CMG CORP | B= | C | 04/25/2023 | All remaining items corrected | DAKOTAB | DAKOTAB | | B= | C | 7725791 |
CMG CORP | B= | P | 04/10/2023 | Temp CO: pending required inspections ( Expires: 5/10/2023 12:00:00 AM) | BRITNEY | BRITNEY | | B= | P | 7711965 |
CMG CORP | B= | P | 03/14/2023 | Temp CO: Pending required inspections ( Expires: 4/13/2023 12:00:00 AM) | JACKIEP | JACKIEP | | B= | P | 7686685 |
CMG CORP | B= | P | 02/08/2023 | Temp CO: Pending required inspections. ( Expires: 3/10/2023 12:00:00 AM) | AMYP | AMYP | | B= | P | 7656393 |
CMG CORP | BIN | C | 01/17/2023 | ES report for spray foam insulation on file | LONNYS | LONNYS | | BIN | C | 7635716 |
CMG CORP | BIN | R | 01/13/2023 | no documents uploaded with inspection request | LONNYS | LONNYS | | BIN | R | 7634004 |
CMG CORP | BFT | C | 01/06/2023 | open hole on file | BOBF | BOBF | | BFT | C | 7627183 |
CMG CORP | B= | P | 01/04/2023 | pending other required inspections / provide open hole to complete BFT / provide ES report for spray foam insulation to complete BIN / still need to splice in framing changes for relocated door in office 8 and removed wall in office 4 / rest of building final OK -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet, External Agency Inspection Z= by ZONING is not Completed yet (Contact: 520-6300), EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, RAPID FIRE PROTECTION, INC. Electrical Final Inspection is not Completed yet, RIAL HEATING AND AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet, ELEVATOR: MORNING STAR ELEVATOR, LLC. Mechanical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 7624907 |
CMG CORP | B= | P | 12/19/2022 | need to complete all other required inspections, provide ANSI compliant signs at all rest tooms, rest of building okay -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet, External Agency Inspection Z= by ZONING is not Completed yet (Contact: 520-6300), EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, RAPID FIRE PROTECTION, INC. Electrical Final Inspection is not Completed yet, RIAL HEATING AND AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet, ELEVATOR: MORNING STAR ELEVATOR, LLC. Mechanical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 7615244 |
CMG CORP | BSP | P | 03/24/2022 | GYP ATTACHMENT INSPECTION AT ELEVATOR SHAFT WALLS, LID AND MACHINE ROOM WALLS AND LID // provide fire stop detail for I beam membrane penetration - wall gyp attachment OK per GA WP 3660 - 1st and 2nd layer attachment at horizontal assembly OK per GA FC 5529 | LONNYS | LONNYS | | BSP | P | 7313532 |
CMG CORP | BIN | P | 03/21/2022 | pending BFR and ES report for spray foam insulation / all insulation OK / all air barriers OK | LONNYS | LONNYS | | BIN | P | 7309009 |
CMG CORP | BIN | P | 03/17/2022 | pending completion of BFR / provide ES report for spray foam insulation / basement insulation OK only | LONNYS | LONNYS | | BIN | P | 7305812 |
CMG CORP | BFR | P | 03/17/2022 | INTERIOR WALL FRAMING THROUGHOUT // door in office 8 in different location of approved plan - office 4 not framed per plan (one room removed) - door framed in basement for under stair storage not per plan - rest of interior wall framing, soffits and hard lids OK pending other required inspections / reviewed accessible elements with site rep | LONNYS | LONNYS | | BFR | P | 7305807 |
CMG CORP | BLA | C | 03/17/2022 | | LONNYS | LONNYS | | BLA | C | 7305798 |
CMG CORP | BFR | P | 02/24/2022 | FRAME INSPECTION FOR EXTERIOR WALLS, ALL TRUSSES, ROOF FRAMING, SHAFT FRAMING AND DECK FRAMING // pending other required inspections - still need to inspect all interior walls both levels - remove spray foam from inside of elevator shaft - floor trusses OK - all exterior walls OK , roof framing OK , deck framing OK, roof LSTA15s OK / reviewed elevator shaft listing and accessible elements with sit rep / PPRBD will be doing insulation inspection | LONNYS | LONNYS | | BFR | P | 7281692 |
CMG CORP | BSP | P | 01/24/2022 | BASEMENT WALL FRAMING // pending other required inspections / will need to provide 3rd party welding and bolting obs. for structural steel / need to splice in floor trusses and have inspected / rest of basement wall framing and hard lids OK / reviewed UL U327 with site rep for elevator shaft and accessible elements in basement | LONNYS | LONNYS | | BSP | P | 7248215 |
CMG CORP | BSP | P | 12/02/2021 | EXTERIOR SHEAR - HOLD DOWNS - SOFFITS - DECK COVER - FRONT ENTRANCE COVER // front entrance cover missing LSTA15s per detail 2/6.3 // rest of soffits and all exterior covers OK / interior and exterior shear fastening and hold downs OK | LONNYS | LONNYS | | BSP | P | 7195783 |
CMG CORP | BFI | C | 11/11/2021 | foundation insulation verified electronically | LONNYS | LONNYS | | BFI | C | 7173171 |
CMG CORP | BFI | P | 09/20/2021 | R10 only installed 24 inches around slab perimeter of walk out comcheck shows foundation insulation to be @ 3ft, will accept photos of correction uploaded to inspection request / Note: Need to complete BFT and BFN | TRENTP | TRENTP | | BFI | P | 7113292 |
CMG CORP | BFN | P | 09/15/2021 | engineer letter for perimeter footings and pads on file / engineer letter for retaining wall and pilasters on file | LONNYS | LONNYS | | BFN | P | 7107228 |
CMG CORP | BFD | C | 09/07/2021 | Engineer letter for perimeter drain on file | DAKOTAB | DAKOTAB | | BFD | C | 7097764 |
CMG CORP | BFN | P | 08/17/2021 | Engineer letter for foundation on file -- Eufer noted | DAKOTAB | DAKOTAB | | BFN | P | 7074381 |
CMG CORP | BFT | P | 08/17/2021 | Engineer letter for footing on file | DAKOTAB | DAKOTAB | | BFT | P | 7074380 |
CMG CORP | BFN | P | 07/16/2021 | Authorized 3rd party engineer inspection with all observation paperwork to follow | DAKOTAB | DAKOTAB | | BFN | P | 7038153 |
CMG CORP | BFT | P | 07/16/2021 | Authorized 3rd party engineer inspection with all observation paperwork to follow | DAKOTAB | DAKOTAB | | BFT | P | 7038152 |
EL PASO ELECTRIC, LLC. | E= | C | 01/12/2023 | E= OK ------- | GREGM | GREGM | | E= | C | 7633012 |
RAPID FIRE PROTECTION, INC. | E= | C | 01/11/2023 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 7632748 |
EL PASO ELECTRIC, LLC. | E= | T | 12/27/2022 | PAID (REC#1923011): building locked at 9:20 | TOMC | TOMC | | E= | T | 7619637 |
EL PASO ELECTRIC, LLC. | E= | P | 12/09/2022 | LABEL PANELS AND A/ UNITS ----- NEED OUTLETS FOR ISLAND ----- POWER FOR D/O ------REST OK ------- | GREGM | GREGM | | E= | P | 7606369 |
EL PASO ELECTRIC, LLC. | ER | C | 12/02/2022 | ER OK ------ ABOVE CEILINGS ------- | GREGM | GREGM | | ER | C | 7598439 |
EL PASO ELECTRIC, LLC. | EP | P | 04/20/2022 | panels A , A1 , B , B1 | TOMC | TOMC | | EP | P | 7344985 |
EL PASO ELECTRIC, LLC. | ES | C | 04/20/2022 | Commercial Service: 600 amp 120 / 240 --- ok to set meter | TOMC | TOMC | | ES | C | 7344983 |
EL PASO ELECTRIC, LLC. | ER | P | 02/10/2022 | ER OK ---- WALLS AND HARD LIDS ------ IRR UFER OK----- | GREGM | GREGM | | ER | P | 7266503 |
EL PASO ELECTRIC, LLC. | ER | P | 01/11/2022 | Basement walls and restroom (x2) hard lids rough OK. | AARONR | AARONR | | ER | P | 7235551 |
EL PASO ELECTRIC, LLC. | EUG | P | 12/10/2021 | 2 x 3 inch from pedestal to MDP / 2 x 2 inch from pedestal to building for future Solar / 1 inch from building for lighting | JOSEPH | JOSEPH | | EUG | P | 7204815 |
MORNING STAR ELEVATOR, LLC. | HE= | C | 02/13/2023 | ELEVATOR COMPLETE | ERIC | ERIC | | HE= | C | 7660315 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | C | 02/08/2023 | TEST AND BALANCE REPORT RECEIVED SEE IMAGES. MECHANICAL FINAL------------------COMPLETE. | TREVORH | TREVORH | | H= | C | 7656295 |
RIAL HEATING AND AIR CONDITIONING, INC. | HSP | P | 02/02/2023 | TAB REPORT RECEIVED SEE IMAGES / QUESTIONING VALUE LISTED FOR SUPPLY#2 OFF FUR-5 PLANS REFLECT 300 CFM DESIGN, TESTED VALUE EXCEEDS +/- 10 % PERMITTED DEVIATION / NEED REVISED APPROVED TAB REPORT OR ENGINEER APPROVED TAB REPORT / REVISED APPROVED PLANS ON FILE / | WHITNEYH | WHITNEYH | | HSP | P | 7651842 |
MORNING STAR ELEVATOR, LLC. | HE= | P | 02/01/2023 | Remove floor drain from elevator machineroom, reroute a/c condensate drain line, remove fire sprinkler from elevator pit, install car top stop switch at upper landing side. Photos acceptable. | ERIC | ERIC | | HE= | P | 7650418 |
LANDMARK PLUMBING AND HEATING, INC. | H= | C | 12/14/2022 | APPROVED WATER HEATER SUBMITTAL SEE IMAGES. GAS FINAL---------------------COMPLETE. | TREVORH | TREVORH | | H= | C | 7610332 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 12/12/2022 | STILL NEED REVISED APPROVED PLANS / FOLLOWING REVIEW OF TAB REPORT, IT APPEARS THAT THE PLAN SPLICE WAS UTILIZED FOR THE TAB REPORT AS MULTIPLE READINGS FOR F-2, F-3, F-4 ,F-6, AND F-7 SYSTEMS DO NOT MATCH PPRBD APPROVED PLAN SET ON FILE / NEED REVISED APPROVED PLANS FOR TAB REPORT COMPARISON, REVISED TAB REPORT MATCHING APPROVED PLAN SET ON FILE, OR ENGINEER APPROVED TAB REPORT / | WHITNEYH | WHITNEYH | | H= | P | 7608718 |
LANDMARK PLUMBING AND HEATING, INC. | H= | P | 12/12/2022 | FINAL PENDING: NEED ENGINEER APPROVED SUBMITTAL OR REVISED APPROVED PLANS WITH UPDATED EQUIPMENT SCHEDULE REFLECTING RHEEM TANK-LESS WATER HEATER INSTALLED IN PLACE OF STATE TANK-LESS WATER HEATER LISTED ON APPROVED PLANS /
| WHITNEYH | WHITNEYH | | H= | P | 7607924 |
LANDMARK PLUMBING AND HEATING, INC. | HV | C | 12/12/2022 | FINAL VENT CONNECTIONS TO WATER HEATER OK / | WHITNEYH | WHITNEYH | | HV | C | 7607911 |
FIREPLACE WAREHOUSE | H= | C | 12/12/2022 | FIREPLACE FINAL OK / | WHITNEYH | WHITNEYH | | H= | C | 7607876 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 12/09/2022 | MECHANICAL FINAL PENDING---------------------PLAN SPLICE, AND VERIFICATION OF THE TEST AND BALANCE REPORT. | TREVORH | TREVORH | | H= | P | 7606854 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 12/08/2022 | TAB REPORT RECEIVED, IN REVIEW / WILL UPDATE NOTES WHEN REVIEW IS COMPLETE / STILL NEED ON-SITE INSPECTION TO REVIEW ITEMS NOTED DURING INSPECTION ON 7/22/22 / | WHITNEYH | WHITNEYH | | H= | P | 7604447 |
LANDMARK PLUMBING AND HEATING, INC. | HC | C | 10/25/2022 | RELEASE METER | TREVORH | TREVORH | | HC | C | 7561613 |
LANDMARK PLUMBING AND HEATING, INC. | HI | C | 10/25/2022 | GAS PIPING PER PLAN SPLICE DATED 10-23-22 | TREVORH | TREVORH | | HI | C | 7561612 |
LANDMARK PLUMBING AND HEATING, INC. | HV | P | 09/02/2022 | CONTRACTOR WILL NEED TO ADD VENTING TO THEIR SCOPE OF WORK. WILL NEED TO SEE AN UPDATED EQUIPMENT SCHEDULE ON PLANS OR AN ENGINEERS APPROVED SUBMITTAL FOR THE RHEEM WATER HEATER. 5 PSIG TEST OK BY FINAL WILL VERIFY CONNECTION TO WATER HEATER. | TREVORH | TREVORH | | HV | P | 7505449 |
LANDMARK PLUMBING AND HEATING, INC. | HI | P | 08/15/2022 | STILL NEED PLAN SPLICE FOR NEW METER LOCATION AND GAS PIPING ROUTING CAN RELEASE METER WHEN SPLICE IS ON FILE. 10 LB TEST OK FOR 3/4'' LINE FOR NEW FIRE PLACE LOCATION. | TREVORH | TREVORH | | HI | P | 7482805 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 07/22/2022 | STILL NEED PREVIOUSLY STATED PLAN CORRECTIONS FROM INSPECTION DATED 3-8-22 NOW WILL ALSO NEED TO INCLUDE DUCT SERVING OFFICES 1 THROUGH 5 CHANGING TO EXPOSED WITH SIDE WALL DIFFUSER. NEED LADDER TO VERIFY F-7 ABOVE STORAGE ROOM, WILL NEED TO VEIRFY DUCT DETECTOR ON F-7 PER NOTE 11 ON PLANS WILL NEED TO SEE AUDIO AND VISIBLE REMOTE INDICATORS FOR EACH DUCT DETECTORS UNLESS BUILDING IS MONITORED BY A SUPERVISORY PANEL SEE SECTION 606.4.1 OF THE 2015 IMC EXCEPTION # 2 , MISSING GRILLE'S IN BOTH REST ROOMS, VENTLESS KITCHEN HOOD HAS NOT BEEN INSTALLED YET. AT NEXT INSPECTION WILL WALK EXTERIOR . BY FINAL WILL NEED TO SEE TEST AND BALANCE REPORT . | TREVORH | TREVORH | | H= | P | 7456971 |
LANDMARK PLUMBING AND HEATING, INC. | HI | R | 06/17/2022 | NEED LINE ON PRESSURE TEST - NEED INSTALL MANUAL FOR FIREPLACE TO VERIFY SERVICE ACCESS TO GAS VALVE AND POWER VENTER - STOPPED INSPECTION | JERRYF | JERRYF | | HI | R | 7415425 |
FIREPLACE WAREHOUSE | HV | P | 06/09/2022 | POWER VENTED MAIN LEVEL FIREPLACE CLEARANCE TO COMBUSTIBLES AND VENT TERMINATION OK / NON-COMBUSTIBLE MATERIALS INSTALLED,OK / GAS HAS NOT BEEN CONNECTED, BY FINAL WILL NEED TO SEE ACCESS DOOR FOR THE SERVICE PANEL OF THE POWER VENT FAN, | TREVORH | TREVORH | | HV | P | 7405641 |
RIAL HEATING AND AIR CONDITIONING, INC. | HRP | P | 04/05/2022 | PRESSURE TEST FOR 8 LINE SETS OK, AT FINAL WILL VERIFY DRYER AND CONDENSER INSTALL. | TREVORH | TREVORH | | HRP | P | 7326976 |
LANDMARK PLUMBING AND HEATING, INC. | HI | P | 03/23/2022 | (CANNOT RELEASE METER UNTIL SPLICE HAS BEEN APPROVED) PIPING INSTALL DOES NOT MATCH DRAWINGS ON FILE, WILL NEED PLAN SPLICE FOR NEW METER LOCATION ,SIZE CHANGES AND PIPE ROUTING. 10 LB TEST OK. | TREVORH | TREVORH | | HI | P | 7311627 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 03/23/2022 | (DO NOT DRYWALL STORAGE ROOM INTERIOR ON THE MAIN LEVEL AS THERE IS A 4'' ROUND EXHAUST IN THE STUD CAVITY ) ABOVE CEILING ROUGH CONFERENCE ROOM LATERAL TIE IN TO LINEAR SLOT DIFFUSERS OK/ | TREVORH | TREVORH | | HD | P | 7311611 |
LANDMARK PLUMBING AND HEATING, INC. | HV | P | 03/18/2022 | WATER HEATER CONCENTRIC LOCATION AND INSTALL OK, WILL NEED TO VERIFY CONTINUOUS VENTING WHEN READY. | TREVORH | TREVORH | | HV | P | 7306759 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 03/17/2022 | MAIN LEVEL DUCT ROUGH-)---- REST ROOM EXHAUST CONNECTIONS AND TERMINATED THROUGH ROOF OK. | TREVORH | TREVORH | | HD | P | 7305594 |
LANDMARK PLUMBING AND HEATING, INC. | HV | P | 03/17/2022 | NO ONE FROM LANDMARK WAS ONSITE, 4'' CONCENTRIC THROUGH ROOF NEED WATER HEATER INSTALLATION INSTRUCTIONS TO VERIFY VENTING AND TERMINATION CLEARANCES. | TREVORH | TREVORH | | HV | P | 7305573 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 03/11/2022 | STILL NEED A FIRE PLACE CONTRACTOR ATTACHED TO THE PERMIT, CONTRACTOR WILL NEED TO REQUEST AN HRP INSPECTION FOR ALL BRAZED LINE SETS, LOWER LEVEL MECHANICAL ROUGH OK, OK TO WRAP. STILL NEED TO VERIFY UPPER LEVEL INCLUDING OFFICES WHEN READY. | TREVORH | TREVORH | | HD | P | 7298925 |
RIAL HEATING AND AIR CONDITIONING, INC. | HV | P | 03/11/2022 | DIRECT VENTING FOR ALL REMAINING FURNACES ALL OK, AT FINAL WILL VERIFY ALL VENT TERMINATIONS. | TREVORH | TREVORH | | HV | P | 7298902 |
RIAL HEATING AND AIR CONDITIONING, INC. | HV | P | 03/08/2022 | F-5 DIRECT VENT FURNACE VENTING INSTALLED PER INSTALLATION INSTRUCTIONS, WILL NEED TO VERIFY THE REMAINING FURNACES WHEN READY. | TREVORH | TREVORH | | HV | P | 7294015 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 03/08/2022 | STILL NEED PREVIOUSLY NOTED PLAN SPLICE ALSO TO INCLUDE DUCT ROUTING CHANGES AND OUTSIDE AIR TERMINATION LOCATIONS AND NEED MECHANICAL SCHEDULE LISTING FURNACE MODELS . DUCT ROUGH PLAN SHEET M 2.1 SUPPLY AND RETURN AIR RISERS FROM MECHANICAL ROOMS TO UPPER LEVEL OK, F-1,2 AND 3 SUPPLY DUCT AND ROUND LATERALS OK, OK TO WRAP, OUTSIDE AIR WITH CONTROL DAMPERS OK, OK TO WRAP. PLAN SHEET M 2 SUPPLY TRUNK LINE FROM F-7 OK, OK TO WRAP. STILL NEED TO SEE ALL EXPOSED DUCTING WHEN READY. | TREVORH | TREVORH | | HD | P | 7294009 |
RIAL HEATING AND AIR CONDITIONING, INC. | HSP | P | 02/16/2022 | ON SITE CONSULTATION ON FURNACE VENTING THROUGH THE SIDE WALL, TERMINATIONS PER THE MANUFACTURES INSTRUCTIONS. PLANS WILL NEED TO REPRESENT THE CHANGE FROM ROOF TO SIDE WALL. CONTRACTOR WILL REQUEST AN HV INSPECTION WHEN READY. | TREVORH | TREVORH | | HSP | P | 7272688 |
LANDMARK PLUMBING AND HEATING, INC. | P= | C | 12/14/2022 | | LEE | LEE | | P= | C | 7610836 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 12/14/2022 | ENTRY FOR COPPER SINK SPECS ( SEE IMAGES ) | LEE | LEE | | P= | P | 7610385 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 12/12/2022 | WAIVED TRIP-FEE -- STILL HAVE SIDE CLEARANCE ISSUE WOMENS RESTROOM -- ATTACH COPPER LAV SPECS TO NEXT INSPECTION REQUEST | LEE | LEE | | P= | P | 7607994 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | C | 12/12/2022 | | LEE | LEE | | PTO | C | 7607977 |
LANDMARK PLUMBING AND HEATING, INC. | PWO | C | 12/12/2022 | | LEE | LEE | | PWO | C | 7607968 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 12/02/2022 | STILL HAVE SIDE CLEARANCE ISSUE AT UPPER WOMENS W/C -- NEED HIGH LOOPS AT BOTH DISHWASHERS -- NEED LISTINGS FOR COPPER SINKS -- INSTALL STRAINER ON FLOOR DRAIN NEAR ELEVATOR ( USED FOR MINI-SPLIT CONDENSATE ) -- OTHER OK | LEE | LEE | | P= | P | 7598531 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 11/21/2022 | revise plans as previously noted for PB inspection, install partitions at men's restroom, need listings for copper vessel sinks, lacks proper side clearance at upstairs women's toilet, install dishwashers to verify hi- loops and thread sealant for aav at sink, lacks proper height for upstairs men's toilet, need hammer arrestor at basement dishwasher and proper air gap at relief port piping at backflow for humidifier. | TAYLOR | TAYLOR | | P= | P | 7588978 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 06/30/2022 | CORRECTIONS MADE, RESEARCHING ELEVATOR F/D ISSUE -- REST OK -- 7-1-22 ADDED NOTE: FLOOR DRAIN HAS TO BE ELIMINATED AT ELEVATOR EQUIPMENT ROOM BY FINAL | LEE | LEE | | PTO | P | 7431412 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 01/03/2022 | need to see vent penetrations, need toilet flanges set and anchored upstairs and down, need water pipe insulation, will need to conduct more research into floor drain by elevator, need engineer letter for water main run over head plans call for it to run under ground see pwo inspection, correction made at sleeve thru wall for water main, rest ok | JOSEPHD | JOSEPHD | | PTO | P | 7226533 |
LANDMARK PLUMBING AND HEATING, INC. | PWO | P | 10/01/2021 | core hole thru foundation needs to be 2 times pipe diameter, need plans to reflect location of stub change and pipe now being run over head not under floor, rest ok note: pre-existing well | JOSEPHD | JOSEPHD | | PWO | P | 7127514 |
LANDMARK PLUMBING AND HEATING, INC. | PB | C | 09/16/2021 | Added Floor Drain To Elevator / Re- Routed 4" To Mechanical Room Because Of Stem Wall / Changed Wall Clean Out @ Mechanical Room To Floor Clean Out / No Trap Primers / Will Be Trap Seal / Splice Plans To Reflect All Changes In PB By Final/ Note: OK / 3' Need To HAcve Accessible Clean Outs By Final | TRAVISR | TRAVISR | | PB | C | 7109684 |
RIAL HEATING AND AIR CONDITIONING, INC. | XMS | P | 01/23/2023 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Layout, backgrounds, sheet notes and schedules revised | JUSTINC | JUSTINC | | XMS | P | 7641849 |
EL PASO ELECTRIC, LLC. | XES | P | 01/23/2023 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised power, lighting and schedules. | BERTHA | BERTHA | | XES | P | 7641546 |
CMG CORP | XBS | T | 01/23/2023 | PAID (REC#1928298): PLAN SPLICE FEE: $50 by: DANM for Construction: Minor floor and reflected ceiling revisions | DANM | DANM | | XBS | T | 7641436 |
RIAL HEATING AND AIR CONDITIONING, INC. | XMS | T | 10/24/2022 | PAID (REC#1910433): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised gas | JUSTINC | JUSTINC | | XMS | T | 7559868 |
CMG CORP | XBS | T | 02/01/2022 | PAID (REC#1840667): PLAN SPLICE FEE: $50 by: DANM for Construction: Red-W floor trusses changed to engineered trusses; wall listed assembly revised | DANM | DANM | | XBS | T | 7256503 |
CMG CORP | XBS | T | 01/26/2022 | PAID (REC#1839365): PLAN SPLICE FEE: $50 by: DANM for Construction: Deferred log truss engineering | DANM | DANM | | XBS | T | 7251183 |