/2022 | SEE IMAGES FOR THE FOLLOWING : CU-7-2 THERMOSTAT INSTALLED / CU-7-1 THERMOSTAT INSTALLED / FCU-7-1 CONDENSATE DISPOSAL DRAIN PAN AND PIPING INSTALL OK / HYDRONIC CONTRACTOR FINAL OK / | LIDO | LIDO | | H= | C | 7429733 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 06/27/2022 | FINAL PENDING : 5TH FLOOR PLAN SPLICE DATED 6/13/22 PAGE MH152 (added return air duct, grill and smoke damper) : NEED VERIFICATION OF REMOTE SMOKE INDICATORS / 6TH FLOOR PLAN SPLICE DATED 6/13/22 PAGE MH162 (added return air duct, grill and smoke damper) : NEED VERIFICATION DAMPER AND REMOTE SMOKE INDICATOR / NEED TO REVIEW IF ALL SCOPE OF WORK IS COMPLETE, SPLICES AND DOCUMENTS ARE COMPLETE / NEED TEST AND BALANCE REPORT / | LIDO | LIDO | | H= | P | 7426877 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 06/27/2022 | FINAL PENDING : 5TH FLOOR PLAN SPLICE DATED 6/13/22 PAGE MH152 : NEED VERIFICATION OF REMOTE SMOKE INDICATORS / 6TH FLOOR PLAN SPLICE DATED 6/13/22 PAGE MH162 : NEED VERIFICATION DAMPER AND REMOTE SMOKE INDICATOR / NEED TO REVIEW IF ALL SCOPE OF WORK IS COMPLETE, SPLICES AND DOCUMENTS ARE COMPLETE / NEED TEST AND BALANCE REPORT / | LIDO | LIDO | | H= | P | 7426878 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | C | 06/27/2022 | 5TH FLOOR PLAN SPLICE DATED 6/13/22 PAGE MH151 (added return air duct and grill) : INSTALL OK / 5TH FLOOR PLAN SPLICE DATED 6/13/22 PAGE MH152 (added return air duct, grill and smoke damper) : NEED VERIFICATION OF REMOTE SMOKE INDICATORS / DAMPER, DUCT AND GRILL INSTALL OK / 6TH FLOOR PLAN SPLICE DATED 6/13/22 PAGE MH161 (added return air duct and grill) : DUCT AND GRILL INSTALL OK / 6TH FLOOR PLAN SPLICE DATED 6/13/22 PAGE MH162 (added return air duct, grill and smoke damper) : NEED VERIFICATION DAMPER AND REMOTE SMOKE INDICATOR INSTALL / DUCT AND GRILL INSTALL OK / ALL DUCT ROUGH COMPLETE / | LIDO | LIDO | | HD | C | 7426867 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 06/09/2022 | ALL THE FOLLOWING HWS / HWR PIPING INSPECTED UNDER OPERATING PRESSURE WITH NO VISIBLE LEAKS / 4TH FLOOR PLAN PAGE MP-141 : UH-1A INSTALL (including hws / hwr piping) OK / 4TH FLOOR PLAN PAGE MP-142 : UH-1B INSTALL (including hws / hwr piping) OK / ROOF PLAN PAGE MP-172 : CU-7-2 MISSING THERMOSTAT. INSTALL (including hws / hwr piping) OK / FCU-7-1 NEED TO COMPLETE CONDENSATE DISPOSAL. NSTALL (including hws / hwr piping) OK / UH-1C INSTALL (including hws / hwr piping) OK / ROOF PLAN PAGE MP-171 : CU-7-1 MISSING THERMOSTAT. INSTALL (including hws / hwr piping) OK /
| LIDO | LIDO | | H= | P | 7406150 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 06/08/2022 | 4TH FLOOR PLAN SPLICE DATED 06/06/2022 SHOWING CORRECT LOCATIONS OF AHU-14 AND AHU-15 IS ON FILE / 4TH FLOOR PLAN PAGE MH-141 (RM# 4507) / PLAN PAGE MH-141 (RM# 4508) : STAIRWELL MECHANICAL ROOM FINAL OK / NEED TO REVIEW PLANS TO VERIFY ALL SCOPE OF WORK IS COMPLETED / 2ND FLOOR PLAN SPLICE MH-121 / MH-123 DATED 05/ 05/ 2022 : SUPPLY AND EXHAUST DUCT ROUGH OK. REGISTERS AND GRILLS OK /
| LIDO | LIDO | | HD | P | 7404437 |
OLSON PLUMBING & HEATING COMPANY | HWP | C | 06/08/2022 | | LIDO | LIDO | | HWP | C | 7404269 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 06/08/2022 | 4TH FLOOR PLAN PAGE MP 142 : SPLICE SHOWING CORRECT LOCATION OF AHU-14 AND AHU-15 ON FILE / FINAL PENDING :REVIEW OF PLANS TO VERIFY ALL SCOPE OF WORK IS COMPLETE / | LIDO | LIDO | | H= | P | 7404262 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 06/05/2022 | PLAN PAGE MH-172 ROOF FINAL OK / PLAN PAGE MH-172 PLICE DATED 04/07/2022 FOR FCU7-1 (roof penthouse elevator lobby) PENETRATIONS THROUGH RATED WALL LOCATED IN IMAGES PER SCANNING / 5TH FLOOR PLAN PAGE MH-151 / 6TH FLOOR PLAN PAGE MH-161 PLAN SPLICE DATED 04/07/2022 FOR ADDED GAS STORAGE ROOMS LOCATED IN IMAGES PER SCANNING. 5TH ENTIRE FLOOR FINAL OK / 6TH FLOOR PLAN PAGE MH-162 FINAL OK / 6TH FLOOR PLAN PAGE MH-161 FINAL PENDING : NEED GAS STORAGE ROOM SUPPLY DAMPER INSTALL INSPECTED / | LIDO | LIDO | | HD | P | 7399707 |
OTIS ELEVATOR COMPANY | H= | R | 06/03/2022 | WITNESSED REMAINING PUNCH LIST ITEMS FOR ELEVATORS #10-13. ELEVATORS #10 AND #11 ARE NEEDING "IN CASE OF FIRE" SIGNS AT FLOORS 5 AND 6. THE TOP OF HOISTWAY FIRE ALARM DETECTION WAS NOT PRESENT AT THE INSPECTION AND STILL NEEDS TO BE INSTALLED AND TESTED. ELEVATORS #12 AND #13 NEED IN CASE OF FIRE SIGNS AT THE 6TH FLOOR AND ALL BADGE ACCESS CARD READERS NEED TO BE INSTALLED AND TESTED ON ALL FLOORS. THE FIRE ALARM DETECTION AT THE TOP OF THE HOISTWAY IS STILL MISSING AND NEEDS TO BE INSTALLED AND TESTED. ELEVATOR #12 DOOR CLOSE FUNCTION IS NOT WORKING ON PHASE 2 FIRE EMERGENCY OPERATION AND SHALL BE REMEDIED. | MIKEM | MIKEM | | H= | R | 7399512 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 06/02/2022 | 4TH FLOOR PLAN PAGE MH 142 (BDA 485) : PLAN SHOWS AHU-14 BUT AHU-15 IS BEING INSTALLED AT THIS LOCATION. NEED REVISED PLAN SPLICE SHOWING THE CORRECT AHU UNIT BEING INSTALLED AT THIS LOCATION . / AHU-15 INSTALL OK / 4TH FLOOR PLAN PAGE MH 141 (BDA 484) : PLAN SHOWS AHU-15 BUT AHU-14 IS BEING INSTALLED AT THIS LOCATION. NEED REVISED PLAN SPLICE SHOWING THE CORRECT AHU UNIT BEING INSTALLED AT THIS LOCATION . AHU-14 INSTALL OK / 5TH FLOOR PLAN PAGE MH 151 : NEED TO CONSULT WITH PLAN SCANNING ABOUT GAS STORAGE ROOM SPLICE NOT ON FILE / 5TH FLOOR PLAN PAGE MH-151/ MH152 : FINAL PENDING GAS STORAGE ROOM SPLICE AND TEST AND BALNCE REPORT / | LIDO | LIDO | | HD | P | 7397352 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 05/23/2022 | 4TH FLOOR PLAN PAGE MP141 (BDA 492) : PLAN SHOWS AHU-14 AS AHU-15. NEED REVISED PLAN SPLICE SHOWING THE CORRECT AHU UNIT BEING INSTALLED AT THIS LOCATION . AHU-14- CWS / CWR AND HWS / HWR PIPING UNDER OPERATING PRESSURE. NO VISIBLE LEAKS. PIPING INSTALLED PER PLAN. FINAL CONNECTIONS TO AHU-14 OK/ HWCP14 (pump) INSTALL OK / 4TH FLOOR PLAN PAGE MP142 (BDA 492) : PLAN SHOWS AHU-15 AS AHU-14. NEED REVISED PLAN SPLICE SHOWING THE CORRECT AHU UNIT BEING INSTALLED AT THIS LOCATION . AHU-15- CWS / CWR AND HWS / HWR PIPING UNDER OPERATING PRESSURE. NO VISIBLE LEAKS. PIPING INSTALLED PER PLAN. FINAL CONNECTIONS TO AHU-15 OK/ HWCP15 (pump) INSTALL OK / | LIDO | LIDO | | HWP | P | 7385960 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 05/06/2022 | 5TH FLOOR PLAN PAGE MH152 : NEED REMOTE SMOKE INDICATORS / ALL THERMOSTATS OK / ALL PRESSURE SENSORS FOR ISOLATION ROOMS OK / SPLICE FOR ADDED PRESSURE SENSORS FOR ALL ISOLATION ROOMS ON FILE / | LIDO | LIDO | | HD | P | 7367389 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 05/05/2022 | 5TH FLOOR PLAN PAGE MH151 : ALL THERMOSTATS OK / FINAL PENDING FOR THIS AREA - COLUMN LINE (XD) EAST FINAL, REMOTE SMOKE INDICATORS. NEED SPLICE FOR ADDED MED GAS ROOM EAST OF COLUMN LINE (XD). NEED TEST AND BALANCE REPORT / 6TH FLOOR PLAN PAGE MH161 / MH162 : SPLICE FOR ADDED PRESSURE SENSORS FOR ALL ISOLATION ROOMS ON FILE /
| LIDO | LIDO | | HD | P | 7365684 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 05/04/2022 | ROOF - EF-9 / EF-11 EXHAUST FANS AND EXHAUST DUCT INSTALLED PER PLAN / REVISED EQUIPMENT SCHEDULE ON FILE SHOWING COOK MANUFACTURER FOR ALL ROOF EXHAUST FANS / ROOF FINAL PENDING : FCU 7-1 -NEED CONSULT WITH PLAN REVIEW IN REGARDS TO PLAN SPLICE NOT ON FILE FOR NO FIRE DAMPER BEING INSTALLED FOR SUPPLY AND RETURN AIR DUCT PENETRATIONS THROUGH A FIRE BARRIER (stamped mechanical plan page is on site referring to 2015 imc code section 607.5.2 (3)./ | LIDO | LIDO | | HD | P | 7364084 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 04/19/2022 | 5TH FLOOR PLAN PAGE MH 151 :ALL VAV'S FROM THIS PLAN PAGE FINAL HWS / HWR PIPE CONNECTION TO COILS UNDER OPERATING PRESSURE, NO VISIBLE LEAKS . CONNECTIONS OK / 4TH FLOOR PLAN PAGE MP-142 - AHU-15 HUMIDIFIER LOW PRESSURE STEAM SUPPLY AND RETURN PIPING OK. CONDENSATE OK / | LIDO | LIDO | | HWP | P | 7343662 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 04/19/2022 | 5TH FLOOR PLAN PAGE MH-151 / 6TH FLOOR PLAN PAGE MH-161 (added storage rooms east of column line (XD)) : INSPECTED PER PLANS ON SITE. PLANS ARE IN THE PROCESS OF BEING REVIEWED BY PLAN REVIEW FOR APPROVAL. PROCEED AT OWN RISK / 2 FIRE DAMPER FRAMES OK / SUPPLY DUCT INSTALL OK / | LIDO | LIDO | | HD | P | 7343656 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 04/13/2022 | CONSULT FOR ADDED MED GAS ROOM ON 6TH FLOOR / APPROVED PLANS FOR THIS ROOM NOT ON FILE. CANNOT DO ANY INSPECTIONS FOR THIS MED GAS ROOM UNTIL APPROVED PLANS ARE ON FILE / | LIDO | LIDO | | HD | P | 7336920 |
U.S. ENGINEERING CONSTRUCTION, LLC | HSP | P | 04/13/2022 | Stamped engineer letter received allowing return air pass to be achieved by a 3/4" undercut door for rooms that do not have ducted return. See images | LIDO | LIDO | | HSP | P | 7336440 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 04/12/2022 | 6TH FLOOR PLAN PAGE MH 161 / MH 162 :ALL VAV'S FROM THIS PLAN PAGE FINAL HWPS / HWPR PIPE CONNECTION TO COILS UNDER OPERATING PRESSURE, NO VISIBLE LEAKS . CONNECTIONS OK / | LIDO | LIDO | | HWP | P | 7335689 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 04/11/2022 | 6TH FLOOR PLAN PAGE MH161 (BDA 580) / MH162 (BDA 581) FINAL PENDING : NEED ADDED MED GAS ROOMS VENTILATION COMPLETED (splice not on file at this time) / PRESSURE SENSORS INSTALLED FOR ALL ISOLATION ROOMS. NEED PLAN SPLICE MATCHING THE INSTALL / ALSO NEED ROOMS FROM COLUMN LINE (XD) TO THE EAST / NEED TEST AND BALANCE REPORT / ALL REMOTE SMOKE INDICATORS INSTALLED /
| LIDO | LIDO | | HD | P | 7334173 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 04/07/2022 | 6TH FLOOR PLAN PAGE MH 161 :ALL VAV'S FROM THIS PLAN PAGE FINAL CONNECTION TO COILS UNDER OPERATING PRESSURE, NO VISIBLE LEAKS . CONNECTIONS OK / | LIDO | LIDO | | HWP | P | 7330663 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 04/07/2022 | 6TH FLOOR PLAN PAGE MH 161 :ALL VAV'S FROM THIS PLAN PAGE FINAL CONNECTION TO COILS UNDER OPERATING PRESSURE, NO VISIBLE LEAKS . CONNECTIONS OK / | LIDO | LIDO | | HWP | P | 7330664 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 04/06/2022 | 6TH FLOOR PLAN PAGE MH 161 : STILL NEED FROM COLUMN LINE XC WEST AND COLUMN LINE 16 NORTH / 17 VAV FINAL CONNECTION TO COILS UNDER OPERATING PRESSURE, NO VISIBLE LEAKS . CONNECTIONS OK / | LIDO | LIDO | | HWP | P | 7329121 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 03/29/2022 | 5TH FLOOR PLAN PAGE MH151 (BDA 575) / MH152 (BDA 579) : CORRIDOR SUPPLY, RETURN GRILLS AND REGISTERS OK / 6TH FLOOR PLAN PAGE MH161 (BDA 580) / MH162 (BDA 581) FINAL PENDING : PRESSURE SENSORS INSTALLED FOR ALL ISOLATION ROOMS. NEED PLAN SPLICE MATCHING THE INSTALL / NEED ALL REMOTE SMOKE INDICATORS / ALSO NEED ROOMS FROM COLUMN LINE (XD) TO THE EAST / NEED TEST AND BALANCE REPORT /
| LIDO | LIDO | | HD | P | 7318232 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 03/23/2022 | 5TH FLOOR PLAN PAGE MH-151 (BDA 575) : HOW IS RETURN AIR BEING ACHIEVED FOR ROOM # 5580 & 5581? SUPPLY, RETURN, EXHAUST, FLEX DUCT, DIFFUSERS AND GRILLS OK / 5TH FLOOR PLAN PAGE MH-152 (BDA 579) : SUPPLY, RETURN, EXHAUST, FLEX DUCT, DIFFUSERS AND GRILLS OK / | LIDO | LIDO | | HD | P | 7312428 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 03/15/2022 | ROOF PLAN PAGE MH 171 (BDA 540) :COOK EXHAUST FANS INSTALLED EQUIPMENT SCHEDULE M 300 (STAMPED 12/8/21) SHOWS GREENHECK. NEED REVISED AND APPROVED EQUIPMENT SCHEDULE OR ENGINEER APPROVED SUBMITAL / GEF-9 - APPROVED PLANS SHOW 26" EXHAUST DUCT. 18" INSTALLED. INSTALL PER PLAN./ GEF-11 - APPROVED PLANS SHOW 22" EXHAUST DUCT. 18" INSTALLED. INSTALL PER PLAN./ GEF-2, 4, 6, 9, 11 / ISO EF-2, 3 / EF-2-9 EXHAUST FAN OK /
| LIDO | LIDO | | HD | P | 7302577 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 03/08/2022 | 6TH FLOOR PLAN PAGE MH162 ( BDA 581) : PRESSURE SENSORS INSTALLED FOR ALL ISOLATION ROOMS. NEED PLAN SPLICE MATCHING THE INSTALL / | LIDO | LIDO | | HD | P | 7294375 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 03/07/2022 | 5TH FLOOR PLAN PAGE MH151 (BDA 575 ) : SUPPLY, RETURN, EXHAUST AIR FLEX DUCT, GRILL AND REGISTERS OK / PLAN PAGE MH152 (BDA 579 ) : SUPPLY, RETURN, EXHAUST AIR FLEX DUCT, GRILL AND REGISTERS OK / | LIDO | LIDO | | HD | P | 7293233 |
OTIS ELEVATOR COMPANY | HE= | P | 03/07/2022 | (ELEVATOR #12) - 1) NEED CORRECT AMOUNT OF SUSPENSION BELT SHACKLE NUTS AND COTTER PINS INSTALLED ON CAR AND COUNTERWEIGHT SIDE. 2) MISSING GUIDE RAIL FISH PLATE BOLTS AT BOTTOM COUNTERWEIGHT RAILS. 3) SECURE TOP OF CAR ESCAPE HATCH. 4) NEED CROSS HEAD IDENTIFICATION. 5) NEED NEW BELT AND GOVERNOR ROPE TAGS INSTALLED. 6) NEED CAR TOP LIGHT. 7) NEED FIRE ALARM DETECTION IN TOP OF SHAFT TO RECALL ELEVATOR TO DESIGNATED LEVEL W/ FLASHING HAT. 8) NEED FIRE SERVICE PHASE I AND II OPERATION CHECKED AT FINAL. 9) CHECK HALL CALL FIXTURES AT FINAL........ (ELEVATOR #13) - 1) MISSING COUNTERWEIGHT GUIDE RAIL FISH PLATE BOLTS AT 2ND FLOOR. 2) GOVERNOR MECHANICAL TRIPPING SPEED IN EXCESS OF ALLOWANCE (NEED TO REPAIR OR REPLACE GOVERNOR AND RETEST). 3) NEED CORRECT AMOUNT OF SUSPENSION BELT SHACKLE NUTS AND COTTER PINS INSTALLED ON CAR AND COUNTERWEIGHT SIDE. 4) NEED TO INSTALL NEW BELT AND GOVERNOR ROPE TAGS. 5) NEED CAR TOP LIGHT. 6) NEED FIRE ALARM DETECTION IN TOP OF SHAFT TO RECALL ELEVATOR TO DESIGNATED LEVEL W/ FLASHING HAT. 7) CHECK HALL CALL FIXTURES AT FINAL..... ELEVATORS OK FOR PUBLIC USE TO FLOORS WITHOUT CONSTRUCTION WORK BEING PERFORMED DUE TO LACK OF FIRE ALARM DEVICES INSTALLED. CONSTRUCTION FLOORS MAY ONLY BE ACCESSED BY AUTHORIZED PERSONNEL WITH ELEVATOR ATTENDANT OPERATION. | ROBERTV | ROBERTV | | HE= | P | 7294677 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 03/02/2022 | 6TH FLOOR PLAN PAGE MH 161 ( BDA 580) : ALL ROOM THERMOSTATS INSTALLED EXCEPT FOR ROOMS EAST OF COLUMN LINE (XD)/ | LIDO | LIDO | | HD | P | 7288090 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 03/01/2022 | 6th FLOOR PLAN PAGE MH 162 (BDA 581) : ROOM FINAL - ROOM # 6570, 6586, 6591 AND 6593 OK/ 6th FLOOR PLAN PAGE MH 161 (BDA 580) : ROOM FINAL - ROOM # 6574, 6576 AND 6580 OK
| LIDO | LIDO | | HD | P | 7286323 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 02/28/2022 | 6th FLOOR PLAN PAGE MH 162 (BDA 581) : ALL ISOLATION ROOMS FINAL PENDING ISOLATION ROOM PRESSURE SENSORS. ALL THERMOSTATS INSTALLED / | LIDO | LIDO | | HD | P | 7284846 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 02/22/2022 | 5TH FLOOR PLAN PAGE MH151 (BDA 575 ) : SUPPLY, RETURN, EXHAUST AIR FLEX DUCT, GRILL AND REGISTERS OK / PLAN PAGE MH152 (BDA 579 ) : 2 SHAFT DAMPERS COMPLETE / SUPPLY, RETURN, EXHAUST AIR FLEX DUCT, GRILL AND REGISTERS OK / | LIDO | LIDO | | HD | P | 7278512 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 02/08/2022 | 5TH FLOOR PLAN PAGE MH-151 (bda 575 / MH-152 (bda 579) : 6 - SMOKE DAMPERS COMPLETE / 14 - FIRE SMOKE AND FIRE DAMPER COMPLETE / | LIDO | LIDO | | HD | P | 7263892 |
OTIS ELEVATOR COMPANY | HE= | P | 02/07/2022 | (ELEVATORS #10 AND #11) - PERFORMED ACCEPTANCE TESTING ON BOTH ELEVATORS FOR ALTERED COMPONENTS. ELEVATOR #10 OK TO OPERATE FOR THE PUBLIC WITH THE EXCEPTION OF NO ACCESS 5TH AND 6TH FLOORS DUE TO LACK OF FIRE ALARM DEVICES AT THOSE FLOORS. ELEVATOR #11 OK TO ACCESS 5TH AND 6TH FLOOR WITH ATTENDANT.... BY FINAL ON CARS #10 AND #11 - NEED LEDGE PROTECTION ON OLD MACHINE BEAM POCKETS IN HOISTWAY. CLIP SHAFT LINER SCREWS PROTRUDING INTO HOISTWAY. NEED ALL HALL FIXTURES INSTALLED. NEED ALTERATION TAGS FOR CONTROLLERS. REPAIR ESCAPE HATCH HINGE ON #10. NEED TO DISCUSS FIRE ALARM DEVICE LOCATIONS WITH CSFD. NEED BUILDING INSPECTOR TO OK INTERIOR SHAFT AT NEW ENTRANCES. NEED ELECTRICAL INSPECTOR TO OK INTERIOR SHAFT NEW WORK..... NO INSPECTIONS HAVE BEEN PERFORMED ON ELEVATORS #12 AND #13 | ROBERTV | ROBERTV | | HE= | P | 7262363 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 02/07/2022 | 6TH FLOOR PLAN PAGE MH-161 (BDA 580) : FLEX DUCT / HARD DUCT CONNECTIONS TO SUPPLY, RETURN,EXHAUST GRILLS AND REGISTERS OK (grill and register installs also ok) / | LIDO | LIDO | | HD | P | 7261877 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 01/25/2022 | 6TH FLOOR PLAN PAGE MH-161 (BDA 580) : ON CALL AREA - ALL DUCT PENETRATIONS THROUGH THE FIRE PARTITIONS IN THIS AREA DONE PER KEY NOT 9 ARE OK / | LIDO | LIDO | | HD | P | 7249789 |
U.S. ENGINEERING CONSTRUCTION, LLC | HSP | P | 01/23/2022 | 6TH FLOOR PLAN PAGE MH161 ON CALL AREA DUCT PENETRATIONS THROUGH CORRIDOR WALLS EXCEPTION (1.) SEE KEY NOTE 9 : HILTI FIRE STOP UL SYSTEM W-L-7155 RECEIVED. SEE IMAGES. | LIDO | LIDO | | HSP | P | 7247198 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 01/11/2022 | 6TH FLOOR PLAN PAGE MH161 (bda 580) / MH162 ( bda 581) : SUPPLY, RETURN AND EXHAUST GRILLS AND REGISTERS OK / | LIDO | LIDO | | HD | P | 7235235 |
U.S. ENGINEERING CONSTRUCTION, LLC | HSP | P | 01/07/2022 | ENGINEER APPROVED SUBMITTAL FOR MANUFACTURER COOK EXHAUST FANS INSTALLED IN PLACE OF GREENHECK. SEE IMAGES. | LIDO | LIDO | | HSP | P | 7231672 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 01/05/2022 | ROOF PLAN PAGE MH 172 (BDA 541) : UPON REVIEW FCU 7-1 SUPPLY AND RETURN DUCT ARE PENETRATING A RATED WALL BETWEEN MECH ROOM # 7101 AND VESTIBULE ROOM # 7100. HOW ARE THESE PENETRATIONS BEING PROTECTED? ENGINEER TO ADDRESS. | LIDO | LIDO | | HD | P | 7228810 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 01/04/2022 | ROOF PLAN PAGE MH 172 (BDA 541) : NEED TO RESEARCH FCU 7-1 SUPPLY AND RETURN DUCT PENETRATING A WALL THAT MAY BE RATED BETWEEN MECH ROOM # 7101 AND VESTIBULE ROOM # 7100 . WILL UPDATE NOTES AFTER RESEARCH / ISOEF-1, 4A, 4B/5A, DEF-1, EF-1-1, GEF-1, 3, 5, 8 AND 10 . NEED TO RESEARCH EXHAUST TERMINATIONS. COOK EXHAUST FANS ON ROOF, MECHANICAL SCHEDULE SHOWS GREENHECK. NEED REVISED AND APPROVED MECHANICAL SCHEDULE OR ENGINEER APPROVED SUBMITTAL / EXHAUST DUCT FROM SHAFT TO EXHAUST FANS OK / 6TH FLOOR PLAN PAGE MH 162 (BDA581) : SUPPLY AND EXHAUST GRILLS AND REGISTERS OK. SEE HIGHLIGHTED PLANS IN OFFICE FOR REFERENCE / | LIDO | LIDO | | HD | P | 7228466 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 01/03/2022 | 4TH FLOOR PLAN PAGE MH - 142 (BDA 485) : RTU-15 / RTU- 14 - RETURN AIR DUCT ROUGH AND FINAL DUCT CONNECTIONS TO THE UNITS OK. OK TO INSULATE / ROOM 4507 - MISSING DUCT SMOKE DETECTOR (see note #9). SPF-1, DAMPER AND DUCT ROUGH OK./ 5TH FLOOR PLAN PAGE MH-151 / MH-152 : ADDED VAV-14-645 / VAV-14-646 AND DUCT ROUGH OK. OK TO INSULATE / 6TH FLOOR PLAN PAGE MH-161 / MH-162 : ADDED VAV-15-648 / VAV-15-647 / VAV-15- 645 AND DUCT ROUGH OK. OK TO INSULATE / ROOM # 6566 - 1 DAMPER COMPLETE /
| LIDO | LIDO | | HD | P | 7227018 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 12/21/2021 | 6TH FLOOR PLAN PAGE MH161 ON CALL AREA DUCT PENETRATIONS THROUGH CORRIDOR WALLS EXCEPTION (1.) SEE KEY NOTE 9 : FIRE STOP W-L-7060 FROM APPROVED PLANS SHOWS SpecSeal LCI SEALANT TO BE USED. CONTRACTOR USED HILTI FS1 MAX. THE SEALANT SHOWN ON THE APPROVED FIRE STOP DETAIL MUST BE USED.
| LIDO | LIDO | | HD | P | 7217682 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 12/21/2021 | 6TH FLOOR PLAN PAGE MH161 ON CALL AREA DUCT PENETRATIONS THROUGH WALL OTHER THAN CORRIDOR WALL EXCEPTION (3.) SEE KEY NOTE 9 : ANGLES FOR WEST DUCT PENETRATION THROUGH WALL BETWEEN ROOM 6565T AND 6565 ARE LESS THAN THE CODE REQUIRED 1.5" / 6 - DUCT PENETRATIONS OK .
| LIDO | LIDO | | HD | P | 7217538 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 12/16/2021 | 150 LB TEST FOR HWS, HWR / CHWS, CHWR PIPE INSTALL FROM 4TH FLOOR UP TO ROOF PENTHOUSE OK. INSTALL OK, OK TO INSULATE AND LABEL / 4TH FLOOR PLAN PAGE MP 141 / MP142 (BDA 118 / BDA 119) : HWS, HWR / CHWS, CHWR PIPE INSTALL AND CONNECTIONS TO EXISTING PIPE OK. OK TO INSULATE AND LABEL/ | LIDO | LIDO | | HWP | P | 7211809 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 12/13/2021 | 5TH FLOOR PLAN PAGE MH-151 ( BDA 569) : 1 DAMPER COMPLETE / 5 VAV'S OK / PARTIAL SUPPLY, RETURN AND EXHAUST DUCT ROUGH OK. OK TO INSULATE / | LIDO | LIDO | | HD | P | 7207155 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 12/08/2021 | 6TH FLOOR PLAN PAGE MH 161 ( BDA 559) : SLEEP ROOMS - 1 ADDED FIRE DAMPER FRAME OK . NEED REVISED AND APPROVED PLANS ./ 2 - DAMPERS COMPLETE / 5TH FLOOR PLAN PAGE MH151 ( BDA 569) : 8 VAV'S OK / PARTIAL MEDIUM / LOW PRESSURE SUPPLY DUCT ROUGH OK. OK TO INSULATE / PARTIAL EXHAUST AND RETURN DUCT ROUGH OK . OK TO INSULATE / | LIDO | LIDO | | HD | P | 7202505 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/18/2021 | 5TH FLOOR PLAN PAGE MH152 ( BDA 570) : 4 - VAV'S OK / PARTIAL DUCT ROUGH - SUPPLY, RETURN AND EXHAUST DUCT ROUGH OK. OK TO INSULATE. SEE HIGHLIGHTED PLANS IN OFFICE FOR REFERENCE / | LIDO | LIDO | | HD | P | 7182687 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/17/2021 | 5TH FLOOR PLAN PAGE MH152 (BDA 570 / SPLICE DATED 11/2/21) DUCT ROUGH: 5 VAV'S OK / MEDIUM PRESSURE SUPPLY MAIN TRUNK LINE DUCT ROUGH OK, RETURN AIR MAIN TRUNK LINE OK AND EXHAUST DUCT ROUGH OK OK TO INSULATE /
| LIDO | LIDO | | HD | P | 7181150 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/05/2021 | 5TH FLOOR PLAN PAGE MH 152 : 2 SHAFT DAMPER FRAMES OK. SEE HIGHLIGHTED PLANS ON OFFICE FOR REFERENCE / | LIDO | LIDO | | HD | P | 7167222 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/04/2021 | 5TH FLOOR SOUTH PLAN PAGE MH151 ( 822) : 5 - VAN'S OK / PARTIAL SUPPLY, RETURN AND EXHAUST DUCT ROUGH OK. OK TO INSULATE / SEE HIGHLIGHTED PLAN IN OFFICE FOR REFERENCE ./ | LIDO | LIDO | | HD | P | 7165839 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/03/2021 | 5TH FLOOR PLAN PAGE MH152 ( BDA 823) : ROOM # 55876 - HOW IS THE 10" DUCT PENETRATION THROUGH THE RATED WALL BEING PROTECTED? ENGINEER TO ADDRESS. / 1 - DAMPER FRAME OK / 1- DAMPER COMPLETE / 5 VAV BOX'S OK / PARTIAL SUPPLY, RETURN AND EXHAUSTR DUCT ROUGH OK. OK TO INSULATE / 5TH FLOOR PLAN PAGE MH151 ( BDA 822) : 1 -SHAFT DAMPER FRAME OK / 1 - DAMPER FRAME OK / SEE HIGHLIGHTED PLANS IN OFFICE FOR REFERENCE./ | LIDO | LIDO | | HD | P | 7164499 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/03/2021 | 6TH FLOOR PLAN PAGE MH-162 : COMMUNICATED THE FOLLOWING WITH MECHANICAL CONTRACTOR ( Jeremy H). MULTIPLE AREAS NOT INSTALLED PER PLAN. STILL NEED REVISED AND APPROVED PLAN SPICE FOR CHANGES MADE TO DUCT DESIGN AND CHANGES MADE FOR FIRE DAMPERS ELIMINATED, ADDED AND LOCATIONS CHANGED. ENGINEER TO ADDRESS.
| LIDO | LIDO | | HD | P | 7165336 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/02/2021 | 5TH FLOOR PLAN PAGE MH152 (BDA 823) : 2- DAMPER FRAMES OK / PARTIAL SUPPLY. RETURN AND EXHAUST DUCT ROUGH OK. OK TO WRAP./ 1 VAV OK / 1- SMOKE DAMPER OK / 5TH FLOOR PLAN PAGE MH-152 ( BDA 822 : PARTIAL SUPPLY. RETURN AND EXHAUST DUCT ROUGH OK. OK TO WRAP./
| LIDO | LIDO | | HD | P | 7163061 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/01/2021 | ON SITE MEETING WITH MECHANICAL CONTRACTOR ( Jeremy H) AND GENERAL CONTRACTOR (Kellen S) PERTAINING TO THE FOLLOWING : 6TH FLOOR PLAN PAGE MH161 SPLICE DATED 9/8/21 ON-CALL AREA : 1HR FIRE PARTITION WALLS SHOWING KEY NOTE #9, EXCEPTION #3 WAS NOT USED FOR DUCT PENETRATIONS THROUGH WALLS OTHER THAN CORRIDOR WALLS. CONTRACTOR TO USE THE CORRECT CODE EXCEPTION SHOWN ON THE APPROVED PLANS. SEE 2015 IBC CODE SECTION 717.5.4 EXCEPTION (3). THIS CODE SECTION IS SHOWN ON THE PLAN SPLICE (dated 9/8/21) PAGE MH161. THE CORRIDOR WALL DUCT PENETRATION FIRE STOP DETAIL SUBMITTED TO PLAN REVIEW ON 9/8/21 FOR CORRIDOR WALL WAS NOT CORRECTLY LABELED AND WAS AN OUTDATED VERSION OF THE DETAIL. DETAIL MUST SHOW THE UL TEST NUMBER REQUIRED BY 2015 IBC CODE SECTION 714. SEE 717.5.4 EXCEPTION 1. THIS CODE DIRECTS YOU TO CODE SECTION 714 . OK FOR THE ENGINEER TO SUBMIT THE CORRECT RATED CORRIDOR WALL PENETRATION PROTECTION DETAILS TO THE MECHANICAL INSPECTOR TO BE REVIEWED FOR APPROVAL. THE DETAILS MUST BE LABELED CORRECT.
| LIDO | LIDO | | HD | P | 7161500 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/01/2021 | 6TH FLOOR PLAN PAGE MH161 SPLICE DATED 9/8/21 ON-CALL AREA : HAD PHONE CONVERSATION WITH MECHANICAL CONTRACTOR (Jeremy) PERTAINING TO THE FOLLOWING . AFTER FURTHER REVIEW WITH SENIOR MECHANICAL INSPECTOR AND BUILDING INSPECTOR. 1HR FIRE PARTITION WALLS SHOWING KEY NOTE #9, EXCEPTION #3 WAS NOT USED FOR DUCT PENETRATIONS THROUGH WALLS OTHER THAN CORRIDOR WALLS. CONTRACTOR MUST USE THE CORRECT CODE EXCEPTION SHOWN ON THE APPROVED PLANS. SEE 2015 IBC CODE SECTION 717.5.4 EXCEPTION (3). THIS CODE SECTION IS SHOWN ON THE PLAN SPLICE (dated 9/8/21) PAGE MH161. THE PENETRATION DETAILS SUBMITTED TO PLAN REVIEW ON 9/8/21 ARE NOT CORRECT. THE ENGINEER MUST REVIEW AND SUBMIT THE CORRECT WALL PENETRATION PROTECTION DETAILS TO PLAN REVIEW FOR APPROVAL AND TO BE SCANNED ONTO THE PLANS. DETAILS MUST BE LABELED CORRECT.
| LIDO | LIDO | | HD | P | 7160757 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 10/28/2021 | 6TH FLOOR PLAN PAGE MH161 (BDA 559) : 3 VAV'S OK / PARTIAL SUPPLY, RETURN AND EXHAUST DUCT ROUGH OK /
| LIDO | LIDO | | HD | P | 7158924 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 10/28/2021 | CONTINUATION OF TODAY'S INSPECTION NOTES / 6TH FLOOR PLAN PAGE MH161 SPLICE DATED 10/6/21 (on call area) : NEED TO CONSULT WITH BUILDING INSPECTOR ON PENETRATIONS THROUGH RATED WALLS / | LIDO | LIDO | | HD | P | 7159444 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 10/27/2021 | 5TH FLOOR PLAN PAGE MH152 ( BDA 823) : 2 SHAFT FIRE / SMOKE DAMPER FRAMES OK / | LIDO | LIDO | | HD | P | 7156937 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 10/25/2021 | 5TH FLOOR PLAN PAGE MP 151 (BDA822) DUCT ROUGH : 3 - VAV'S OK. / PARTIAL S/A MEDIUM PRESSURE, S/A LOW PRESSURE. RETURN AND EXHAUST DUCT ROUGH OK. OK TO INSULATE/ 5TH FLOOR PLAN PAGE MP 152 (BDA823) DUCT ROUGH : 5 - VAV'S OK / PARTIAL S/A MEDIUM PRESSURE, S/A LOW PRESSURE. RETURN AND EXHAUST DUCT ROUGH OK. OK TO INSULATE/ SEE HIGH LIGHTED PLAN IN OFFICE FOR REFERENCE/
| LIDO | LIDO | | HD | P | 7153567 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 10/20/2021 | 5TH FLOOR PLAN PAGE MH-151 ( BDA 822) : 2 DAMPER FRAMES OK / PARTIAL MEDIUM PRESSURE DUCT ROUGH DOWN CORRIDOR OK. OK TO INSULATE / 5TH FLOOR PLAN PAGE MH-152 ( BDA 823) : 1 - DAMPER FRAMES OK / 1 - SMOKE DAMPER OK / PARTIAL MEDIUM PRESSURE DUCT ROUGH DOWN CORRIDOR OK. OK TO INSULATE / | LIDO | LIDO | | HD | P | 7149031 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 10/18/2021 | 5TH FLOOR PLAN PAGE MH151 ( BDA 448) : THE FOLLOWING WAS NOT INSTALLED PER THE APPROVED PLANS. NEED REVISED AND APPROVED PLANS. 1 ADDED SUPPLY FIRE DAMPER FRAME OK./ 6TH FLOOR PLAN PAGE MH162 ( BDA 451) : 2 - DAMPERS COMPLETE . 1 - SMOKE DAMPER COMPLETE. / 6TH FLOOR PLAN PAGE MH161 ( BDA 559) : 4 - DAMPERS COMPLETE . 2 - SMOKE DAMPER COMPLETE. PARTIAL EXHAUST AND RETURN DUCT ROUGH OK./
| LIDO | LIDO | | HD | P | 7145400 |
OTIS ELEVATOR COMPANY | HER | C | 10/08/2021 | ELEVATOR ROUGH INSPECTION | ERIC | ERIC | | HER | C | 7135642 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 10/06/2021 | 6TH FLOOR PLAN PAGE MH161 ( BDA 450) : VAV-15-625 AND LOW PRESSURE DUCT WAS NOT INSTALLED PER PLAN. VAV-15-625 WAS MOVED FROM CORRIDOR 6513 TO STAFF LOCKER ROOM # 6576 AND DUCT WAS REROUTED. INSTALL WAS DONE PER PLANS ON SITE. NEED REVISED AND APPROVED PLANS AS SOON AS POSSIBLE../ PARTIAL MEDIUM PRESSURE SUPPLY DUCT, SUPPLY LOW PRESSURE DUCT, RETURN AND EXHAUST AIR DUCT ROUGH OK. OK TO INSULATE./ 5 -DAMPERS COMPLETE ./ | LIDO | LIDO | | HD | P | 7132575 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 10/05/2021 | 5TH FLOOR PLAN PAGE MH151 ( BDA 448) : TWO DAMPER FRAMES OK / PLAN PAGE MH152 ( BDA 449) : THREE DAMPER FRAMES OK / 6TH FLOOR PLAN PAGE MH161 ( BDA 450) : SUPPLY AND RETURN DUCT ROUGH OK. OK TO INSULATE . / AREA'S INSPECTED TODAY ARE HIGHLIGHTED IN PURPLE ON SITE PLAN /
| LIDO | LIDO | | HD | P | 7131070 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 09/28/2021 | 6TH FLOOR PLAN PAGE MH161 ( BDA 825) : 1- SHAFT DAMPER COMPLETE / 2- SMOKE DAMPERS COMPLETE / 9 VAV'S, SUPPLY LOW PRESSURE DUCT AND LATERAL RUN OUTS OK. OK TO WRAP / MEDIUM PRESSURE MAIN TRUNK LINE AND INLET CONNECTIONS TO THE 9 VAV BOXERS OK. OK TO WRAP/ RETURN AIR MAIN TRUNK LINE AND LATERAL RUN OUTS OK. OK TO WRAP./ EXHAUST AIR MAIN TRUNK LINE AND LATERAL RUN OUTS OK ./
| LIDO | LIDO | | HD | P | 7122645 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 09/21/2021 | 6TH FLOOR PLAN PAGE MH-162 ( BDA 451) : 3- SHAFT DAMPERS COMPLETE/ 1- VAV OK / PARTIAL SUPPLY, RETURN AND EXHAUST DUCT ROUGH OK / | LIDO | LIDO | | HD | P | 7114621 |
U.S. ENGINEERING CONSTRUCTION, LLC | HSP | P | 09/19/2021 | Stamped engineer letter received approving the following. See images. 6TH FLOOR PLAN 14" ROUND MEDIUM PRESSURE DUCT THAT SERVES VAV 15-612, 15-613, 15-617 AND 15-618 CHANGED TO 14"X14" . | LIDO | LIDO | | HSP | P | 7112035 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 09/15/2021 | 6TH FLOOR MH162 (BDA 451) : 13 - DAMPERS COMPLETE / 3 -VAV BOXES AND LOW PRESSURE DUCT OK. OK TO WRAP DUCT/ SUPPLY, RETURN AND EXHAUST PARTIAL DUCT ROUGH OK. OK TO WRAP./ | LIDO | LIDO | | HD | P | 7108317 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 09/14/2021 | 6TH FLOOR PLAN PAGE MH161 ( BDA 450) : 1 - DAMPER FRAME OK / 5 - VAV'S AND LOW PRESSURE DUCT ROUGH OK. OK TO INSULATE / DUCT ROUGH - SUPPLY. RETURN AND EXHAUST DUCT MAIN TRUNK LINES AND LATERAL RUN OUTS OK. OK TO WRAP
| LIDO | LIDO | | HD | P | 7107051 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 09/09/2021 | 6TH FLOOR MH-161 ( BDA 450) : 3 - DAMPER FRAMES OK / 1 VAV BOX AND LOW PRESSURE DUCT ROUGH OK . OK TO WRAP / 6TH FLOOR MH-162 ( BDA 451) : 2 - DAMPERS COMPLETE / PARTIAL DUCT ROUGH OK. OK TO WRAP / | LIDO | LIDO | | HD | P | 7101955 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 09/07/2021 | 6TH FLOOR PLAN PAGE MH-161 (BDA 450) / PLAN PAGE MH-162 (BDA 450) DUCT ROUGH : 14" ROUND MEDIUM PRESSURE DUCT THAT SERVES VAV 15-613, 15-617 AND 15-618 WAS CHANGED TO 14"X14" . NEED REVISED AND APPROVED PLANS OR ENGINEER LETTER APPROVING THE 14"X14" M/P DUCT INSTALLED/ SUPPLY, RETURN AND EXHAUST MAIN TRUNK LINES AND LATERAL RUN OUTS OK. OK TO WRAP . 5 VAV BOXES AND LOW PRESSURE DUCT ROUGH OK. OK TO INSULATE / 6TH FLOOR PLAN PAGE MH-161 (BDA 450) DAMPER FRAME : 3 DAMPER FRAMES OK /
| LIDO | LIDO | | HD | P | 7099016 |
U.S. ENGINEERING CONSTRUCTION, LLC | HSP | P | 08/30/2021 | 6TH FLOOR PLAN PAGE MH162 ( BDA 451) : STAMPED ENGINEER LETTER RECEIVED TAKING NO EXCEPTION TO ALL 11" X 11" EXHAUST DUCT BRANCH LINES SHOWN ON PLANS CHANGED TO 12" ROUND. SEE IMAGES. | LIDO | LIDO | | HSP | P | 7090995 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 08/30/2021 | 6TH FLOOR DUCT ROUGH : PLAN PAGE MH162 ( BDA 451) - PARTIAL EXHAUST DUCT ROUGH OK / 6TH FLOOR DAMPER FRAME: PLAN PAGE MH162 ( BDA 450) - 1 DAMPER FRAME OK ./ | LIDO | LIDO | | HD | P | 7090253 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 08/25/2021 | 6TH FLOOR PLAN PAGE MH162 ( BDA 451) : ROOM # 6526, 6528, 6530 AND 6532 - PLAN SHOW 11" X 11" EXHAUST DUCT, 12" ROUND INSTALLED. INSTALL PER PLAN. / 1 - SHAFT DAMPER COMPLETE / 3- DAMPER FRAMES OK / 5 VAV BOXES AND LOW PRESSURE DUCT ROUGH OK. OK TO WRAP./ PARTIAL RETURN AND EXHAUST AIR MAIN TRUNK LINE AND LATERAL RUN OUTS OK, OK TO WRAP./
| LIDO | LIDO | | HD | P | 7085210 |
OLSON PLUMBING & HEATING COMPANY | HSP | P | 08/25/2021 | 5TH FLOOR PLAN PAGE MP151 (BDA120) / MP152 (BDA121) : STAMPED ENGINEER LETTER RECEIVED FOR HEAT WATER SUPPLY BRANCH LINES FOR VAV 14-542 AND VAV 14-516 BRANCHED OF THE 1.5" HWS INSTEAD OF THE 2" HWS . SEE IMAGES | LIDO | LIDO | | HSP | P | 7083929 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 08/24/2021 | 6TH FLOOR PLAN PAGE MH 162 ( BDA 451) : NEED REVISED AND APPROVED PLANS FOR THE FOLLOWING - MEDIUM PRESSURE MAIN TRUNK LINE DUCT CHANGES IN WEST AND NORTH CORRIDOR, ADDED FIRE DAMPERS IN ROOM # 6592 AND 6588. / 7 - DAMPER FRAMES OK / 7 - VAV'S INCLUDING LOW PRESSURE DUCT ROUGH OK, OK TO WRAP./ MEDIUM PRESSURE AND RETURN AIR MAIN TRUNK LINE DUCT ROUGH OK, OK TO WRAP ./ | LIDO | LIDO | | HD | P | 7083559 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 08/18/2021 | 6TH FLOOR PLAN PAGE MH161 ( BDA 450) / MH 162 ( BDA 451) DAMPER FRAME INSPECTION : VAV-15-611 - FIRE DAMPER MOVED FROM RATED WALL AT PHY DOC ROOM # 6590 TO CORRIDOR WALL. NEED REVISED AND APPROVED PLANS ./ 6 DAMPER FRAMES OK./
| LIDO | LIDO | | HD | P | 7077172 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 08/16/2021 | 6TH FLOOR PLAN PAGE MH-162 ( BDA 451) : 4 SHAFT DAMPER FRAMES OK / | LIDO | LIDO | | HD | P | 7073698 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 08/11/2021 | 6TH FLOOR PLAN PAGE MH162 ( BDA 451) : CLEAN SUPPLY ROOM # 6587 - PER CONVERSATION WITH CONTRACTOR AND THERE SHOP (cad) PLANS, 1 FIRE DAMPER IS BEING ELIMINATED AND 8" LOW PRESSURE SUPPLY DUCT ROUTING CHANGED. NEED REVISED AND APPROVED PLANS./ FIRE DAMPER FRAME INSPECTION : TWO FIRE DAMPER FRAMES OK ./ | LIDO | LIDO | | HD | P | 7068397 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 08/05/2021 | 5TH FLOOR PLAN PAGE MP151 (BDA120) / MP152 (BDA121) HEAT WATER SUPPLY AND RETURN MAIN LINES : 125LB TEST OK / HWS AND HWR INSTALLED PER PLAN EXCEPT FOR SUPPLY BRANCH LINES FOR VAV 14-542 AND VAV 14-516 ARE BRANCHED OF THE 1.5" HWS INSTEAD OF THE 2" HWS SHOWN ON THE PLANS. INSTALL PER PLAN./ | LIDO | LIDO | | HWP | P | 7062055 |
OLSON PLUMBING & HEATING COMPANY | HSP | P | 07/27/2021 | 6TH FLOOR PLAN PAGE MP161 / MP162 : STAMPED ENGINEER LETTER RECEIVED TAKING NO EXCEPTION TO THE HEAT WATER SUPPLY AND RETURN MAIN PIPE SIZE INSTALLED DIFFERENT THAN WHAT IS SHOWN ON THE PLANS. SEE IMAGES.
| LIDO | LIDO | | HSP | P | 7049791 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 07/14/2021 | 6TH FLOOR PLAN PAGE MP.161 ( BDA122) / MP.162 ( BDA 123) : HEAT WATER SUPPLY AND RETURN PIPING MAINS - HWS PIPING WAS REDUCES FROM 2" TO 1-1/2" AT COLUMN LINE 5, PLANS SHOW PIPE TO REDUCE AT COLUMN LINE 8. INSTALL PER PLAN. ALSO HWP 1-1/2" PIPING WAS REDUCED FROM 1-1/2" TO 1-1/4" AT COLUMN LINE 10, PLANS SHOW REDUCTION TO BE AT COLUMN LINE 13. INSTALL PER PLAN. HWP 1-1/4" WAS REDUCED TO 1" BEFORE VAV -15 -635, PLANS SHOW REDUCTION TO BE AFTER VAV. INSTALL PER PLAN . 100 LB TEST OK / | LIDO | LIDO | | HWP | P | 7035986 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 07/14/2021 | 5th FLOOR NORTH AND SOUTH SHAFT PLAN PAGE M.152 ( BDA 449 ) / M.151 ( BDA 448) ; SOUTH SHAFT - 1 DAMPER BREAK AWAY CONNECTION IN SHAFT ONLY OK / NORTH SHAFT - 4 DAMPER BREAK AWAY CONNECTIONS IN SHAFT ONLY OK/ | LIDO | LIDO | | HD | P | 7035963 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 06/30/2021 | 4TH FLOOR PLAN PAGE MH142 ( BDA111) : STAIRWELL MECH / ROOM 4508 - SPF-2 FAN AND DUCT ROUGH STUBBED THROUGH WALL OK, OK TO WRAP. MOTORIZED DAMPER OK ./ STILL NEED DUCT SMOKE DETECTOR. SEE NOTE 14./ | LIDO | LIDO | | HD | P | 7020727 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 06/17/2021 | NORTH SHAFT 4TH FLOOR UP TO 7TH FLOOR ( ROOF) PLAN PAGE MP162 (123) / MP152 ( 121) / MP 142 (BDA 119) : 100LB TEST FOR CHILLED WATER SUPPLY AND RETURN OK. PIPE INSTALLED PER PLAN. OK TO INSULATE ./ 150LB TEST FOR HEAT WATER SUPPLY AND RETURN OK. PIPE INSTALLED PER PLAN. OK TO INSULATE. / SOUTH SHAFT 5TH FLOOR FUTURE TO 6TH FLOOR PLAN PAGE MP161 (BDA 122) / MP151 ( BDA 120) : 150LB TEST FOR HEAT WATER SUPPLY AND RETURN OK. PIPE INSTALLED PER PLAN. OK TO INSULATE./ | LIDO | LIDO | | HWP | P | 7006489 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 06/14/2021 | PLAN PAGE MH142 ( BDA111) : RTU-14 /15 - RETURN AIR DUCT ROUGH OK. OK TO WRAP./ HUMIDIFIER H-4-14 OK./ | LIDO | LIDO | | HD | P | 7001883 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 06/01/2021 | 4TH FLOOR PLAN PAGE M141 (BDA 110) / M142 (BDA 111) - ROOM # 4507 / 4508 PLENUM AND LOUVER OK. / 6TH FLOOR SOUTH SHAFT PLAN PAGE MH 161 (BDA 450) - ONE FIRE SMOKE DAMPER BREAKAWAY CONNECTION IN SHAFT ONLY OK./ 6TH FLOOR NORTH SHAFT PLAN PAGE MH 162 (BDA 451)- FOUR FIRE SMOKE DAMPER BREAKAWAY CONNECTIONS IN SHAFT ONLY OK./ | LIDO | LIDO | | HD | P | 6987086 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 05/18/2021 | MH171 AND MH172 (BDA 490 AND 826) EXHAUST DUCTS FROM ELBOWS TO OUTSIDE SHAFT OK. | DUSTINS | DUSTINS | | HD | P | 6973102 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 05/12/2021 | 6TH FLOOR PLAN PAGE MH 162 ( BDA 451) : 2 DAMPER FRAMES OK ./ | LIDO | LIDO | | HD | P | 6966425 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 05/10/2021 | 4TH FLOOR MECHANICAL ROOM PLAN PAGE MH142 ( BDA 111) : AHU-14 / AHU-15 - SUPPLY DUCT CONNECTIONS TO UNITS OK. PARTIAL RETURN AIR DUCT ROUGH OK. OK TO WRAP. SUPPLY DUCT CONNECTIONS TO EXISTING DUCT AT SHAFT OK . OK TO WRAP. 5TH FLOOR SOUTH SHAFT PLAN PAGE MH151 (BDA 448) / 6TH FLOOR SOUTH SHAFT PLAN PAGE MH161 (BDA 450 ) - ALL EXHAUST DUCT INSTALLED IN SHAFT OK . 5TH FLOOR NORTH SHAFT PLAN PAGE MH152 (BDA 449) / 6TH FLOOR SOUTH SHAFT PLAN PAGE MH162 (BDA 451 ) - 2 SUPPLY DUCTS AND 2- RETURN AIR DUCTS OK. OK TO WRAP . 8 - EXHAUST DUCTS OK
| LIDO | LIDO | | HD | P | 6963672 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 04/05/2021 | 4TH FLOOR RTU 14 / RTU 15 DUCT ROUGH : SUPPLY AND RETURN DUCT STARTING 10 FEET INSTALLED FROM UNIT TO 10 FEET BEFORE SHAFT OK. OK TO INSULATE ( still need tie-in for rtu's and duct outside of shaft ) / OUTSIDE AIR DUCT FROM PLENUM TO RTU UNITS COMPLETE . OK TO INSULATE / | LIDO | LIDO | | HD | P | 6922306 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 05/31/2022 | 5th and 6th floor ok | JOSEPHD | JOSEPHD | | P= | C | 7394256 |
OLSON PLUMBING & HEATING COMPANY | PTO | C | 05/31/2022 | splices done | JOSEPHD | JOSEPHD | | PTO | C | 7394250 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 05/26/2022 | 5th floor only, rooms 4,6,8,12,14,18,52-60 ok | JOSEPHD | JOSEPHD | | P= | P | 7391171 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 05/24/2022 | for 5th floor only, room 26 leak at hand sink, rooms 20-24,28-42 ok | JOSEPHD | JOSEPHD | | P= | P | 7387657 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 05/19/2022 | hand spray in room 6565 not in accessible location, rest of 6th floor ok | JOSEPHD | JOSEPHD | | P= | P | 7382594 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 05/17/2022 | 6th floor center area ok | JOSEPHD | JOSEPHD | | P= | P | 7379424 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 05/11/2022 | rooms 6530,6534,6536,6538,6540,6542,6546,6548,6550,6552 ok | JOSEPHD | JOSEPHD | | P= | P | 7372179 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 05/04/2022 | 6562 lacking knee protection, rooms 6502-6512 ok, rooms 6554-6560 ok | JOSEPHD | JOSEPHD | | P= | P | 7364135 |
OLSON PLUMBING & HEATING COMPANY | P= | L | 04/28/2022 | call ahead completed at 1:01 pm, arrived at 1:34 contractor phone going to voice mail, will have to reschedule when someone can meet inspector | JOSEPHD | JOSEPHD | | P= | L | 7356295 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 04/19/2022 | 6th floor units 6532, 6515 ok | JOSEPHD | JOSEPHD | | P= | P | 7343824 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 04/12/2022 | 6TH FLOOR -- ROOMS 6522, 6520, 6518 AND 6516 OK PENDING LAV SIDE CLEARANCE ISSUE IN 6516 | LEE | LEE | | P= | P | 7336014 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 04/07/2022 | rooms 6528,6530,6534,6536,6538,6540 ok | JOSEPHD | JOSEPHD | | P= | P | 7330449 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/26/2022 | 5TH FLOOR -- ROOMS # 5510, 5512 ALL DWV ONLY OK THIS INSPECTION, LEAK AND HANGERS PREVIOUSLY NOTED OK TOO | LEE | LEE | | PTO | P | 7250749 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/25/2022 | ROOM # 5565 IN WALL H20 ONLY OK -- ROOMS # 5502, 5504, 5506, 5508 AND 5567 IN WALL DWV OK, LEAK ON 2" SWEEP BELOW FLOOR AND MISSING TWO HANGERS ( ONE ON W/C AND OTHER ON 3" STACK ) | LEE | LEE | | PTO | P | 7249614 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/24/2022 | 5TH FLOOR -- ROOMS # 5573, 5575, 5577 AND 5578 DWV IN WALLS ONLY OK -- GRADE ISSUES BELOW 4TH FLOOR CEILING | LEE | LEE | | PTO | P | 7247882 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/20/2022 | 5TH FLOOR -- ROOMS # 5567, 5502, 5504, 5506, 5508, 5510 AND 5512 IN WALL DOMESTIC H20 ONLY | LEE | LEE | | PTO | P | 7244832 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/13/2022 | 5TH FLOOR DWV ONLY ROOMS # 5536 ( D.I. BOXES ) AND 5542 OK | LEE | LEE | | PTO | P | 7238404 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/12/2022 | 5TH FLOOR -- ROOMS # 5538, 5540 DWV IN WALL / DOWN TO 4TH FLOOR OK-- D-I BOXES OK -- ((( STACK VENT # 5548 OK PENDING SPLICED INTO PLANS ))) | LEE | LEE | | PTO | P | 7236680 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/11/2022 | 5TH FLOOR -- IN WALL H20 ONLY ROOMS # 5575 AND 5513A | LEE | LEE | | PTO | P | 7235020 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/10/2022 | 5TH FLOOR -- ROOMS # 5576, 5577, 5578 AND 5573 IN WALL DOMESTIC H20 OK | LEE | LEE | | PTO | P | 7233532 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/06/2022 | 5TH FLOOR -- IN WALL AND DOWN TO 4TH DWV OK # 5556 AND 5558 -- DWV IN WALL ONLY # 5560, TWO TRAPS ON SINGLE TRAP ARM BELOW FLOOR # 5560 -- IN WALL DOMESTIC H20 # 5584 AND NOURISH SINK # 5533A OK | LEE | LEE | | PTO | P | 7230944 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 01/05/2022 | 5TH FLOOR -- # 5560 IN WALL DOMESTIC H20 ONLY OK -- # 5534, 5536, 5538, 5540 AND 5542 IN WALL DOMESTIC H20 ONLY -- # 5548 AND 5550 OK 5TH FLOOR BUT LEAKING ON 4TH FLOOR, ALSO WASTE STACK AND VENT STACK ARE CONNECTED 4TH FLOOR CEILING -- STACK VENT NOT PIPED TO CODE AT 5548 LAVS / FLOOR SINKS -- ((( NEED PLANS REVISED TO SHOW FLOOR SINKS IN PRE ACTION CLOSETS WITH ENGINEERS APPROVAL FOR STACK VENTING LAVS WITH FLOOR SINKS ))) | LEE | LEE | | PTO | P | 7229518 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/29/2021 | 5TH FLOOR -- ROOMS # 5552 AND 5554 DWV OK UP TO 6TH AND DOWN TO 4TH FLOOR TIE-IN | LEE | LEE | | PTO | P | 7223667 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/28/2021 | 5TH FLOOR -- DWV AND H20 IN WALL ROOMS # 5544, 5546 AND EVS 5592 DOWN TO 4TH FLOOR TIE-IN -- H20 IN WALL ONLY ROOMS # 5548, 5550, 5552, 5554, 5556, 5558 | LEE | LEE | | PTO | P | 7221689 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/23/2021 | dwv only correction made at column X7 room 5532 | JOSEPHD | JOSEPHD | | PTO | P | 7219688 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/22/2021 | dwv only, 5th floor rooms 6534,6536,6594 ok | JOSEPHD | JOSEPHD | | PTO | P | 7218093 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/21/2021 | shower at column X7 5th floor s-trapped and not vented to code, rest of bathroom group column X7 5th & 6th floor ok, | JOSEPHD | JOSEPHD | | PTO | P | 7216178 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/20/2021 | DWV the following rooms 5528 and 5530: Need under floor rest ok. | DANR | DANR | | PTO | P | 7214918 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/17/2021 | 5TH FLOOR -- ROOMS # 5524, 5526 DWV DOWN TO 4TH OK -- ALL OVERHEAD H20 5TH FLOOR OK -- ((( NEED PLANS REVISED TO SHOW RE-CIRC PIPING CHANGES ON BOTH FLOORS ))) | LEE | LEE | | PTO | P | 7213240 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/16/2021 | 5TH FLOOR -- # 5514 IN WALL H20 ONLY OK -- 5520 AND 5522 DWV ONLY UP TO SHOWERS AND DOWN TO 4TH FLOOR | LEE | LEE | | PTO | P | 7211720 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/15/2021 | DWV only: 4th floor to rooms on 5th at columns 13 - XA ok.\ Domestic water only 5th floor only between columns 16 - XA and X7- XA: leak room 5530/ need nail protection / rest ok to insulate this area.
| DANR | DANR | | PTO | P | 7210238 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/08/2021 | 5TH FLOOR -- ROOM # 5514 -- DWV ONLY DOWN TO 4TH FLOOR OK | LEE | LEE | | PTO | P | 7201650 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/02/2021 | 6TH FLOOR DWV AND H20 COMPLETE | LEE | LEE | | PTO | P | 7195447 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/01/2021 | 6TH FLOOR ACCESSIBLE ROOM #-6514 IN WALL H20 OK -- ACCESSIBLE SHOWER VALVES IN SLEEP ROOMS # 6565 AND 6566 NEED TO BE SWITCHED TO OTHER WALL | LEE | LEE | | PTO | P | 7193401 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 11/23/2021 | 6TH FLOOR -- IN WALL H20 IN ROOMS # 6502, 6504, 6506, 6508, 6510, 6512 -- ALSO JANITORS # 6563 OK | LEE | LEE | | PTO | P | 7186715 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 11/11/2021 | 6TH FLOOR -- IN WALL H20 IN ROOMS # 6516, 6518, 6520 AND 6522 , ALSO 6584, 6578, 6576, 6573 AND 6575, ALSO N/E CORRIDOR SINK AND EAST EMPLOYEE SINK | LEE | LEE | | PTO | P | 7173891 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 11/03/2021 | 6TH FLOOR -- H20 IN WALL ROOMS # 6546, 48, 50, 52, 54, 56, 58, 60 AND 6562 OK, ALSO 6592 OK -- SHOWER DRAINS # 6554, 56, 58, 60 AND 6562 OK | LEE | LEE | | PTO | P | 7164120 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 10/21/2021 | 6TH FLOOR -- IN WALL H20 ROOMS # 5524, 5526, 5528, 5530 AND 5532 OK -- DWV ONLY IN WALL AND VTR ROOMS # 6573, 6575, 6577 AND 6578 OK | LEE | LEE | | PTO | P | 7150453 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 10/14/2021 | 6TH FLOOR IN WALL H20 - ROOMS # 6534, 6536, 6538, 6540 AND 6542 OK -- SLEEP ROOMS # 6565 AND 6566 DWV ONLY IN WALL AND UNDERFLOOR COMPLETE -- SOUTH END ROOMS # 6502, 6504, 6506, 6508, 6510 AND 6512 DWV IN WALL ONLY OK | LEE | LEE | | PTO | P | 7141962 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 09/17/2021 | 6TH FLOOR DWV AND OVERHEAD MAINS COLUMN XD TO XC -- 3 TO 16 ABOVE FLOOR ONLY, 5- GROUPS MISSING SHOWER DWV, WILL RE-TEST WHEN PIPING INSTALLED -- ((( NEED PLANS TO REFLECT ADA SHOWER CHANGE ROOM # 6562 ))) | LEE | LEE | | PTO | P | 7111537 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 09/13/2021 | 6TH FLOOR - N/W ROOMS 8-LINE TO XC.1 DWV ONLY ( STUBBED THRU FLOOR TO 5TH ) -- OVERHEAD MAINS SAME AREA OK TOO, DROPS VALVED AND CAPPED -- ((( NEED PLANS REVISED TO SHOW HOT LOOP RE-CIRC AND ADA SHOWER RE-LOCATED IN ROOM # 6352 ))) | LEE | LEE | | PTO | P | 7104872 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 09/09/2021 | Call ahead made 12:36pm / called contractor 3 times no answer. | DANR | DANR | | PTO | P | 7101705 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 07/27/2021 | Domestic water risers on 4th, 5th, and 6th floor shaft 1 ok,. | DANR | DANR | | PTO | P | 7050524 |
OLSON PLUMBING & HEATING COMPANY | PRD | C | 07/15/2021 | INSPECTED TWO 4" VENT EXTENSIONS IN EACH SHAFT, OK THRU ROOF | LEE | LEE | | PRD | C | 7036887 |
OLSON PLUMBING & HEATING COMPANY | PRD | P | 06/08/2021 | SOUTH SET OF DRAINS COLUMN 13 TO 20 OK MINUS CONNECTIONS TO ROOF DRAINS SOUTH / WEST END WHERE LIFT IS IMPEDING -- ALSO NEED RESTRAINTS THRU-OUT 4" AND LARGER -- ((( STILL NEED REVISIONS FOR PENTHOUSE DRAINS ))) | LEE | LEE | | PRD | P | 6994651 |
OLSON PLUMBING & HEATING COMPANY | PRD | P | 06/01/2021 | INSPECTED 6TH FLOOR DRAINS NORTH END COLUMN 1 THRU 5 EAST TO WEST -- NEED RESTRAINTS THRU-OUT -- TESTS OK ((( NEED PLANS REVISED TO SHOW PENTHOUSE DRAINS TYING INTO EAST SIDE 4" DRAINS ))) | LEE | LEE | | PRD | P | 6986746 |
OLSON PLUMBING & HEATING COMPANY | PRD | L | 05/27/2021 | FIELD CANCELLED BY TANNER | LEE | LEE | | PRD | L | 6983885 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 06/14/2022 | PAID (REC#1875489): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Clouds | DALEH | DALEH | | XMS | T | 7410098 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 06/06/2022 | PAID (REC#1872342): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: clouds | DALEH | DALEH | | XMS | T | 7400045 |
ENCORE ELECTRIC, INC. | XES | T | 05/05/2022 | PAID (REC#1865823): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised power and special systems plans. Removed junction boxes. | BERTHA | BERTHA | | XES | T | 7365014 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 05/05/2022 | PAID (REC#1865821): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Duct for two new vestibule's | DALEH | DALEH | | XMS | T | 7364485 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 05/04/2022 | PAID (REC#1864768): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Adding doors and walls to allow for stair pressurization. | MICHAELA | MICHAELA | | XBS | T | 7364156 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 05/02/2022 | PAID (REC#1863985): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Fan manufacturer change | DALEH | DALEH | | XMS | T | 7359134 |
ENCORE ELECTRIC, INC. | XES | P | 04/25/2022 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised plans - added storage closet. | BERTHA | BERTHA | | XES | P | 7351440 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 04/25/2022 | PAID (REC#1861666): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise layout to add storage closet. | MICHAELA | MICHAELA | | XBS | T | 7351130 |
OLSON PLUMBING & HEATING COMPANY | XMS | P | 04/21/2022 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: PRESSURE SENSOR LOCATIONS | DALEH | DALEH | | XMS | P | 7346539 |
OLSON PLUMBING & HEATING COMPANY | XPS | T | 04/14/2022 | PAID (REC#1858747): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 81 revisions: Adjusted sheet PL142. | SHANEN | SHANEN | | XPS | T | 7338165 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 04/13/2022 | PAID (REC#1858458): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Add oxygen rooms | MICHAELA | MICHAELA | | XBS | T | 7336388 |
ENCORE ELECTRIC, INC. | XES | P | 01/19/2022 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised background | BERTHA | BERTHA | | XES | P | 7243418 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 01/19/2022 | PAID (REC#1837863): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Create oxygen room - Shaft termination detail | MICHAELA | MICHAELA | | XBS | T | 7242793 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 12/29/2021 | PAID (REC#1833285): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Add hoistway beam | MICHAELA | MICHAELA | | XBS | T | 7223736 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 12/17/2021 | PAID (REC#1830785): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: removal of dampers | DALEH | DALEH | | XMS | T | 7212718 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 12/14/2021 | PAID (REC#1829983): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Replacing listed assembly | MICHAELA | MICHAELA | | XBS | T | 7207796 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 11/30/2021 | PAID (REC#1825965): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Modifications to comply with FAA regulations. | MICHAELA | MICHAELA | | XBS | T | 7191095 |
OLSON PLUMBING & HEATING COMPANY | XMS | P | 11/12/2021 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: clouds | DALEH | DALEH | | XMS | P | 7174851 |
ENCORE ELECTRIC, INC. | XES | T | 11/10/2021 | PAID (REC#1824579): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised to indicate 125HP fire pump | BERTHA | BERTHA | | XES | T | 7172629 |
ENCORE ELECTRIC, INC. | XES | P | 11/02/2021 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised Nourish Room. | BERTHA | BERTHA | | XES | P | 7163255 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 11/02/2021 | PAID (REC#1819768): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: clouds | DALEH | DALEH | | XMS | T | 7162866 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 10/21/2021 | PAID (REC#1818397): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: cloud | DALEH | DALEH | | XMS | T | 7149777 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 10/08/2021 | PAID (REC#1813168): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Clarify wall types - location of protection | MICHAELA | MICHAELA | | XBS | T | 7134595 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 10/06/2021 | PAID (REC#1813180): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: clouds | DALEH | DALEH | | XMS | T | 7131351 |
OLSON PLUMBING & HEATING COMPANY | XPS | T | 10/06/2021 | PAID (REC#1814523): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 62R1 revisions: adjusted sheet PL142. | SHANEN | SHANEN | | XPS | T | 7131230 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | P | 10/06/2021 | PLAN SPLICE: (No Fee) by: MICHAELA for Construction: Rated penetration | MICHAELA | MICHAELA | | XBS | P | 7131214 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 08/10/2021 | PAID (REC#1797881): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Introduce new listed assemblies | MICHAELA | MICHAELA | | XBS | T | 7065927 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 07/02/2021 | PAID (REC#1787418): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: clouds | DALEH | DALEH | | XMS | T | 7024318 |
ENCORE ELECTRIC, INC. | XES | P | 07/01/2021 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Added cameras, relocated patient lift, revised security plans. | BERTHA | BERTHA | | XES | P | 7021899 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 06/29/2021 | PAID (REC#1789484): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Clouds | DALEH | DALEH | | XMS | T | 7019738 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | P | 06/29/2021 | PLAN SPLICE: (No Fee) by: MICHAELA for Construction: Revise dimensions | MICHAELA | MICHAELA | | XBS | P | 7019683 |
OLSON PLUMBING & HEATING COMPANY | XPS | T | 06/29/2021 | PAID (REC#1789486): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 50 revisions: Adjusted sheet PL162 and PL171. | SHANEN | SHANEN | | XPS | T | 7019320 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XES | T | 01/29/2021 | PAID (REC#1747355): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Additional UPS UPS4LDP3 added to one line ans floor plan////Lighting changes/// as builts | SHELBY | SHELBY | | XES | T | 6853525 |
U.S. ENGINEERING CONSTRUCTION, LLC | XMS | T | 01/28/2021 | PAID (REC#1748157): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: clouds | DALEH | DALEH | | XMS | T | 6851368 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XPS | T | 01/28/2021 | PAID (REC#1746750): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 039 revisions: P201 adjusted water service entry piping detail, PL142, PL152, PL162 adjusted waste & vent plan, PP151, PP152, PP161, PP162 adjusted domestic water plan | SHANEN | SHANEN | | XPS | T | 6851108 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 01/27/2021 | PAID (REC#1747360): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise listed assemblies - revise layout - additional details - structural revisions | MICHAELA | MICHAELA | | XBS | T | 6850545 |