CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | C | 06/22/2023 | | LONNYS | LONNYS | | B= | C | 7778682 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 06/09/2023 | Temp CO: pending final inspections ( Expires: 7/9/2023 12:00:00 AM) | JACKIEP | JACKIEP | | B= | P | 7768247 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 05/12/2023 | Temp CO: pending final inspections ( Expires: 6/11/2023 12:00:00 AM) | JACKIEP | JACKIEP | | B= | P | 7743081 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 04/13/2023 | Temp CO: Pending mechancial and building finals ( Expires: 5/13/2023 12:00:00 AM) | ASHLEYL | ASHLEYL | | B= | P | 7715242 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 02/28/2023 | Temp CO: Extension ( Expires: 3/30/2023 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 7672353 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 02/17/2023 | Observed all corrections and interior elevator shaft.. / Building final OK pending other finals /. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ADVANTAGE HEATING AND COOLING Mechanical Final Inspection is not Completed yet, ELEVATOR: PEAK ELEVATOR, LLC Mechanical Final Inspection is not Completed yet, ALLRIGHT PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | ERAMIREZ | ERAMIREZ | | B= | P | 7664635 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | R | 02/08/2023 | Elevator shaft inspection - Field canceled due to no power to elevator. No inspection performed. | ERAMIREZ | ERAMIREZ | | BSP | R | 7657191 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 01/23/2023 | Temp CO: extension ( Expires: 2/22/2023 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 7641375 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 12/20/2022 | Temp CO: pending required inspections ( Expires: 1/19/2023 12:00:00 AM) | BRITNEY | BRITNEY | | B= | P | 7616239 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 11/30/2022 | Spoke to contractor via phone regarding outstanding items / No inspections will be performed until contractor can verify if items have been corrected | ADAML | ADAML | | BSP | P | 7595720 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 11/30/2022 | Uploaded plumbing documents need to be submitted to a plumbing inspection so the inspector can view and approve -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ALLRIGHT PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | ADAML | ADAML | | B= | P | 7595622 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | R | 11/29/2022 | Inspection canceled by email prior to call ahead. | NATHAN | NATHAN | | BSP | R | 7594654 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 11/28/2022 | Temp CO: Pending required inspections. ( Expires: 12/28/2022 12:00:00 AM) | AMYP | AMYP | | B= | P | 7594008 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 05/03/2022 | Temp CO: Temp CO: Pending F, B, M, E, P finals ( Expires: 6/2/2022 12:00:00 AM) | BRITNEY | BRITNEY | | B= | P | 7360734 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 03/18/2022 | Temp CO: Pending fire, plumbing, mechanical, electrical and builidng finals ( Expires: 4/17/2022 12:00:00 AM) | AMYP | AMYP | | B= | P | 7306747 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | T | 02/22/2022 | PAID (REC#1845293): For TCO. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ALLRIGHT PLUMBING & HEATING Mechanical Final Inspection is not Completed yet, ALLRIGHT PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | RITA | RITA | | B= | T | 7277343 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 02/22/2022 | Temp CO: Pending fire, plumbing, mechanical, electrical and building finals. ( Expires: 3/24/2022 12:00:00 AM) | RITA | RITA | | B= | P | 7277333 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 02/17/2022 | Pending all other required inspections / Still need to complete elevator / Need 3rd party observation letter for new storage lockers / Restroom 125 lavatory is currently 35" FFF ( From finished floor ) , needs to be 34" / Missing Restroom door / Missing accessible restroom signage / Missing grab bars / Water closet is not oriented correctly per approved plans / Still need to complete splice for layout change near Restroom 103 per previous inspection notes / Fire caulk edges of stairwell lid / Missing cane rail under stairs / Restroom 103 Side grab bar exceeds 36" FFF ( Currently 39" ) and lacks 12" from rear wall / Rear grab bar exceeds 36" FFF ( Currently 39" ) / Lavatory exceeds 34" ( Currently 35" ) / Missing pipe protection / Mirror exceeds 40" to bottom of reflective surface -- Schedule a new Building Final when above items are complete. | ADAML | ADAML | | B= | P | 7274910 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | R | 01/31/2022 | Building final inspection was requested by mistake, only needed upload of document for stair ceiling assembly. Inspector changed inspection to BSP . Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), FIRE ALARM: ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, ADVANTAGE HEATING & COOLING Mechanical Final Inspection is not Completed yet, ALLRIGHT PLUMBING & HEATING Mechanical Final Inspection is not Completed yet, ALLRIGHT PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | R | 7256116 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 01/31/2022 | Stamped letter for ceiling assembly on file. Inspection to follow . | NATHAN | NATHAN | | BSP | P | 7254711 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 01/14/2022 | Observed all blocking in restroom for grab bars and misc fixtures | ADAML | ADAML | | BSP | P | 7240431 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 01/06/2022 | Observed two layers of 5/8 drywall on lid of stair enclosure / Splice pending for exact listing / Discussed 3rd party observations for new structural steel beams and columns and grouting under columns / Discussed backing for grab bars in new restroom | ADAML | ADAML | | BSP | P | 7230780 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFR | P | 12/23/2021 | Inspection request for rated lid at interior stair enclosure / Observed a horizontal assembly consisting of 3 5/8" metal studs 16" oc with 1" American shaft liner / Need listed assembly that matches as built conditions | ADAML | ADAML | | BFR | P | 7220348 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 10/13/2021 | Consultation/Inspection for interior stairs - Risers, tread, hand rails and guards OK / No other inspections performed at this time | ADAML | ADAML | | BSP | P | 7140092 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFT | C | 09/28/2021 | Open hole/compaction on file | ADAML | ADAML | | BFT | C | 7121654 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFN | C | 09/27/2021 | Engineer letter on file for footing/foundation for elevator pad | ADAML | ADAML | | BFN | C | 7120141 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFT | P | 09/27/2021 | Soils on file / Still need open hole report | ADAML | ADAML | | BFT | P | 7120138 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFR | P | 09/22/2021 | PARTIAL FRAME - Pending all other required inspections / 1st Floor Restroom 125 - Metal framing for restroom 125 OK / MOP room 127 is not present and per contractor will not be built / Need to obtain splice for that room as well as any other rooms that are not going to be built or have been added that are not in the current plans / **Need to splice elevator structurals into plan
Provided consultation with David Stevens / Discussed rated assemblies and inspection procedures / Need open hole/soils and 3rd party observations for elevator pad / Discussed 3rd party observations for pre built storage lockers and any structural steel and/or CMU / | ADAML | ADAML | | BFR | P | 7116836 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFN | P | 09/22/2021 | Authorized 3rd party engineer inspection with all observation paperwork to follow / | ADAML | ADAML | | BFN | P | 7116636 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFT | P | 09/22/2021 | Authorized 3rd party engineer inspection with all observation paperwork to follow / | ADAML | ADAML | | BFT | P | 7116634 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 08/24/2021 | On site consultation with contractor about covered work, 3rd party inspections, stair enclosures, elevator inspections, and inspection expectations | TIMOTHYS | TIMOTHYS | | BSP | P | 7083868 |
ENCORE ELECTRIC, INC. | E= | C | 03/27/2023 | FIRE ALARM INSPECTION: Rough in complete | BRETC | BRETC | | E= | C | 7698506 |
ENCORE ELECTRIC, INC. | E= | C | 03/22/2023 | AMM - Accepted | BRETC | BRETC | | E= | C | 7694378 |
ENCORE ELECTRIC, INC. | E= | P | 03/13/2023 | Need AMM for elevator pit sump / Elevator exhaust fan - Ok | BRETC | BRETC | | E= | P | 7685357 |
ENCORE ELECTRIC, INC. | E= | P | 03/09/2023 | Not ready | BRETC | BRETC | | E= | P | 7683213 |
ENCORE ELECTRIC, INC. | E= | P | 03/08/2023 | EC needs to attach to permit N95517 /---------------------------- / --------------Need AMM for elevator sump pit receptacle or will need 2 single receptacles with GFCI protection on 2 separate circuits / --------------EC Note: New Panel and transformer along with all RTU's added in Phase 2 will be captured in Permit # N95517 | BRETC | BRETC | | E= | P | 7680872 |
ENCORE ELECTRIC, INC. | E= | P | 03/03/2023 | Elevator splice - Ok /------------------------------ Need new panels - 3 RTU's and exhaust fan spliced and attached to permit / Need AMM for elevator sump pit receptacle or will need 2 single receptacles with GFCI protection on 2 separate circuits / Elevator circuit will need to be spliced to show exact installation, wire, breaker & fuses / Splice required, please submit splice for changes in scope. If unfamiliar in submitting electronic splice, please click the following link: https://youtu.be/dG3kHpgDP0w / | BRETC | BRETC | | E= | P | 7675856 |
ENCORE ELECTRIC, INC. | E= | P | 02/09/2023 | See rough notes | BRETC | BRETC | | E= | P | 7658082 |
ENCORE ELECTRIC, INC. | ER | P | 02/09/2023 | Need new panels - 3 RTU's and exhaust fan spliced and attached to permit / Need AMM for elevator sump pit receptacle or will need 2 single receptacles with GFCI protection on 2 separate circuits / Elevator circuit will need to be spliced to show exact installation, wire, breaker & fuses / Splice required, please submit splice for changes in scope. If unfamiliar in submitting electronic splice, please click the following link: https://youtu.be/dG3kHpgDP0w / | BRETC | BRETC | | ER | P | 7658077 |
ENCORE ELECTRIC, INC. | ER | P | 08/23/2022 | 1 st and 2 nd floor GFI protection ok | CRAIG | CRAIG | | ER | P | 7492115 |
ENCORE ELECTRIC, INC. | E= | P | 08/11/2022 | 1st & 2nd floor GFCI protection will need to be readily accessible, GFCI receptacles will need to be below 6'-7" aff - all mounted 8' to center / 2nd floor lighting - Ok | BRETC | BRETC | | E= | P | 7479781 |
ENCORE ELECTRIC, INC. | ER | P | 08/11/2022 | 2nd floor NE corner all new emt and mc will need 1 1/2" separation from roof decking / All A/C's & furnaces per past inspection will need to be spliced to permit, Need AIC ratings for A/C's on drawings / Elevator to come - make sure drawings reflect install / | BRETC | BRETC | | ER | P | 7479758 |
ENCORE ELECTRIC, INC. | ER | P | 07/08/2022 | FIRE ALARM INSPECTION: 2nd floor phase 2 ok. / | LOGANP | LOGANP | | ER | P | 7440275 |
ENCORE ELECTRIC, INC. | E= | P | 01/21/2022 | 1 st floor ok plans need to show 2 furnace and 2 A/C s --------------------------- need to verify SCCR to both A/C s ------------- both A/C s are on 30 amp each ok ------------------ note elevators are on back order | CRAIG | CRAIG | | E= | P | 7246501 |
ENCORE ELECTRIC, INC. | E= | P | 12/30/2021 | FIRE ALARM INSPECTION: Phase 1 - 1st floor area minus elevator - Ok | BRETC | BRETC | | E= | P | 7225065 |
ENCORE ELECTRIC, INC. | ER | P | 12/30/2021 | FIRE ALARM INSPECTION: Phase 1 - 1st floor area minus elevator - Ok | BRETC | BRETC | | ER | P | 7225062 |
ENCORE ELECTRIC, INC. | EUG | C | 10/26/2021 | 3 - 1" PVC to parking lot center - Ok | BRETC | BRETC | | EUG | C | 7154541 |
ENCORE ELECTRIC, INC. | EUG | P | 10/14/2021 | Front sidewalk PVC - 2 - 3/4" , 3 - 1" stubs to trench | BRETC | BRETC | | EUG | P | 7141711 |
ENCORE ELECTRIC, INC. | ER | P | 10/14/2021 | West restroom - Ok | BRETC | BRETC | | ER | P | 7141703 |
ENCORE ELECTRIC, INC. | ER | P | 08/31/2021 | need FA permit/ walls, see plans, a lot of cut ins/ strip lights partially finished, look ok. | JOHNN | JOHNN | | ER | P | 7092082 |
PEAK ELEVATOR, LLC | HE= | C | 06/21/2023 | ELEVATOR FINAL - OK FOR PUBLIC USE | MIKEM | MIKEM | | HE= | C | 7778262 |
ADVANTAGE HEATING AND COOLING | H= | C | 03/01/2023 | RECEIVED TEST AND BALANCE REPORT, SEE IMAGES / | MATTM | MATTM | | H= | C | 7673068 |
PEAK ELEVATOR, LLC | HE= | P | 02/21/2023 | ELEVATOR -- ITEMS ADDRESSED FROM PREVIOUS INSPECTION EXCEPT THE ACCEPTANCE TAG. STILL NEED FINALS FROM C.S.F.D., ELECTRICAL, MECHANICAL AND PLUMBING -- NO PUBLIC USE | MIKEM | MIKEM | | HE= | P | 7665923 |
ADVANTAGE HEATING AND COOLING | HD | P | 02/13/2023 | FOR FINAL - Provide test and balance report for EF-3 in elevator equipment room. FIRE/SMOKE DAMPERS - ANNULAR SPACE, ANGLES AND BREAK AWAY CONNECTIONS COMPLETE FOR BOTH DAMPERS. | MARKB | MARKB | | HD | P | 7660797 |
PEAK ELEVATOR, LLC | H= | R | 02/09/2023 | (Elevator #1) -- NO PUBLIC USE -- ELEVATOR NOT REGISTERED WITH THE STATE AND SHALL BE BY FINAL --/ ALL HOISTWAY PROTRUSIONS NEED TO BE REMOVED OR ADDRESSED --/ PHASE 1 AND PHASE 2 AUDIBLE RECALL NOT ALARMING --/ PROVIDE A TYPE "ABC" FIRE EXTINGUISHER INSIDE THE MACHINE ROOM --/ ELEVATOR PIT OIL CANS ARE MISSING AND OIL IS PRESENT IN THE PIT, JACK HEADS HAVE BEEN DRILLED AND NEED TO BE ADDRESSED --/ LABEL THE MACHINE ROOM DOOR --/ PROVIDE CROSS HEAD DATA TAG AND STICKERS --/ INSTALL THE ELEVATOR CAB STEADIERS AND MODIFY THE TOE GUARD TO ALLOW PROPER INSTALLATION OF CAB STEADIERS --/ BUILDING TO ADDRESS THE TOP OF HOISTWAY SHAFT I BEAM (LOOSE INSIDE THE BEAM POCKETS) --/ THE PIT STOP SWITCH NEEDS TO BE RELOCATED APPROXIMATELY 18 INCHES ABOVE THE LANDING SILL --/ ELEVATOR ENTRANCE AT GROUND LEVEL IS OUT OF LEVEL BY 3/4 OF AN INCH. SILL TO SILL HEIGHT TO BE ADDRESSED --/ SUMP PUMP DISCHARGE PIPE TO BE RELOCATED OUTSIDE OF THE MACHINE ROOM --/ ELEVATOR PIT LIGHTING, RECEPTACLE, AND SUMP PUMP RECEPTACLE TO BE ON DEDICATED BRANCH CIRCUITS AND LABELED ACCORDINGLY AT THE DEVICES AND CIRCUIT BREAKER PANEL SCHEDULE --/ MACHINE ROOM RECEPTACLE AND LIGHTS TO BE ON THEIR OWN DEDICATED BRANCH CIRCUITS AND LABELED ACCORDINGLY AT THE CIRCUIT BREAKER PANEL SCHEDULE --/ ELEVATOR PUMP AND PUMP MOTOR ARE NOT ALIGNED AND NEED TO BE REMEDIED --/ CSFD TO ADVISE ON THE PIT SPRINKLER NEEDING SHUNT OR DEVICE PROTECTION --/ PROVIDE INSTALLATION METHODS USED AND INSTILLATION INSTRUCTIONS FOR THE TOP OF HOISTWAY RAIL BRACKETS (CAN NOT DETERMINE IF BLOCKS HAVE APPROPRIATE FILL) --/ PROVIDE MISSING HARDWARE ON RAIL BRACKETS (SOME ARE NOTED AS MISSING WASHERS) --/ PEAK ELEVATOR TO PROVIDE AN ACCEPTANCE TEST TAG FOR FINAL --/ SECOND FLOOR FACIA NEEDS TO BE BEVELED BACK TO THE WALL AND SECURED --/ STILL NEED TO VERIFY EMPTY, RUNNING/WORKING, AND RELIEF PRESSURES AND THAT THE VALVE HAS BEEN TAGGED ACCORDINGLY --/ STILL NEED TO SEE THE AUXILIARY BATTER LOWERING TEST PERFORMED --/ NEED FIRE, BUILDING, PLUMBING, AND ELECTRICAL INSPECTIONS FOR FINAL –/ NO PUBLIC USE | MIKEM | MIKEM | | H= | R | 7658046 |
ADVANTAGE HEATING AND COOLING | HD | P | 01/17/2023 | ELEVATOR ROOM TRANSFER FSD DAMPER FRAMING OK, SEE IMAGES / | MATTM | MATTM | | HD | P | 7635513 |
ADVANTAGE HEATING AND COOLING | HD | P | 01/13/2023 | ELEVATOR MECHANICAL ROOM FSD FRAMING FOR FAN OK. FSD framing for transfer cannot have hole or screws in opening / ok to attach picture of correction to next inspection request / Plans need to be updated to include correct FSD's, show exhaust duct and updated equipment schedule / | MATTM | MATTM | | HD | P | 7635061 |
ADVANTAGE HEATING AND COOLING | HE | L | 01/12/2023 | Renewed online for Half Fee at Jan 12 2023 9:48AM (RECEIPT #: 1926147) | WEBSITE | WEBSITE | | HE | L | 7632905 |
ALLRIGHT PLUMBING & HEATING | H= | C | 10/05/2022 | SPLICE ON FILE, OTHER CORRECTION MADE - SEE IMAGES | MARKB | MARKB | | H= | C | 7539891 |
ADVANTAGE HEATING AND COOLING | H= | P | 02/10/2022 | CHANGED TO PARTIAL ON 1/4/23 TO ALLOW FOR ELEVATOR EQUIPMENT ROOM INSPECTIONS AFTER TALKING TO CHIEF. TEST AND BALANCE REPORT RECEIVED AND SPLICE ON FILE | MARKB | MARKB | | H= | P | 7265728 |
ADVANTAGE HEATING AND COOLING | H= | P | 01/25/2022 | FINAL PENDING - Remove EF-7 from plans if being installed under phase 2 scope or install. Provide test and balance report. | MARKB | MARKB | | H= | P | 7250130 |
ADVANTAGE HEATING AND COOLING | HD | P | 01/25/2022 | DUCT FROM RTU DOWN TO 1ST FLOOR STORAGE UNITS INSTALLED PER PLAN SPLICE. EF-4 & EF-5 COMPLETE | MARKB | MARKB | | HD | P | 7250129 |
ALLRIGHT PLUMBING & HEATING | H= | P | 12/30/2021 | FINAL PENDING PLANS SPLICE AND VENTILATION FOR GAS REGULATORS IN MECHANICAL ROOM / OK TO ATTACH PICTURE TO NEXT INSPECTION REQUEST. PLEASE NOTIFY INSPECTOR WHEN PLAN SPLICE IS READY / | MATTM | MATTM | | H= | P | 7225706 |
ADVANTAGE HEATING AND COOLING | HV | C | 12/06/2021 | | MATTM | MATTM | | HV | C | 7198844 |
ADVANTAGE HEATING AND COOLING | HD | P | 11/30/2021 | SHOWROOM DUCT DESIGN PER PLANS. OK TO WRAP OUTSIDE AIR DUCT / PROVIDE TEST AND BALANCE REPORT BY FINAL / | MATTM | MATTM | | HD | P | 7192438 |
ADVANTAGE HEATING AND COOLING | HV | P | 11/30/2021 | RIGHT FURNACE INTAKE AND VENT ARE BACKWARDS AT THE CONCENTRIC KIT / LEFT FURNACE VENT OK / | MATTM | MATTM | | HV | P | 7192433 |
ADVANTAGE HEATING AND COOLING | HRP | C | 11/30/2021 | SHOWROOM LINESETS AND CONDENSATE DRAINS OK / | MATTM | MATTM | | HRP | C | 7192430 |
ALLRIGHT PLUMBING & HEATING | H= | P | 11/18/2021 | --NEED CONTRACTOR ATTACHED TO PERMIT FOR OTHER GAS PIPING BESIDES FURNACES OR PLAN SPLICE REMOVING ALL OTHER GAS PIPING. -- ----ENGINEER TO ADDRESS: Plan shows low pressure gas piping but building has existing medium pressure gas pipe. If regulators are to be in mechanical room how is room ventilated for vent limiters?---- Still need regulators and medium pressure stickers installed | MARKB | MARKB | | H= | P | 7182950 |
ALLRIGHT PLUMBING & HEATING | HI | C | 11/18/2021 | SHOWROOM GAS ONLY: 10 PSI PRESSURE TEST FROM ROOF DOWN TO BOTH FURNACES INSTALLED PER PLAN OK. Still need regulators for existing medium pressure and stickers. | MARKB | MARKB | | HI | C | 7182948 |
ALLRIGHT PLUMBING & HEATING | P= | C | 02/21/2023 | Corrections complete | FRANKM | FRANKM | | P= | C | 7665516 |
ALLRIGHT PLUMBING & HEATING | P= | P | 12/28/2022 | there was no plan splice submitted to plan review, plans were uploaded to building inspector but they need to be submitted to plan review | JOSEPHD | JOSEPHD | | P= | P | 7620679 |
ALLRIGHT PLUMBING & HEATING | P= | P | 10/05/2022 | just need engineer letter for pvc and plan splices done, other corrections made | JOSEPHD | JOSEPHD | | P= | P | 7540009 |
ALLRIGHT PLUMBING & HEATING | PSP | P | 08/08/2022 | consultation, phase 2 on permit number N95517 | JOSEPHD | JOSEPHD | | PSP | P | 7474239 |
ALLRIGHT PLUMBING & HEATING | PTO | R | 08/01/2022 | changed to a pto, can not drain 2nd floor mop sink into 1st floor mop sink vent, need engineer letter for pvc plans call for cast iron, still need all other items from previous inspections, plumber will need to be on site at next inspection | JOSEPHD | JOSEPHD | | PTO | R | 7466024 |
ALLRIGHT PLUMBING & HEATING | PTO | C | 03/15/2022 | JUST INSPECTED RE-LOCATED BACK DRINKING FOUNTAIN ROUGH-IN, ITS OK -- STILL NEED ALL SPLICES / LETTERS AND PREVIOUS INSPECTION DEFICIENCIES | LEE | LEE | | PTO | C | 7302596 |
ALLRIGHT PLUMBING & HEATING | P= | P | 02/16/2022 | REAR RESTROOM -- LAV TOO HIGH -- LAV LACKS TEMPERING VALVE -- NO HOT WATER -- NEED OPEN FRONT SEAT -- SUPPORT COPPER AND PVC TOO CODE BACK ROOM -- COMPLETE ELEVATOR DISCHARGE PIPING IN PIT | LEE | LEE | | P= | P | 7273360 |
ALLRIGHT PLUMBING & HEATING | PTO | P | 02/07/2022 | TESTS OK IN RESTROOM WALLS -- STILL NEED ALL REVISIONS / SPLICES / LETTERS AS NOTED | LEE | LEE | | PTO | P | 7261984 |
ALLRIGHT PLUMBING & HEATING | PTO | P | 02/01/2022 | LOST TEST ON TOILET DISCHARGE -- DISCHARGE PIPE CROSSES W/C GRAB BAR, WILL NEED TO BE RELOCATED -- ((( PLANS NEED TO BE REVISED TO SHOW NEW RESTROOM LAYOUT ))) -- FLOOR DRAIN IN WHEEL CHAIR PATH IN FRONT OF TOILET -- NEED PVC SUPPORT IN HALL WAY OUTSIDE OF RESTROOM | LEE | LEE | | PTO | P | 7257582 |
ALLRIGHT PLUMBING & HEATING | PTO | P | 01/20/2022 | STORAGE RESTROOM INSULATION WALLS ONLY OK | LEE | LEE | | PTO | P | 7245439 |
ALLRIGHT PLUMBING & HEATING | PTO | P | 01/18/2022 | REAR RESTROOM WALLS OK MINUS MACERATING TOILET INSTALL INSTRUCTIONS | LEE | LEE | | PTO | P | 7242193 |
ALLRIGHT PLUMBING & HEATING | PTO | P | 12/30/2021 | DRINKING FOUNTAIN DRAIN IS FLAT IN SPOTS ( LACKS MIN. 2% SLOPE ) -- SCREW / NAIL PROTECTION INCOMPLETE SEVERAL SPOTS -- ISOLATE COPPER FROM METAL ELECTRICAL BOX BRACKET -- TOILET SUPPLY LACKS SUPPORT -- OVERHEAD COPPER PIPE LACKS SUPPORT ( MAX 6' SPACING ) -- NEED INSTALLATION INSTRUCTIONS FOR ROUGH-IN ON MACERATING TOILET -- WATER HEATER MISSING THERMAL EXPANSION DEVICE -- STILL NEED ALL OTHER REVISIONS / SPLICES FROM PREVIOUS INSPECTION -- NOTE: DRINKING FOUNTAINS OK PENDING ONE IS AT NORMAL HEIGHT AND OTHER IS ACCESSIBLE HEIGHT | LEE | LEE | | PTO | P | 7225803 |
ALLRIGHT PLUMBING & HEATING | PTO | P | 11/18/2021 | NOT READY -- NOTHING ON TEST -- SCREW PROTECTION MISSING EVERYWHERE -- ALL DOMESTIC H20 NEEDS TO BE INSULATED PER PLANS -- (((( NEED PLAN REVISED TO SHOW ALL CHANGES --- (1- WATER PIPE SIZING AT RESTROOM W/C -- (2- PIPE MATERIAL -- (3- DELETED UTILITY SINK -- (4- ELEVATOR DISCHARGE -- (5- ADDITIONAL W/H )))) NEED INSTALL INSTRUCTIONS FOR MACERATING SYSTEM -=- ETC | LEE | LEE | | PTO | P | 7182917 |
ENCORE ELECTRIC, INC. | XES | P | 03/01/2023 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: Revise elevator feeder OCPD | SHELBY | SHELBY | | XES | P | 7674054 |
ALLRIGHT PLUMBING & HEATING | XPS | P | 01/25/2023 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Delta 7 revisions: Adjusted sheet P0.2.1 and P1.1.1. | SHANEN | SHANEN | | XPS | P | 7643633 |
ADVANTAGE HEATING AND COOLING | XMS | T | 01/23/2023 | PAID (REC#1928873): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised EF tag and schedule | JUSTINC | JUSTINC | | XMS | T | 7641954 |
ENCORE ELECTRIC, INC. | XES | P | 02/04/2022 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: Remove exhaust fan. | SHELBY | SHELBY | | XES | P | 7260558 |
ADVANTAGE HEATING AND COOLING | XMS | P | 02/02/2022 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Removed exhaust fan from scope | JUSTINC | JUSTINC | | XMS | P | 7257828 |
ALLRIGHT PLUMBING & HEATING | XPS | P | 01/19/2022 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Delta 6 revisions: Adjusted sheet P1.1.1 (see alternate in images). | SHANEN | SHANEN | | XPS | P | 7243931 |
ENCORE ELECTRIC, INC. | XES | T | 12/21/2021 | PAID (REC#1832781): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Water heater, Fan coil as builts | SHELBY | SHELBY | | XES | T | 7216480 |
ADVANTAGE HEATING AND COOLING | XMS | T | 11/09/2021 | PAID (REC#1825398): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Scope and layout revised | JUSTINC | JUSTINC | | XMS | T | 7170048 |