BLUE RIDGE CONTRACTORS, INC. | B= | C | 02/05/2024 | Stamped welding letter on file | PAULP | PAULP | | B= | C | 7986533 |
BLUE RIDGE CONTRACTORS, INC. | B= | P | 01/18/2024 | Spoke with rep by phone to provide stamped welding and steel observation report per S1 Roof Plan Will schedule with site visit -- Schedule a new Building Final when above items are complete. | PAULP | PAULP | | B= | P | 7971112 |
BLUE RIDGE CONTRACTORS, INC. | B= | P | 01/18/2024 | Welding observation on file / site inspection for Final -- Schedule a new Building Final when above items are complete. | PAULP | PAULP | | B= | P | 7970631 |
WIGGINS, INCORPORATED | E= | C | 01/08/2024 | AHU-2 125A ok / #2 CU and raceway ok / | MIGUEL | MIGUEL | | E= | C | 7962624 |
WIGGINS, INCORPORATED | EE | P | 11/14/2023 | | RITA | RITA | | EE | P | 7918507 |
AES MECHANICAL SERVICES GROUP, INC. | H= | C | 12/19/2023 | Received photo of labeled AHU-2 (SEE IMAGES). MECHANICAL CONTRACTOR COMPLETE. | PAULO | PAULO | | H= | C | 7948337 |
AES MECHANICAL SERVICES GROUP, INC. | H= | P | 12/18/2023 | Received Test & Balance Report (ACCEPTED). FINAL PENDING-- AHU-2 LABELED (MAY USE PERMANENT TAG OR PAINT /MAY ATTACH CLEAR PHOTOS TO PERMIT AND RECALL FOR INSPECTION). | PAULO | PAULO | | H= | P | 7947076 |
AES MECHANICAL SERVICES GROUP, INC. | H= | P | 12/15/2023 | Final pending- Label AHU-2 and TAB report | SEANM | SEANM | | H= | P | 7945987 |
AES MECHANICAL SERVICES GROUP, INC. | H= | P | 12/15/2023 | FINAL PENDING-- REMOVE FURNACE FROM SCOPE OF WORK, LABEL AHU (AHU-2), TEST & BALANCE REPORT. | PAULO | PAULO | | H= | P | 7945773 |
AES MECHANICAL SERVICES GROUP, INC. | HC | C | 12/15/2023 | ADDED 800K TO LOAD (OUTSIDE CONNECTION). | PAULO | PAULO | | HC | C | 7945772 |
AES MECHANICAL SERVICES GROUP, INC. | HI | C | 12/15/2023 | 60 lb. test ok 10 lb. test ok. Note / All gas installed per plans / Medium labels applied. | PAULO | PAULO | | HI | C | 7945771 |
AES MECHANICAL SERVICES GROUP, INC. | H= | T | 12/13/2023 | PAID (REC#2016756) AFTER-HOURS INSPECTION: $200 From: JANE Per Whitney | JANE | JANE | | H= | T | 7944571 |
AES MECHANICAL SERVICES GROUP, INC. | HE | L | 12/13/2023 | Renewed for No Fee at 12/13/2023 2:57:11 PM | JANE | JANE | | HE | L | 7944568 |
AES MECHANICAL SERVICES GROUP, INC. | HSP | P | 02/15/2023 | PERMITS MUST BE OBTAINED FOR BUILDING & ELECTRICAL PRIOR TO NEXT MECHANICAL INSPECTION. | PAULO | PAULO | | HSP | P | 7662266 |
AES MECHANICAL SERVICES GROUP, INC. | H= | P | 02/14/2023 | NOT READY. CONTRACTOR TO ADDRESS THE FOLLOWING-- PERMITS TO BE OBTAINED FOR BUILDING (NEW CURB), & ELECTRICAL ( NEW DEDICATED LINE), CHANGE SCOPE OF WORK FROM FURNACE TO AHU & 1 GAS OUTLET, LABEL AHU, TEST & BALANCE REPORT. Note / AHU installation ok. (Smoke Duct Detectors/Overflow Switch). | PAULO | PAULO | | H= | P | 7661863 |
AES MECHANICAL SERVICES GROUP, INC. | HI | P | 02/14/2023 | NO TEST AT TIME OF INSPECTION. CONTRACTOR TO ADDRESS THE FOLLOWING-- 60 lb. TEST IS REQUIRED FOR ALL WELDED JOINTS & 10 lb. TEST FOR THREADED, MEDIUM PRESSURE STICKERS EVERY 10' FOR ENTIRE RUN OF NEW GAS LINE. Note / All gas installed per plans (INSPECTION DONE FROM CONTRACTORS PHONE WITH RBD APPROVED STAMPED PLAN) / Supports ok / Final connection ok / | PAULO | PAULO | | HI | P | 7661860 |
AES MECHANICAL SERVICES GROUP, INC. | HSP | C | 01/03/2023 | HAD DISCUSSION WITH CONTRACTOR (Ousman Taal/AES MECHANICAL) ABOUT SCOPE OF WORK, CONTRACTOR STATES THAT WORK DONE IS NEW AND NOT A CHANGE OUT OF AN EXISTING RTU. (ALL NEW WORK DONE REQUIRES ENGINEERED PLANS AND PERMITS FOR BUILDING (NEW CURB), MECHANICAL (NEW RTU & GAS) & ELECTRICAL ( NEW DEDICATED LINE) SUBMITTED TO PPRBD PLAN REVIEW & APPROVAL, CHANGE SCOPE OF WORK FROM FURNACE TO RTU & GAS OUTLET. | PAULO | PAULO | | HSP | C | 7624251 |