SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | C | 07/28/2023 | All other required Final inspections are complete. (This is a computer generated result) | BOBF | BOBF | | B= | C | 7811674 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | P | 07/24/2023 | pending completion of other required inspections, building okay. Additional Inspections Required (computer generated): External Agency Inspection FHZ= by FIREDEPT is not Completed yet, COLORADO ELECTRICAL SYSTEMS, LLC Electrical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 7806354 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | P | 05/17/2023 | pending completion of other required inspections, final on 2nd floor okay -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection FHZ= by FIREDEPT is not Completed yet, BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, COLORADO ELECTRICAL SYSTEMS, LLC Electrical Final Inspection is not Completed yet, PIPE LINE SPECIALTIES INC. Mechanical Final Inspection is not Completed yet, PIPE LINE SPECIALTIES INC. Plumbing Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 7747210 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 04/11/2023 | drywall install per U 419 on 2nd floor okay | BOBF | BOBF | | BFR | P | 7712486 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 03/28/2023 | Above lid in patient rooms on 2nd floor OK | DAKOTAB | DAKOTAB | | BFR | P | 7700320 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | R | 03/22/2023 | field cancelled per site rep Lynn | LONNYS | LONNYS | | BFR | R | 7694490 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | R | 03/21/2023 | not ready for inspection | LONNYS | LONNYS | | BFR | R | 7694129 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 02/09/2023 | 2ND FLOOR BALANCE OF WALL AND SOFFIT FRAMING / interior light gauge steel wall framing OK
2ND FLOOR GYP ATTACHMENT / non IBC gyp attachment OK - still need to inspect 1 hour fire barrier gyp attachment and continuity in C2212e when ready
3RD FLOOR FRAME / interior light gauge steel wall and soffit framing OK pending other required inspections | LONNYS | LONNYS | | BFR | P | 7658398 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 11/07/2022 | LEVEL 2 -- site visit to observe project progress / walked rough framing and discussed MEP inspections, rated assemblies, 3rd party inspections for structural steel welding and bolting, 3rd party repairs for structural steel fire protection, accessibility | LONNYS | LONNYS | | BFR | P | 7575321 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 10/11/2022 | site visit with site rep to observe progress / reviewed required PPRBD inspection to include rated assemblies, accessibility and 3rd party inspections | LONNYS | LONNYS | | BFR | P | 7546964 |
COLORADO ELECTRICAL SYSTEMS, LLC | E= | C | 07/28/2023 | FIRE ALARM INSPECTION: | RANDY | RANDY | | E= | C | 7811673 |
BIBLE ELECTRIC, INC. | E= | C | 07/17/2023 | | AARONR | AARONR | | E= | C | 7799575 |
BIBLE ELECTRIC, INC. | ER | P | 06/09/2023 | third floor patient rooms drop ceilings and headwalls | RANDY | RANDY | | ER | P | 7767734 |
BIBLE ELECTRIC, INC. | ER | P | 06/01/2023 | ER OK ----- 3RD FLOOR BATHROOMS ------ | GREGM | GREGM | | ER | P | 7759953 |
BIBLE ELECTRIC, INC. | E= | P | 05/12/2023 | all finals except nursery | RANDY | RANDY | | E= | P | 7743363 |
BIBLE ELECTRIC, INC. | E= | P | 05/01/2023 | all rooms but nurse station, BIO, and need wiremold installed | RANDY | RANDY | | E= | P | 7731893 |
BIBLE ELECTRIC, INC. | E= | P | 05/01/2023 | all rooms but nurse station, BIO, and need wiremold installed | RANDY | RANDY | | E= | P | 7731894 |
BIBLE ELECTRIC, INC. | ER | R | 04/10/2023 | desk rough, last corridor ceiling, wall rough---will put room numbers next inspection | RANDY | RANDY | | ER | R | 7711985 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 04/10/2023 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 7711885 |
BIBLE ELECTRIC, INC. | ER | P | 03/30/2023 | Rooms C2313 --- C2317 --- C2309 --- C2305 --- C2301 above ceilings OK. --- Room C2319 hard lid OK. --- Corridor C2-9 --- C2-14 --- C2-15 above ceilings OK. | AARONR | AARONR | | ER | P | 7703404 |
BIBLE ELECTRIC, INC. | ER | P | 03/17/2023 | patient bed ceilings | RANDY | RANDY | | ER | P | 7691284 |
BIBLE ELECTRIC, INC. | ER | P | 02/02/2023 | all walls minus nurse station and headwalls | RANDY | RANDY | | ER | P | 7651549 |
BIBLE ELECTRIC, INC. | ER | P | 01/25/2023 | 2nd fl headwalls ok | RANDY | RANDY | | ER | P | 7644401 |
BIBLE ELECTRIC, INC. | ER | P | 01/09/2023 | ok to proceed with headwall rough | RANDY | RANDY | | ER | P | 7629228 |
BIBLE ELECTRIC, INC. | ER | R | 01/04/2023 | called at 8:45, called at 9:42 no answer had to keep going | RANDY | RANDY | | ER | R | 7624834 |
BIBLE ELECTRIC, INC. | ER | P | 11/28/2022 | all walls minus headwalls | RANDY | RANDY | | ER | P | 7593298 |
BIBLE ELECTRIC, INC. | ER | P | 11/14/2022 | only walls left are bathrooms and headwalls | RANDY | RANDY | | ER | P | 7582903 |
BIBLE ELECTRIC, INC. | ER | P | 11/02/2022 | west walls except headwalls and bathrooms------ exterior walls ok------marked on plans in GCs office----- | RANDY | RANDY | | ER | P | 7570077 |
BIBLE ELECTRIC, INC. | ER | P | 10/28/2022 | exterior walls need correct box brackets | RANDY | RANDY | | ER | P | 7566096 |
PIPE LINE SPECIALTIES INC. | H= | C | 07/19/2023 | FINAL TEST AND BALANCE REPORT RECEIVED SEE IMAGES. THERMOSTAT LOCATIONS PER PLAN MECHANICAL FINAL---------------------- COMPLETE | TREVORH | TREVORH | | H= | C | 7801829 |
PIPE LINE SPECIALTIES INC. | HD | P | 06/20/2023 | ABOVE CEILING FLEX AND REGISTERS INSTALLED PER PLAN BY FINAL TEST AND BALANCE REPORT, THERMOSTAT LOCATIONS | TREVORH | TREVORH | | HD | P | 7776818 |
PIPE LINE SPECIALTIES INC. | HD | P | 06/08/2023 | (3 RD FLOOR) UPDATED PICTURES OF DUCT BEFORE WRAP UPLOADED SEE IMAGE: OK TO ATTACH PICTURES OF DUCT WORK SEALANT THAT WAS INSULATED PRIOR TO INSPECTION TO NEXT INSPECTION REQUEST (DUCT ROUGH) PLAN SHEET M133 MAIN TRUNK LINE AND ROUND LATERAL RUN OUTS FOR VAV'S # 14,16,18,AND 20, OK, OK TO WRAP NEED TO VERIFY NEW DUCTING ADDED NEAREST THE ELEVATORS WHEN READY. | TREVORH | TREVORH | | HD | P | 7766193 |
PIPE LINE SPECIALTIES INC. | HD | P | 06/07/2023 | OK TO ATTACH PICTURES OF DUCT WORK SEALANT THAT WAS INSULATED PRIOR TO INSPECTION TO NEXT INSPECTION REQUEST (DUCT ROUGH) PLAN SHEET M133 MAIN TRUNK LINE AND ROUND LATERAL RUN OUTS FOR VAV'S # 14,16,18,AND 20, OK, OK TO WRAP NEED TO VERIFY NEW DUCTING ADDED NEAREST THE ELEVATORS WHEN READY. | TREVORH | TREVORH | | HD | P | 7765391 |
PIPE LINE SPECIALTIES INC. | HWP | P | 06/07/2023 | PLAN SHEET MP133 100 LB TEST FOR 4 VAV'S HWS/HWR OK, OK TO INSULATE | TREVORH | TREVORH | | HWP | P | 7765379 |
PIPE LINE SPECIALTIES INC. | H= | P | 05/18/2023 | (PARTIAL FINAL 2 ND FLOOR, OK.) BY FINAL COMPLETION WILL NEED TO VERIFY ALL REQUIREMENTS OF PLAN SHEET M620 HAVE BEEN MET. 2 ND FLOOR TEST AND BALANCE REPORT HAS BEEN SUBMITTED AND RECEIVED BY FINAL COMPLETION WILL NEED THE ENGINEER PROVIDE A STAMPED LETTER ACCEPTING THE LOW RETURN AIR VALUES. THE 3RD FLOOR PORTION OF THIS PERMIT IS ON GOING AND WILL INSPECT WHEN READY. | TREVORH | TREVORH | | H= | P | 7747653 |
PIPE LINE SPECIALTIES INC. | H= | P | 05/15/2023 | 2 ND FLOOR ALL MECHANICAL ITEMS COMPLETE MINUS THE THE TEST AND BALANCE REPORT 3RD FLOOR HAS NOT STARTED AT THIS TIME 3 RD FLOOR WILL NEED TO BE COMPLETED BEFORE PERMIT CAN BE CLOSED | TREVORH | TREVORH | | H= | P | 7744018 |
PIPE LINE SPECIALTIES INC. | HD | P | 03/28/2023 | 2 ND FLOOR ONLY , PLAN SHEET M122 (BDA PAGE 46) 2ND FLOOR, ABOVE CEILING FLEX AND REGISTERS FOR BOTH CORRIDORS OK, AND ROOMS C2313,C2317,C2311,C2301 ALSO OK. STILL NEED TO VERIFY ALL REMAINING HARD LID FLEX AND CANS WHEN READY. | TREVORH | TREVORH | | HD | P | 7700758 |
PIPE LINE SPECIALTIES INC. | HD | P | 03/23/2023 | PLAN SHEET M122 (BDA PAGE 46) 2ND FLOOR, ABOVE CEILING FLEX AND REGISTERS FOR ALL PATIENT ROOMS INCLUDING NURSES STATION OK,///////EXCEPT ISOLATION ROOM VERIFY WHEN READY./////// 2 FIRE DAMPER FRAMING AND DAMPER INSTALL OK IN CLEAN STORAGE 1 DAMPER STILL TO INSPECT IN SAME ROOM. | TREVORH | TREVORH | | HD | P | 7696801 |
PIPE LINE SPECIALTIES INC. | HD | P | 02/21/2023 | LEVEL 3: RESPITE ROOM C3222 BOTH FIRE DAMPERS OK FOR FRAME, ANNULAR SPACE, ANGLES AND BREAK AWAY CONNECTIONS. / SUPPLY AND RETURN OK FOR ROOMS 3320, 3318 AND 3316. EXHAUST OK FOR ROOMS 3320, 3318, 3315 AND 3314 /
LEVEL 2: FIRE DAMPER FRAMING OK ONLY FOR ROOM 2212e /
| MATTM | MATTM | | HD | P | 7666636 |
PIPE LINE SPECIALTIES INC. | HWP | P | 02/10/2023 | 2ND FLOOR HYDRONICS TO ALL VAV's INSTALLED PER PLAN. 100 LB TEST OK / | MATTM | MATTM | | HWP | P | 7659006 |
PIPE LINE SPECIALTIES INC. | HD | P | 12/29/2022 | CONTRACTOR STILL PROCEEDING WITH PLANS THAT HAVE NOT BEEN APPROVED BY PPRBD, (PLAN SHEET M122) BDA PAGE 46 (DUCT ROUGH) ALL EXHAUST DUCTING ROUGHED IN ///////EXCEPT ROOM C2314 NOT COMPLETED YET////// FIRE DAMPER NOT INSTALLED YET AT IDF ROOM, NO 3 RD FLOOR WORK AT THIS TIME. | TREVORH | TREVORH | | HD | P | 7622284 |
PIPE LINE SPECIALTIES INC. | HSP | P | 12/09/2022 | STILL NEED PLAN SPLICE REPRESENTING ALL ADDED FIRE DAMPERS AND DUCT CHANGES., PER CONVERSATION WITH CONTRACTOR ON SITE SOME WALL RATINGS MAY BE CHANGING THIS WILL NEED TO BE APPROVED BY BUILDING. (DUCT ROUGH) (BDA PAGE 46) ROOM C2305 TO ADDED FIRE DAMPERS FOR THE 18 X 14 DUCT PASSING THROUGH ROOM C2305 OK FOR RETAINING ANGLE BREAK AWAY CONNECTION OK , FIRE DAMPER AT VAV 2305 OK FOR RETAINING ANGLE. WILL VERIFY BREAK AWAY CONNECTION WHEN READY. | TREVORH | TREVORH | | HSP | P | 7606720 |
PIPE LINE SPECIALTIES INC. | HD | P | 12/07/2022 | PLANS ON SITE DO NOT MATCH APPROVED SET STILL NEED PREVIOUSLY MENTIONED PLAN SPLICE (FIRE DAMPER) POSTPARTUM ROOM C2302 FIRE DAMPER FRAMING/ANNULAR SPACING OK, VERIFY RETAINING ANGLE AND BREAK AWAY CONNECTIONS WHEN READY. (DUCT ROUGH) ALL LOW PRESSURE SUPPLY AIR IN THE EAST POSTPARTUM ROOMS OK, OK TO WRAP. VERIFY VAV AND EXHAUST WHEN READY. | TREVORH | TREVORH | | HD | P | 7603430 |
PIPE LINE SPECIALTIES INC. | HD | P | 11/22/2022 | PLAN SPLICE NEEDED FOR THE ADDITION OF FIRE DAMPERS,DUCT ROUTING CHANGES AND DUCT SIZING NOT SHOWN ON PLANS, PLAN SHEET M 122 (BDA PAGE 46 ) FIRE DAMPER INSTALL ROOM C2319 SUPPLY AND RETURN DAMPERS OK, OK FOR RETAINING ANGLE, ADDED 18 X 14 FIRE DAMPER FRAMING OK, DAMPER INSTALL AND BREAK AWAY OK, (DUCT ROUGH) ALL SUPPLY MAINS AND ROUND LATERAL RUN OUTS FROM NURSES STATION AND ALL THE WAY EAST OK, OK TO WRAP. AT NEXT INSPECTION REQUEST WILL NEED TO SEE FIRE DAMPER FRAMING COMPLETED FOR THE 18 X 14 DUCT PENETRATING ROOM C2305 ADJACENT TO THE SERVER ROOM. WILL VERIFY DUCT ROUGH IN ALL POSTPARTAM ROOMS | TREVORH | TREVORH | | HD | P | 7590392 |
PIPE LINE SPECIALTIES INC. | HD | P | 11/09/2022 | PLAN SPLICE NEEDED FOR THE ADDITION OF FIRE DAMPERS AND DUCT SIZING NOT SHOWN ON PLANS, PLAN SHEET M 122 (BDA PAGE 46 ) STORAGE ROOM C 2300 ADDING FIRE DAMPER TO EXISTING 46 X 22 RETURN AIR TRUNK LINE FRAMING AND ANNULAR SPACING OK VERIFY RETAINING ANGLE AND BREAK AWAY WHEN READY ALSO PROVIDE PICTURES OF ANGLE AND BREAK AWAY CONNECTION ON OCCUPIED SIDE OF WALL , REVIEWED PICTURES ON SITE WITH FOREMAN. | TREVORH | TREVORH | | HD | P | 7577562 |
PIPE LINE SPECIALTIES INC. | HD | P | 11/03/2022 | PLAN SHEET M 122 (BDA PAGE 46 ) STORAGE ROOM C 2300 ADDING FIRE DAMPER TO EXISTING 46 X 22 RETURN AIR TRUNK LINE FRAMING AND ANNULAR SPACING OK VERIFY RETAINING ANGLE AND BREAK AWAY WHEN READY ALSO PROVIDE PICTURES OF ANGLE AND BREAK AWAY CONNECTION ON OCCUPIED SIDE OF WALL , SAME CONDITION FOR 32 X 20 LOCATED IN ROOM C 2323., 16 X 10 FIRE DAMPER FRAMING OK IN ROOM C 2300 VERIFY RETAINING ANGLE AND BREAK AWAY ON ROOM SIDE WHEN READY , CORRIDOR SIDE OK. NEED TO VERIFY DUCT ROUTING AND REMAINING FIRE DAMPER FRAMING AT NEXT INSPECTION REQUEST. | TREVORH | TREVORH | | HD | P | 7571725 |
PIPE LINE SPECIALTIES INC. | HSP | P | 10/17/2022 | ON PHONE DISCUSSION WITH MARCUS @ PIPE LINE PERTAINING TO FIRE DAMPER INSPECTION AND OCCUPIED AREAS , DISCUSSED THE POSSIBILITY OF EXCEPTING PICTURES FOR FRAMING , RETAINING ANGLE AND BREAK AWAY . | TREVORH | TREVORH | | HSP | P | 7551975 |
PIPE LINE SPECIALTIES INC. | HSP | P | 10/11/2022 | THERE WILL BE A FORTHCOMING PLAN SPLICE ADDING FIRE DAMPERS (ON SITE DISCUSSION ON FIRE DAMPERS AND THE GREEN HECK FRAMING REQUIREMENTS , ON SITE MEETING PARTICIPANTS WERE Lynn Harrison the G.C site super and pipe lines foreman David Caron. the framing contractor was not present. FIRE DAMPERS ARE THE DFD-150 , DISCUSSED THE ADVANTAGE OF FREQUENT INSPECTIONS . | TREVORH | TREVORH | | HSP | P | 7547213 |
PIPE LINE SPECIALTIES INC. | P= | C | 07/12/2023 | | LEE | LEE | | P= | C | 7795554 |
PIPE LINE SPECIALTIES INC. | P= | P | 05/05/2023 | 2ND FLOOR COMPLETE | LEE | LEE | | P= | P | 7737415 |
PIPE LINE SPECIALTIES INC. | P= | P | 04/26/2023 | 2ND FLOOR OK MINUS BREAK ROOM ICE MACHINE (MISSING) | LEE | LEE | | P= | P | 7727992 |
PIPE LINE SPECIALTIES INC. | PTO | P | 03/27/2023 | 2ND FLOOR FLANGES OK | LEE | LEE | | PTO | P | 7699339 |
PIPE LINE SPECIALTIES INC. | PTO | P | 03/07/2023 | RESPITE RESTROOM COMPLETE -- NEED ALL CLOSET FLANGES | LEE | LEE | | PTO | P | 7679577 |
PIPE LINE SPECIALTIES INC. | PTO | P | 01/31/2023 | 2ND FLOOR & 3RD FLOOR H20 / DWV COMPLETE MINUS " RESPITE " RESTROOM | LEE | LEE | | PTO | P | 7649504 |
PIPE LINE SPECIALTIES INC. | PTO | P | 01/24/2023 | 3RD FLOOR - DWV IN WALLS AND UP TO TIE-INS ROOMS C-3320 AND 3318 OK -- DOMESTIC WATER IN WALLS AND OVERHEAD MAINS C-3314, 3316, 3318 AND 3320 OK | LEE | LEE | | PTO | P | 7643275 |
PIPE LINE SPECIALTIES INC. | PTO | P | 01/17/2023 | REMAINING DWV 2ND FLOOR IS COMPLETE -- STILL NEED ALL 3RD FLOOR PIPING ( UNDERFLOOR, WALLS AND VENTS ) | LEE | LEE | | PTO | P | 7637099 |
PIPE LINE SPECIALTIES INC. | PTO | P | 01/11/2023 | DWV 2ND FLOOR IN WALLS AND OVERHEAD OK ROOMS - C-2302, 2323, 2302 THRU 2312, 2311 AND 2315 --- 2ND FLOOR WATER DISTRIBUTION IN WALLS AND MAINS COMPLETE MINUS COLD WATER TIE-IN | LEE | LEE | | PTO | P | 7632252 |
PIPE LINE SPECIALTIES INC. | PTO | P | 01/09/2023 | DWV ONLY BELOW FLOOR - ROOMS 2302 AND 2304 OK | LEE | LEE | | PTO | P | 7629553 |
PIPE LINE SPECIALTIES INC. | PTO | P | 01/06/2023 | WATER MAINS WEST SIDE AND WATER DIST IN ROOMS C-2300 THRU C-2312 OK PENDING INSULATION -- NO DWV | LEE | LEE | | PTO | P | 7628475 |
PIPE LINE SPECIALTIES INC. | PTO | P | 12/22/2022 | under floor DWV at rooms C2301 and C2319 ok. | TAYLOR | TAYLOR | | PTO | P | 7619259 |
PIPE LINE SPECIALTIES INC. | PTO | P | 12/19/2022 | PHASE 7 -- C-2323 UNDER-FLOOR DWV ONLY - 2- 3" P-TRAPS / VENT OK | LEE | LEE | | PTO | P | 7615344 |
PIPE LINE SPECIALTIES INC. | PTO | P | 12/08/2022 | UNDER-FLOOR DWV FOR SINKS C-2308, 2310 OK -- PHASE 3-4 TIE-INS OK | LEE | LEE | | PTO | P | 7605551 |
PIPE LINE SPECIALTIES INC. | PTO | P | 11/22/2022 | under floor DWV only at rooms 2306 and 2308 ok. | TAYLOR | TAYLOR | | PTO | P | 7590573 |
PIPE LINE SPECIALTIES INC. | PTO | P | 11/15/2022 | UNDERFLOOR DWV ONLY ROOMS 2312 AND 2310 OK | LEE | LEE | | PTO | P | 7584022 |
PIPE LINE SPECIALTIES INC. | PTO | P | 11/01/2022 | PHASE 2 -- UNDER FLOOR DWV ONLY - REST ROOMS C-2316, 2318, 2314 AND 2315 - 2311 SINK OK | LEE | LEE | | PTO | P | 7569359 |
PIPE LINE SPECIALTIES INC. | PTO | P | 10/19/2022 | RE-INSPECTED SHOWER DRAIN 2320 - DESIGN / TEST OK | LEE | LEE | | PTO | P | 7554986 |
PIPE LINE SPECIALTIES INC. | PTO | P | 10/18/2022 | PHASE 1 -- UNDERFLOOR DWV ONLY ROOMS - C-2319, 2324, 2322, 2320, 2318 AND 2309 -- 2320 SHOWER S-TRAPPED -- OTHER ROOMS LISTED OK | LEE | LEE | | PTO | P | 7554117 |
BIBLE ELECTRIC, INC. | XES | P | 04/24/2023 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised panel/circuit number. | BERTHA | BERTHA | | XES | P | 7724970 |
PIPE LINE SPECIALTIES INC. | XMS | T | 04/24/2023 | PAID (REC#1949842) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised exhaust fan schedule | JUSTINC | JUSTINC | | XMS | T | 7724626 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XBS | T | 04/24/2023 | PAID (REC#1949762): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised listing, verified dimensions. | SHELLEY | SHELLEY | | XBS | T | 7724573 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XBS | T | 02/28/2023 | PAID (REC#1937731): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Floor plan revision at nurse team station | SHELLEY | SHELLEY | | XBS | T | 7671873 |
BIBLE ELECTRIC, INC. | XES | P | 02/24/2023 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Added dimmer, added receptacle. | BERTHA | BERTHA | | XES | P | 7669526 |
PIPE LINE SPECIALTIES INC. | XMS | P | 02/23/2023 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Layout and note revisions | JUSTINC | JUSTINC | | XMS | P | 7668347 |
PIPE LINE SPECIALTIES INC. | XPS | T | 02/23/2023 | PAID (REC#1937638): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 3 revisions: Adjusted sheet P434. | SHANEN | SHANEN | | XPS | T | 7668338 |
PIPE LINE SPECIALTIES INC. | XMS | P | 02/06/2023 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Layout revised | JUSTINC | JUSTINC | | XMS | P | 7654185 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XBS | T | 02/06/2023 | PAID (REC#1932011): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Port locations, furred wall at EVS | SHELLEY | SHELLEY | | XBS | T | 7653897 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XBS | T | 02/03/2023 | PAID (REC#1931228): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Minor floor plan revisions, finish details | SHELLEY | SHELLEY | | XBS | T | 7652737 |
BIBLE ELECTRIC, INC. | XES | T | 02/02/2023 | PAID (REC#1940209): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Minor lighting and power revisions. | BERTHA | BERTHA | | XES | T | 7651850 |
PIPE LINE SPECIALTIES INC. | XMS | P | 02/01/2023 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Revised CFM at (2) locations clouded in red for clarity | JUSTINC | JUSTINC | | XMS | P | 7650485 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XBS | T | 02/01/2023 | PAID (REC#1930385): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Multiple plan details to include existing door on nutrish room, cabinetry, dimensions, etc. | SHELLEY | SHELLEY | | XBS | T | 7650468 |
BIBLE ELECTRIC, INC. | XES | T | 01/27/2023 | PAID (REC#1930414): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised power, revised schedules. | BERTHA | BERTHA | | XES | T | 7647331 |
PIPE LINE SPECIALTIES INC. | XMS | P | 01/12/2023 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Revised VAV schedule | JUSTINC | JUSTINC | | XMS | P | 7633807 |
PIPE LINE SPECIALTIES INC. | XPS | P | 01/12/2023 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Delta 2 revisions: Adjusted sheet P434 and P930. | SHANEN | SHANEN | | XPS | P | 7633768 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XBS | T | 01/12/2023 | PAID (REC#1930328): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised details, cabinetry, finishes, equipment | SHELLEY | SHELLEY | | XBS | T | 7633693 |